BLD-Final | 10/18/2011 | 10/19/2011 | 10/19/2011 | A | PASS |
Tom Arcoraci
|
|
|
mike Phone #: ###-####
|
FIRE-Final Inspection | 10/18/2011 | 10/18/2011 | 10/18/2011 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 10/10/2011 | 10/11/2011 | 10/11/2011 | A | PART |
Tom Arcoraci
|
|
|
Mike Phone #: ###-#### ok for temp occ then ok for perm when fire and plumbing sign final
|
FIRE-Final Inspection | 10/10/2011 | 10/11/2011 | 10/11/2011 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the Opticon has been provided for the fire dept access gate on the south side of the building.
|
FIRE-Final Inspection | 10/7/2011 | 10/10/2011 | 10/10/2011 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm permit finaled and all of the exit signs/emergency lights, noted on the city approved plans, repaired. Also one door is marked with exit signage on the plans but not installed in the field. Also the rear fire dept access gate does not have the required 20'-0" clearance between posts.
|
FIRE-Final Inspection | 9/28/2011 | 9/30/2011 | 9/30/2011 | A | FAIL |
Troy Cobbley
|
|
|
This project was not ready for life safety inspection but mike and I went over life safety items that will need addressed such as an "opticon" for the electric gate.
|
BLD-Framing/Rough-in | 9/6/2011 | 9/7/2011 | 9/7/2011 | A | PART |
Jim Sly
|
|
|
mikie - ceiling cover Phone #: ###-#### Grid OK...2nd floor only.
|
BLD-Other | 8/4/2011 | 8/5/2011 | 8/5/2011 | A | PASS |
Tom Arcoraci
|
|
|
Mike Phone #: ###-#### ok 1st floor grid
|
BLD-Framing/Rough-in | 7/13/2011 | 7/14/2011 | 7/14/2011 | A | PASS |
Mike Jordan
|
|
|
Gary Phone #: ###-####. furout channel at demising wall.
|
BLD-Other | 7/8/2011 | 7/13/2011 | 7/13/2011 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 7/6/2011 | 7/12/2011 | 7/12/2011 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 7/7/2011 | 7/8/2011 | 7/8/2011 | A | PASS |
Tom Arcoraci
|
|
|
level 2//Mike Phone #: ###-####
|
BLD-Wall cover | 7/6/2011 | 7/6/2011 | 7/6/2011 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 6/29/2011 | 7/6/2011 | 7/6/2011 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 6/22/2011 | 6/29/2011 | 6/29/2011 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Other | 6/17/2011 | 6/22/2011 | 6/22/2011 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Conference | 6/13/2011 | 6/21/2011 | 6/21/2011 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 6/10/2011 | 6/17/2011 | 6/17/2011 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 6/6/2011 | 6/13/2011 | 6/13/2011 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Framing/Rough-in | 6/9/2011 | 6/10/2011 | 6/10/2011 | A | PASS |
Tom Arcoraci
|
|
|
Mike Phone #: ###-#### ext walls roof and 1st floor int ok
|
BLD-Conference | 5/23/2011 | 6/6/2011 | 6/6/2011 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Framing/Rough-in | 5/20/2011 | 5/23/2011 | 5/24/2011 | P | PASS |
Tom Arcoraci
|
|
|
exterior steel stud framing soffits//Mike Phone #: ###-#### wip ok
|
BLD-Conference | 5/16/2011 | 5/23/2011 | 5/23/2011 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Other | 5/9/2011 | 5/16/2011 | 5/16/2011 | A | PASS |
Tom Arcoraci
|
|
|
wip
|
BLD-Wall cover | 5/6/2011 | 5/9/2011 | 5/9/2011 | A | PASS |
Tom Arcoraci
|
|
|
work in progress spec insp
|