Permit Information
Permit NumberBLD10-02915
StatusFinaled
Name JAYO CONSTRUCTION
Site Address 10572 W BUSINESSPARK LN
Project NameDr. Robert Stevens Dental Offi
Customer Number 
ePlanReviewNo
Description
(DR. ROBERT STEVENS DENTAL OFFICE) Permit is to build out for the first time a 2,495 square foot dentist office building (Building was constructed under BLD07-01108). Approval contingent upon adhering to the approved plans on file. Work to include: [construction of interior non-bearing walls to create a waiting area, a quiet room, a lab, a staff lounge, a consult room, open office area, a mechanical closet, separate sex accessible restrooms, and other accessory spaces,] installation of new accessible doors / hardware, installation of new plumbing, installation of new electrical, installation of new mechanical, and finishes in compliance with chapter 8 of the 2006 IBC. This building is not fire sprinklered. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/28/20114/29/20114/29/2011APASS
DetailsMike Jordan
Cameron Phone #: ###-####. All issues were resolved. Ok for perm. occ.
BLD-Final4/19/20114/20/20114/20/2011PPART
DetailsMike Jordan
Cameron Phone #: ###-####. ok for temp. occ. Needs to provide vertical grab bars in both restrooms, complete firecaulking in 1hr. roof/ceiling assembly and provide code compliant door hardware on employee enterance.
FIRE-Final Inspection4/19/20114/20/20114/20/2011APASS
DetailsTroy Cobbley
life safety passed. Per conversation with the building inspector the west facing exit doors that require the single action hardware will be verified by the building inspector.
FIRE-Final Inspection4/15/20114/19/20114/19/2011PFAIL
DetailsTroy Cobbley
See the correction notice for items completed as the job site. Not all of the items have been addressed.
FIRE-Final Inspection4/11/20114/12/20114/12/2011AFAIL
DetailsTroy Cobbley
Provide for final inspection for BLD11-00265. Provide for testing of the exit discharge lights and exit signs. Repair emergency light in "check out" area. Provide single action hardware for the west exterior exit doors (per the plans one door panel is to be fixed). The "Cylinder Closet" exterior wall venting does not meet the height requirements of IFC 3006.2.1. Provide the NFPA Hazard Warning Sign per IFC 2703.5. Door is missing the smoke seal.
BLD-Energy code compliance3/15/20113/16/20113/16/2011PPASS
DetailsTom Arcoraci
Cameron Phone #: ###-#### grid ok, 1 hr can lights covers ok
BLD-Other2/23/20112/24/20112/24/2011APASS
DetailsMike Jordan
drywall nail inspection 2nd layer//cameron Phone #: ###-####. face layer of 5/8 type x rock for 1hr. ceiling and 1hr. firewall.
BLD-Other2/23/20112/23/20112/23/2011PPART
DetailsMike Jordan
drywall nail inspection 1st layer//Cameron Phone #: ###-####. Base layer of 5/8 type x rock for 1hr. ceiling assembly.
BLD-Framing/Rough-in2/18/20112/22/20112/22/2011APASS
DetailsMike Jordan
Cameron Phone #: ###-####. All framing issues have been resolved. Also met with sheetrock contractor. All other fire issues with 1hr. ceiling have been discussed and will be inspected as job progresses.
BLD-Energy code compliance2/22/20112/22/20112/22/2011APASS
DetailsMike Jordan
Cameron Phone #: ###-####
BLD-Energy code compliance2/16/20112/18/20112/18/2011PCANC
DetailsMike Jordan
cameron Phone #: ###-####
BLD-Framing/Rough-in2/16/20112/17/20112/17/2011PFAIL
DetailsMike Jordan
cameron Phone #: ###-####. Sprinkler rough in required prior to cover, Bearing blocks required at girder truss T15 and T14. Truss T7 requires min 2x6 T bracing, 2x4 was used. Need approved plan forshell portion of work. Needs to provide rated can lights or box out. Provide damperas for ducts, fire collar for water heater vent, 5/8 type x rock reqiured at ceiling at pre built soffits. ok to inulate.
BLD-Energy code compliance2/4/20112/4/20112/4/2011PPART
DetailsMike Jordan
CAMERON Phone #: ###-####. Wall insulation at 1hr. gas room.
BLD-Conference1/27/20112/1/20112/1/2011ACANC
DetailsMike Jordan
cameron Phone #: ###-#### 1-31-11 PER CAMERON JAYO CONSTRUCTION CANCEL INSPECTION ///DLD
BLD-Footing1/26/20111/27/20111/27/2011PPASS
DetailsMike Jordan
cameron Phone #: ###-####. Footing for 1hr gas room.