Permit Information
Permit NumberBLD10-02963
StatusFinaled
Name CM COMPANY
Site Address 11197 W FAIRVIEW AVE
Project NamePrimary Health - Wildwood
Customer Number 
ePlanReviewNo
Description
Primary Health - To construct a new 5,275 square foot, one story, wood framed medical office building and related site improvements. This building will contain a reception and waiting area, offices, exam rooms, x-ray room, procedure room, five accessible restrooms and a break room. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/18/20118/18/20118/18/2011PPASS
DetailsMike Jordan
tom - ###-####. Ok for perm. occ.
BLD-Final8/16/20118/18/20118/17/2011PNR
DetailsMike Jordan
tom Phone #: ###-####
FIRE-Final Inspection8/16/20118/17/20118/17/2011APASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection8/12/20118/15/20118/15/2011PFAIL
DetailsTroy Cobbley
The life safety will be ready to sign off when the project related fire alarm and fire sprinkler permits are finaled and approved single action hardware is provided on the fire riser door.
BLD-Other7/20/20117/21/20117/21/2011PPASS
DetailsTom Arcoraci
Above ceiling for cover--Tom Phone #: ###-####
BLD-Other7/20/20117/20/20117/20/2011PNR
DetailsMike Jordan
ceiling grid insp//Tom Phone #: ###-####. Needs mech. rough in inspection.
BLD-Framing/Rough-in6/17/20116/17/20116/17/2011PPASS
DetailsMike Jordan
tom Phone #: ###-####. Interior steel stud framed walls at foier.
BLD-Energy code compliance6/6/20116/7/20116/7/2011PPASS
DetailsMike Jordan
Tom Phone #: ###-####
BLD-Framing/Rough-in6/2/20116/3/20116/3/2011PPASS
DetailsMike Jordan
Tom Phone #: ###-####. Interior steel stud walls and exterior wood framed walls only.
BLD-Framing/Rough-in5/17/20115/17/20115/17/2011PPART
DetailsMike Jordan
Verified fireblocking at all pop outs. ok to cover.
FIRE-Conference5/13/20115/16/20115/16/2011ADONE
DetailsTroy Cobbley
Per discussion the "concealed combustible" chases on the exterior of the building are not required to have sprinkler protection and can be covered with no further modifications.
BLD-Framing/Rough-in5/12/20115/13/20115/13/2011PPART
DetailsMike Jordan
Tom Phone #: ###-####Exterior shear nailing only. Needs to provide coil straps at east and north side of building, provide fire blocking at 10ft. intervals at pop outs.
BLD-Framing/Rough-in5/9/20115/10/20115/10/2011APART
DetailsMike Jordan
tom Phone #: ###-####. Visually inspected the attachment and all associated hardware of the roof diaphragm system. All work was done in accordance with approved plans.
FIRE-Conference5/5/20115/6/20115/6/2011ADONE
DetailsTroy Cobbley
Tom and I went over fire dept access requirements for the site.
BLD-Foundation4/13/20114/14/20114/14/2011APASS
DetailsJim Sly
tom Phone #: ###-####
OK pending MTI special inspection, tests and approvals.....Also looked at trash enclosure footing.....appears OK.
BLD-Footing4/11/20114/12/20114/12/2011PPASS
DetailsMike Jordan
Tom Phone #: ###-####. Perimeter footing.