BLD-Final | 5/18/2011 | 5/19/2011 | 5/19/2011 | P | PART |
Mike Jordan
|
|
|
Bryce Phone #: ###-####. Ok for temp. occ. Wil be ok for perm occ. once elec. signs perm.
|
FIRE-Final Inspection | 5/19/2011 | 5/19/2011 | 5/19/2011 | P | PASS |
Forrest France
|
|
|
Life safety is acceptable pending two items including (1) the fire extinguisher is located along a normal path of travel as discussed and (2) approved hardware at the restroom is installed and verified prior to structural final.
|
BLD-Energy code compliance | 5/9/2011 | 5/10/2011 | 5/10/2011 | A | PASS |
Mike Jordan
|
|
|
Brice Phone #: ###-####
|
BLD-Energy code compliance | 5/2/2011 | 5/2/2011 | 5/2/2011 | P | PASS |
Mike Jordan
|
|
|
BRYCE Phone #: ###-####
|
BLD-Framing/Rough-in | 5/2/2011 | 5/2/2011 | 5/2/2011 | P | PASS |
Mike Jordan
|
|
|
BRYCE Phone #: ###-####
|
BLD-Framing/Rough-in | 4/29/2011 | 4/29/2011 | 4/29/2011 | P | PART |
Mike Jordan
|
|
|
Bryce ###-####. Needs to provide truss engineering. Will check on energy ok. Ok to insulate. Also additional rebar added to footing for dumpster enclosure.
|
BLD-Framing/Rough-in | 4/27/2011 | 4/28/2011 | 4/28/2011 | P | NR |
Mike Jordan
|
|
|
bryce Phone #: ###-####. Needs rough in inspections.
|
BLD-Footing | 4/25/2011 | 4/25/2011 | 4/25/2011 | P | PART |
Mike Jordan
|
|
|
STeve Phone #: ###-####. Needs to add #4 horizontal in footing. Footing for dumpster enclosure.
|
BLD-Framing/Rough-in | 4/21/2011 | 4/21/2011 | 4/21/2011 | P | PASS |
Mike Jordan
|
|
|
Sheathing only--Bryce Phone #: ###-####. Shear ok. Reviewed supplemental info and approved fix from engineer. All issues have been resolved.
|
BLD-Other | 4/19/2011 | 4/19/2011 | 4/19/2011 | P | FAIL |
Mike Jordan
|
|
|
exterior sheathing insp//Bryce Phone #: ###-####. Nailing ok. Needs approved fix for missing holdowns, clarification on A2 holdowns and straps around openings and corners.
|
BLD-Other | 4/4/2011 | 4/5/2011 | 4/5/2011 | A | PASS |
Mike Jordan
|
|
|
slab on grade insp//Jeremy Phone #: ###-####
|
BLD-Wall cover | 3/29/2011 | 3/30/2011 | 3/30/2011 | P | CANC |
Mike Jordan
|
|
|
Stem Wall---Jeremy Phone #: ###-####
|
BLD-Foundation | 3/30/2011 | 3/30/2011 | 3/30/2011 | P | PASS |
Mike Jordan
|
|
|
Stem Wall---Jeremy Phone #: ###-####
|
BLD-Footing | 3/28/2011 | 3/29/2011 | 3/29/2011 | A | PASS |
Mike Jordan
|
|
|
Jeremy Phone #: ###-####
|
BLD-Footing | 3/25/2011 | 3/28/2011 | 3/28/2011 | A | NR |
Mike Jordan
|
|
|
Jeremy Phone #: ###-####. Reinforcement not yet installed. Also noted that due to rain, footing footprint is partially flooded. Contacted jermey to discuss issues. Will let dry out, and install rebar and cal for reinspection.
|