BLD-Final | 7/5/2011 | 7/6/2011 | 7/6/2011 | A | PASS |
Jim Storey
|
|
|
ryan Phone #: ###-#### final ok
|
BLD-Final | 6/23/2011 | 6/24/2011 | 6/24/2011 | A | PART |
Dave Hannah
|
|
|
Brian Phone #: ###-#### ok for temp occ ok for perm occ after mec gos perm
|
FIRE-Final Inspection | 6/22/2011 | 6/23/2011 | 6/23/2011 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed acceptable. One EM light repaired while on site, signage at the electrical room and elevator lobbies to be posted as discussed.
|
FIRE-Final Inspection | 6/21/2011 | 6/22/2011 | 6/22/2011 | P | NR |
Forrest France
|
|
|
Final pending project related FIR permit.
|
BLD-Other | 6/3/2011 | 6/6/2011 | 6/6/2011 | A | PART |
Dave Hannah
|
|
|
RYAN Phone #: ###-#### ceiling in basement ok to cover
|
BLD-Wall cover | 5/20/2011 | 5/20/2011 | 5/23/2011 | P | PASS |
Dave Hannah
|
|
|
Ceiling cover--Ryan Phone #: ###-#### ok to cover first floor
|
BLD-Framing/Rough-in | 5/5/2011 | 5/6/2011 | 5/6/2011 | A | PASS |
Dave Hannah
|
|
|
Ryan Phone #: ###-#### ext canopy
|
BLD-Wall cover | 4/7/2011 | 4/8/2011 | 4/11/2011 | P | PASS |
Dave Hannah
|
|
|
ryan Phone #: ###-#### ok to cover the rest of first floor and all of the basement
|
BLD-Energy code compliance | 4/1/2011 | 4/4/2011 | 4/5/2011 | P | PART |
Dave Hannah
|
|
|
ryan - as soon as possible after lunch please Phone #: ###-#### ok to cover first floor
|
BLD-Framing/Rough-in | 3/30/2011 | 3/31/2011 | 3/31/2011 | A | PART |
Dave Hannah
|
|
|
ryan Phone #: ###-#### ok to insulate ext wall basement and first floor
|
BLD-Other | 3/18/2011 | 3/21/2011 | 3/22/2011 | P | PART |
Dave Hannah
|
|
|
rebar in masonry//Ryan Smith Phone #: ###-#### elevator cmu walls ok to grout
|
BLD-Concrete | 3/17/2011 | 3/18/2011 | 3/18/2011 | P | PART |
Jim Sly
|
|
|
late pm//Ryan (or Matt @ ###-####) Phone #: ###-#### Looked at Stairway wall East side.....walls for Ramp and stairway- South side......2500 PSI design strength...Contractor says he is ordering 3500 mud.....Eng. only required 3000. Looked at CMU elevator shaft...Rebar in place and appears OK up to 6' high. They should call daily for inspection of CMU. Need test samples on Mortar. Supervisor for Benington was just filling in for today...his name was Matt. I let him know all this.
|
BLD-Foundation | 3/9/2011 | 3/10/2011 | 3/11/2011 | A | PASS |
Dave Hannah
|
|
|
late A.M. call before arrival--Ryan Phone #: ###-#### ftgs for stairs into basement and ada ramp
|
BLD-Concrete | 3/3/2011 | 3/4/2011 | 3/4/2011 | A | PASS |
Mike Jordan
|
|
|
ryan - pouring at 10 Phone #: ###-####. Reinforcement for elevator pit ok. Also noted to contracotr that design professional as required special inspection as per table 1704 that has been submitted.
|