BLD-Final | 8/12/2011 | 8/15/2011 | 8/15/2011 | A | PASS |
Dave Hannah
|
|
|
Chad Phone #: ###-####
|
DOC - Permit Finaled | 8/15/2011 | 8/15/2011 | 8/15/2011 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Grading Inspection | 8/12/2011 | 8/12/2011 | 8/12/2011 | A | DONE |
Terry Records
|
|
|
Final grading and drainage approved.
|
BLD-Energy code compliance | 4/22/2011 | 4/22/2011 | 4/22/2011 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 4/21/2011 | 4/22/2011 | 4/22/2011 | A | DEFR |
Jim Storey
|
|
|
chad Phone #: ###-####
|
BLD-Framing/Rough-in | 4/20/2011 | 4/20/2011 | 4/21/2011 | P | PART |
Dave Hannah
|
|
|
CHAD (CONF ,SHEER & RI) With ENG 4 PM Phone #: ###-#### ok to cover ext shear was renailed and is per city approved plans framing ok all but for one hold down on se wall right of fire place needs to be instaled framing contractor builder and the builders engineer all on site for this inspection. engineer ok stru changes made and was ok with framing energy star inspector also on site walking project . Troy with boise city mec inspection also on site has several items said it was ok to insulate but dont cover until he signs off so ok to insulate.
|
BLD-Framing/Rough-in | 4/15/2011 | 4/15/2011 | 4/15/2011 | P | FAIL |
Dave Hannah
|
|
|
CHAD Phone #: ###-#### shear nailing on ext not per plan do not cover
|
BLD-Footing | 3/9/2011 | 3/9/2011 | 3/9/2011 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Footing | 3/7/2011 | 3/8/2011 | 3/8/2011 | A | NR |
Dave Hannah
|
|
|
BILL Phone #: ###-#### footings and site are very muddy contractor will wait for site to dry out so they dont have to remove bar to clean out
|
BLD-Footing | 3/4/2011 | 3/4/2011 | 3/7/2011 | P | CANC |
Dave Hannah
|
|
|
aaron Phone #: ###-####
|
BLD-Footing | 3/2/2011 | 3/3/2011 | 3/3/2011 | P | CANC |
Dave Hannah
|
|
|
BILL Phone #: ###-####
|