DOC - Permit Finaled | 10/14/2011 | 10/14/2011 | 10/14/2011 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 8/4/2011 | 8/5/2011 | 8/5/2011 | P | PART |
Tony Young
|
|
|
ok for final pending all others,, paperwork from engineer is in the mailbox
|
FIRE-Final Inspection | 8/3/2011 | 8/5/2011 | 8/5/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Other | 8/3/2011 | 8/4/2011 | 8/4/2011 | A | NR |
Tom Arcoraci
|
|
|
Jim, this is a call for the final structural inspection for occupancy. If any questions please feel free to call. Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald
|
BLD-Framing/Rough-in | 7/25/2011 | 7/25/2011 | 7/25/2011 | A | PASS |
Jim Sly
|
|
|
We are ready to start flooding the ceiling grid. A late AM inspection would be very much appreciated. Phone #: ###-#### >> Inspection requested via web by Ron Oswald
|
BLD-Framing/Rough-in | 7/19/2011 | 7/19/2011 | 7/19/2011 | P | DONE |
Mike Jordan
|
|
|
Please provide a cursory inspection on suspended ceiling grid. Entrance to site has change to school parking lot, east entrance. Phone #: ###-#### >> Inspection requested via web by Ron Oswald. Cisca 3-4 system to be used, grid exceeds nthe 2.5 lbs. per square foot.
|
BLD-Framing/Rough-in | 7/7/2011 | 7/8/2011 | 7/8/2011 | A | PART |
Jim Sly
|
|
|
Please provide a late morning hard lid inspection for the project restrooms. We have a am Electrical and have passed the HVAC and Plumbing roughs for this area. Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald Hard lids in restrooms and restroom walls OK to cover. Trusses OK.
|
BLD-Framing/Rough-in | 6/29/2011 | 6/29/2011 | 6/29/2011 | P | PART |
Tom Arcoraci
|
|
|
Please provide a interior wall framing inspection for cover. I have the main classrooms electrical inspections signed off for this area by the state. The restroom areas will be inspected for plumbing this afternoon. Thanks you Phone #: ###-#### >> Inspection requested via web by Ron Oswald classrooms ok for cover tom
|
BLD-Framing/Rough-in | 6/20/2011 | 6/21/2011 | 6/21/2011 | A | PART |
Jim Sly
|
|
|
We are currently installing the sheeting and If possible I would like to schedule my roofing crew in late morning. If able please schedule for the first of the morning. Thanks Ron Oswald Phone #: ###-#### >> Inspection requested via web by Ron Oswald Roof sheathing and trusses OK
|
BLD-Concrete | 5/6/2011 | 5/9/2011 | 5/9/2011 | P | PART |
Jim Sly
|
|
|
Changing inspection due to weather, we will pour on Tuesday AM. Afternoon inspection is prefered. Strata providing Special inspections also in afternoon. Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald OK pending STRATA special insp, tests and approvals.
|
BLD-Concrete | 5/6/2011 | 5/9/2011 | 5/6/2011 | A | CANC |
Jim Sly
|
|
|
This inspection is for slab pour, We are Scheduled for concrete to arrive at 7:30 am. Don Hill with Strata is Handling the special inspections, Rebar, Wire mesh and pour observations. Underslab Plumbing has been inspected and logged with Sticker attached. Any Questions feel free to call me at anytime.
Thanks
Ron Oswald Phone #: ###-#### >> Inspection requested via web by Ron Oswald Inspection cancelled from web by: Ron Oswald
|
BLD-Foundation | 4/21/2011 | 4/22/2011 | 4/22/2011 | P | PASS |
Tom Arcoraci
|
|
|
wip ok spec insp
|
BLD-Foundation | 4/21/2011 | 4/21/2011 | 4/21/2011 | P | NR |
Tom Arcoraci
|
|
|
Stem wall, Scheduled for 2:00 pm. Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald
|
BLD-Footing | 4/19/2011 | 4/21/2011 | 4/21/2011 | A | PART |
Mike Jordan
|
|
|
Good afternoon, We have a specific access road to get to project site. It is East of the school proper at our Company sign. If possible please schedule for as early as we can near 8:30 am. Thanks and have a great day Ron Oswald Site Superintendent Phone #: ###-#### >> Inspection requested via web by Ron Oswald. Permiter and interior footings. Special inspector on site.
|