Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD11-00080
StatusFinaled
Name WRIGHT BROTHERS THE BLDG CO
Site Address 7701 W NORTHVIEW ST
Project NameMorley Nelson Elementary
Customer Number 
ePlanReviewNo
Description
Morley Nelson Elementary School - Classroom Addition - To construct a 5,627 square foot, one story classroom and restroom addition at the south end of the south wing of an existing 58,243 square foot elementary school. The addition is constructed of masonry exterior walls with wood framed roof trusses and metal interior stud walls, to match existing school construction. The addition contains four new classrooms and two new accessible restrooms. This permit also includes related site improvements. The original school building was completed in 2008 under building permit BLD06-03277. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled10/14/201110/14/201110/14/2011PPASS
DetailsJim Sly
BLD-Final8/4/20118/5/20118/5/2011PPART
DetailsTony Young
ok for final pending all others,, paperwork from engineer is in the mailbox
FIRE-Final Inspection8/3/20118/5/20118/5/2011APASS
DetailsTroy Cobbley
life safety passed
BLD-Other8/3/20118/4/20118/4/2011ANR
DetailsTom Arcoraci
Jim, this is a call for the final structural inspection for occupancy. If any questions please feel free to call. Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald
BLD-Framing/Rough-in7/25/20117/25/20117/25/2011APASS
DetailsJim Sly
We are ready to start flooding the ceiling grid. A late AM inspection would be very much appreciated. Phone #: ###-#### >> Inspection requested via web by Ron Oswald
BLD-Framing/Rough-in7/19/20117/19/20117/19/2011PDONE
DetailsMike Jordan
Please provide a cursory inspection on suspended ceiling grid. Entrance to site has change to school parking lot, east entrance. Phone #: ###-#### >> Inspection requested via web by Ron Oswald. Cisca 3-4 system to be used, grid exceeds nthe 2.5 lbs. per square foot.
BLD-Framing/Rough-in7/7/20117/8/20117/8/2011APART
DetailsJim Sly
Please provide a late morning hard lid inspection for the project restrooms. We have a am Electrical and have passed the HVAC and Plumbing roughs for this area.
Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald
Hard lids in restrooms and restroom walls OK to cover. Trusses OK.
BLD-Framing/Rough-in6/29/20116/29/20116/29/2011PPART
DetailsTom Arcoraci
Please provide a interior wall framing inspection for cover. I have the main classrooms electrical inspections signed off for this area by the state. The restroom areas will be inspected for plumbing this afternoon. Thanks you Phone #: ###-#### >> Inspection requested via web by Ron Oswald classrooms ok for cover tom
BLD-Framing/Rough-in6/20/20116/21/20116/21/2011APART
DetailsJim Sly
We are currently installing the sheeting and If possible I would like to schedule my roofing crew in late morning. If able please schedule for the first of the morning. Thanks Ron Oswald Phone #: ###-#### >> Inspection requested via web by Ron Oswald
Roof sheathing and trusses OK
BLD-Concrete5/6/20115/9/20115/9/2011PPART
DetailsJim Sly
Changing inspection due to weather, we will pour on Tuesday AM. Afternoon inspection is prefered. Strata providing Special inspections also in afternoon. Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald
OK pending STRATA special insp, tests and approvals.
BLD-Concrete5/6/20115/9/20115/6/2011ACANC
DetailsJim Sly
This inspection is for slab pour, We are Scheduled for concrete to arrive at 7:30 am. Don Hill with Strata is Handling the special inspections, Rebar, Wire mesh and pour observations. Underslab Plumbing has been inspected and logged with Sticker attached. Any Questions feel free to call me at anytime.

Thanks
Ron Oswald Phone #: ###-#### >> Inspection requested via web by Ron Oswald Inspection cancelled from web by: Ron Oswald
BLD-Foundation4/21/20114/22/20114/22/2011PPASS
DetailsTom Arcoraci
wip ok spec insp
BLD-Foundation4/21/20114/21/20114/21/2011PNR
DetailsTom Arcoraci
Stem wall, Scheduled for 2:00 pm.
Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald
BLD-Footing4/19/20114/21/20114/21/2011APART
DetailsMike Jordan
Good afternoon, We have a specific access road to get to project site. It is East of the school proper at our Company sign. If possible please schedule for as early as we can near 8:30 am. Thanks and have a great day