BLD-Final | 8/12/2011 | 8/15/2011 | 8/15/2011 | A | PASS |
Jim Sly
|
|
|
Hank Bothman Phone #: ###-#### C/C issued.
|
DOC - Permit Finaled | 8/15/2011 | 8/15/2011 | 8/15/2011 | P | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 8/5/2011 | 8/5/2011 | 8/5/2011 | P | NR |
Tony Young
|
|
|
devon Phone #: ###-####,, need trades 1st,,, wanted a final,,, no inspection made
|
BLD-Conference | 7/25/2011 | 7/25/2011 | 7/25/2011 | P | PASS |
Jim Sly
|
|
|
Devin ###-#### insp of ceiling grid and 1 hr wall (exterior) above front soffit at entry.
|
BLD-Conference | 7/19/2011 | 7/19/2011 | 7/19/2011 | P | DONE |
Mike Jordan
|
|
|
deven Phone #: ###-####. Must maintain continuity at 2hr. firewall.
|
BLD-Framing/Rough-in | 6/30/2011 | 7/1/2011 | 7/1/2011 | A | PART |
Jim Sly
|
|
|
Devon Phone #: ###-#### Interior walls and double sheetrock above ceiling between joists OK... Main floor.
|
BLD-Framing/Rough-in | 6/20/2011 | 6/21/2011 | 6/21/2011 | A | PART |
Jim Sly
|
|
|
Devon Phone #: ###-#### Framing and modified 2hr wall OK at 2nd floor.....and framing OK at bottom of stairway area 1st floor.
|
BLD-Conference | 6/6/2011 | 6/7/2011 | 6/7/2011 | A | PASS |
Jim Sly
|
|
|
Devon Phone #: ###-####
|