Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberBLD11-00300
StatusFinaled
Name CHAD JOHNSON
Site Address 601 W MAIN ST
Project NameTHE BRICKYARD
Customer Number 
ePlanReviewNo
Description
(THE BRICKYARD) Fire sprinklers used for story and area increase. To combine two restaurant spaces into one 5,265 square foot bar and restaurant (4,270 square foot 1st story and 1,095 square foot basement). The basement is approved only for office and storage use, not assembly. The “Green Room” is NOT approved for public assembly. Work is to include interior nonbearing walls, a staff restroom accessible to the disabled, new exterior door, new exterior windows, new interior doors, millwork, and finishes. The public restrooms and the grease hood were installed under permit BLD04-01146. Structural work was done under permit BLD10-02918. All work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection6/30/20117/1/20117/1/2011APASS
DetailsTroy Cobbley
Life safety passed
BLD-Final7/1/20117/1/20117/1/2011PPASS
DetailsDave Hannah
FIRE-Final Inspection6/29/20116/30/20116/30/2011PFAIL
DetailsForrest France
Correction items include; repair two exit signs at the main entry vestibule area, provide approved hardware at the staff restroom door, replace missing ceiling tile at the electrical room next to the mens restroom, foam DP at the exisitng cooler, post fire extinguishers per plan and K class in the kitchen as discussed.
BLD-Final6/29/20116/30/20116/30/2011PPART
DetailsDave Hannah
John Phone #: ###-#### ok for perm occ after fire oks for perm occ
FIRE-Conference6/27/20116/27/20116/28/2011PDONE
DetailsForrest France
Conversation with contractor regarding project schedule and related trade permit final inspections including fire sprinkler and hood suppression.
BLD-Conference6/1/20116/1/20116/1/2011PPASS
DetailsDave Hannah
John Phone #: ###-#### exit lights
BLD-Conference5/31/20116/1/20116/1/2011APASS
DetailsDave Hannah
John Phone #: ###-####
BLD-Other5/26/20115/27/20115/27/2011APART
DetailsTony Young
Ceiling grid---John Phone #: ###-####,, ceil grids ok
FIRE-Sprinkler Rough-in5/25/20115/25/20115/25/2011PPART
DetailsForrest France
Overhead fire sprinkler work okay to cover as noted on city stamped FP plan set.
BLD-Framing/Rough-in4/19/20114/19/20114/19/2011PPASS
DetailsDave Hannah
John Phone #: ###-####
BLD-Framing/Rough-in4/7/20114/8/20114/8/2011ANR
DetailsDave Hannah
john Phone #: ###-#### needs plumbing and elec rough ins and fire blocking in furred out wall got mti s report on bolting all passed also ok fix on cut floor joist in basement