BLD-Final | 2/10/2014 | 2/10/2014 | 2/10/2014 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 2/10/2014 | 2/10/2014 | 2/10/2014 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 2/5/2014 | 2/7/2014 | 2/10/2014 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 10/10/2013 | 10/10/2013 | 10/18/2013 | | PEND |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 5/29/2013 | 5/29/2013 | 5/29/2013 | A | PASS |
Forrest France
|
|
|
Life safety inspection completed and passed.
|
BLD-Aging Inspection | 5/7/2013 | 5/7/2013 | 5/7/2013 | A | DONE |
Forrest France
|
|
|
Okay to final
|
BLD-Aging Inspection | 5/3/2013 | 5/3/2013 | 5/7/2013 | | PEND |
Dave Hannah
|
|
|
|
FIRE-Conference | 5/23/2012 | 5/23/2012 | 5/23/2012 | A | DONE |
Forrest France
|
|
|
Regarding scope of permit attatched fire sprinkler work for replacement of existing system piping.
|
BLD-Final | 5/8/2012 | 5/8/2012 | 5/8/2012 | P | PASS |
Dave Hannah
|
|
|
Please call -- Boyd Phone #: ###-####
|
BLD-Final | 1/12/2012 | 1/12/2012 | 1/12/2012 | A | PART |
Dave Hannah
|
|
|
Late AM---Rob Phone #: ###-#### ok to reopen the west stair tower we will final project in the spring
|
BLD-Final | 1/4/2012 | 1/5/2012 | 1/12/2012 | A | PART |
Dave Hannah
|
|
|
Late AM---Rob Phone #: ###-####
|
FIRE-Final Inspection | 1/4/2012 | 1/5/2012 | 1/5/2012 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection for the scope of work completed. Locks at the egress side doors from the parking deck to the stair towers to be removed prior to structural final as agreed.
|
BLD-Final | 10/12/2011 | 10/13/2011 | 10/14/2011 | A | PART |
Dave Hannah
|
|
|
Rob Phone #: ###-#### ok to reopen east stairtower and move to west stair
|
BLD-Final | 10/5/2011 | 10/10/2011 | 10/10/2011 | A | NR |
Dave Hannah
|
|
|
Rob Phone #: ###-####
|
BLD-Conference | 10/4/2011 | 10/4/2011 | 10/5/2011 | P | PART |
Dave Hannah
|
|
|
Rob Phone #: ###-#### walked stairs on east end all looks ok they will finish monday
|
BLD-Concrete | 8/12/2011 | 8/15/2011 | 8/16/2011 | A | PART |
Dave Hannah
|
|
|
concrete coming at 10// 6th floor// Rob Phone #: ###-####
|
BLD-Concrete | 8/5/2011 | 8/8/2011 | 8/8/2011 | A | PART |
Dave Hannah
|
|
|
rob - concrete at 10:00 Phone #: ###-####
|
BLD-Concrete | 7/29/2011 | 7/29/2011 | 7/29/2011 | P | PART |
Dave Hannah
|
|
|
rob Phone #: ###-#### spec inspection on site foe rebar and concrete
|
BLD-Concrete | 7/19/2011 | 7/19/2011 | 7/20/2011 | P | PART |
Dave Hannah
|
|
|
rob - pouring at 1 Phone #: ###-####
|
BLD-Concrete | 7/8/2011 | 7/8/2011 | 7/8/2011 | P | PASS |
Jim Storey
|
|
|
Rob-please call prior to inspection-pouring concrete at 1:00 Phone #: ###-#### 2nd floor landing ok
|