BLD-Final | 12/22/2011 | 12/23/2011 | 12/23/2011 | A | PASS |
Tony Young
|
|
|
t j Phone #: ###-####,, perm occupancy ok now
|
BLD-Final | 11/8/2011 | 11/8/2011 | 11/9/2011 | P | PART |
Tony Young
|
|
|
john Phone #: ###-####,, temp occupancy ok untill trades are fully finaled
|
BLD-Final | 11/4/2011 | 11/7/2011 | 11/9/2011 | P | PART |
Tony Young
|
|
|
john Phone #: ###-####,, temp occ ok,, need full sign off from trades
|
FIRE-Final Inspection | 11/4/2011 | 11/7/2011 | 11/7/2011 | P | PASS |
Forrest France
|
|
|
Corrections verified for completion. Fire life safety passed.
|
FIRE-Conference | 10/26/2011 | 10/26/2011 | 10/26/2011 | P | DONE |
Forrest France
|
|
|
Regarding project related fire alarm permit status and final.
|
BLD-Final | 10/12/2011 | 10/13/2011 | 10/13/2011 | A | NR |
Tony Young
|
|
|
John Phone #: ###-####
|
FIRE-Final Inspection | 10/12/2011 | 10/13/2011 | 10/13/2011 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm and fire sprinkler permits need to be addressed. Also see the city approved plans, 1st approval, for the exit signs and emergency lights that are either missing or do not function. Also many of the existing exit lights and emergency lights are not functional and will need repaired prior to a final sign off.
|
BLD-Conference | 10/12/2011 | 10/12/2011 | 10/12/2011 | P | PART |
Tony Young
|
|
|
John Phone #: ###-####,, walk through
|
FIRE-Final Inspection | 10/12/2011 | 10/12/2011 | 10/12/2011 | P | CANC |
Troy Cobbley
|
|
|
Overbooked. Rescheduled for tomorrow.
|
FIRE-Final Inspection | 10/12/2011 | 10/12/2011 | 10/12/2011 | P | CANC |
Troy Cobbley
|
|
|
Duplicate inspection
|
BLD-Final | 10/7/2011 | 10/10/2011 | 10/12/2011 | P | NR |
Tony Young
|
|
|
Late afternoon--John Phone #: ###-####,, conf only
|
FIRE-Final Inspection | 10/7/2011 | 10/10/2011 | 10/10/2011 | P | CANC |
Troy Cobbley
|
|
|
To be canceled per Scott Arellano. Tom Gainer has visited job site and provided update on job status to Scott.
|
BLD-Final | 10/7/2011 | 10/7/2011 | 10/7/2011 | P | NR |
Tony Young
|
|
|
Late afternoon--John Phone #: ###-####,, walk through only
|
FIRE-Final Inspection | 10/5/2011 | 10/6/2011 | 10/6/2011 | P | NR |
Forrest France
|
|
|
john Phone #: ###-####
|
FIRE-Sprinkler Rough-in | 10/3/2011 | 10/3/2011 | 10/3/2011 | P | PART |
Forrest France
|
|
|
Overhead work okayed for cover with the exception of the first floor corrdior at the new addition.
|
BLD-Other | 9/27/2011 | 9/27/2011 | 9/27/2011 | P | PASS |
Tony Young
|
|
|
john - ceiling grid Phone #: ###-####
|
BLD-Framing/Rough-in | 9/16/2011 | 9/16/2011 | 9/16/2011 | P | PART |
Mike Jordan
|
|
|
Cieling grid inspection please-John Phone #: ###-####. HArdlids in girls and boys restroom, 1st. floor. Pending fire sprinkler rough in approvals.
|
FIRE-Conference | 9/13/2011 | 9/13/2011 | 9/13/2011 | P | DONE |
Forrest France
|
|
|
Regarding fire alarm manual pull station locations.
|
FIRE-Final Inspection | 9/12/2011 | 9/12/2011 | 9/12/2011 | P | PART |
Forrest France
|
|
|
Inspection request intended for fire sprinkler cover at the second floor remodeled classroom. Noted one sprinkler head to be replaced due to mechanical damage of the deflector.
|
BLD-Framing/Rough-in | 9/12/2011 | 9/12/2011 | 9/12/2011 | P | PART |
Tony Young
|
|
|
john - ceiling grid Phone #: ###-####,, 2nd floor existing room ok pending trades
|
BLD-Framing/Rough-in | 9/1/2011 | 9/2/2011 | 9/2/2011 | P | PART |
Dave Hannah
|
|
|
John phone ####-#### framing rooms 113 thru 117 ok to insulate
|
BLD-Final | 8/30/2011 | 8/31/2011 | 9/1/2011 | P | NR |
Tony Young
|
|
|
john - temp occupancy Phone #: ###-####
|
BLD-Conference | 8/23/2011 | 8/24/2011 | 9/1/2011 | P | PART |
Tony Young
|
|
|
partial final-John Phone #: ###-####,, kinder gaerten room and offices ok pending others
|
FIRE-Final Inspection | 8/30/2011 | 8/31/2011 | 8/31/2011 | A | NR |
Forrest France
|
|
|
|
BLD-Other | 8/30/2011 | 8/30/2011 | 8/30/2011 | P | PART |
Tony Young
|
|
|
ceiling grid insp//John Phone #: ###-#### office area ok pending others
|
BLD-Framing/Rough-in | 8/24/2011 | 8/25/2011 | 8/26/2011 | P | PASS |
Tony Young
|
|
|
john Phone #: ###-####,, classrooms ok
|
BLD-Conference | 8/23/2011 | 8/24/2011 | 8/25/2011 | P | DONE |
Forrest France
|
|
|
Regarding occupancy at the remodeled classroom 1st floor.
|
BLD-Other | 8/23/2011 | 8/23/2011 | 8/24/2011 | P | PART |
Tony Young
|
|
|
Ceiling grid--John Phone #: ###-####,, ok pending trades in admin and kindergarden area
|
BLD-Framing/Rough-in | 8/19/2011 | 8/19/2011 | 8/22/2011 | P | DONE |
Tom Arcoraci
|
|
|
john Phone #: ###-####
|
BLD-Framing/Rough-in | 8/19/2011 | 8/22/2011 | 8/22/2011 | A | PART |
Tom Arcoraci
|
|
|
john Phone #: ###-#### wip ok walls 2nd story
|
BLD-Conference | 8/18/2011 | 8/19/2011 | 8/19/2011 | A | PART |
Tony Young
|
|
|
john Phone #: ###-####,, on site conference with all parties,, e-mail to all parties will follow up by Scott A., (Fire) issues are construction will still be going on while school is starting,, alternate egress issues. Possible changes in the mechanical system, but will take place later (3-4 weeks)
|
BLD-Conference | 8/19/2011 | 8/19/2011 | 8/19/2011 | P | DONE |
Forrest France
|
|
|
john Phone #: ###-####,, 1:30 pm if possible * NOTE: On site conference completed by S. Arellano.
|
BLD-Wall cover | 8/12/2011 | 8/15/2011 | 8/19/2011 | A | PASS |
Tony Young
|
|
|
john Phone #: ###-####,, re look at shear,, shear ok now,, 2nd floor walls ok to insulate
|
FIRE-Conference | 8/18/2011 | 8/19/2011 | 8/19/2011 | A | DONE |
Scott Arellano
|
|
|
Onsite Meeting *SJA* See conditions for TEMP occupancy in attached documents.
|
BLD-Wall cover | 8/16/2011 | 8/16/2011 | 8/16/2011 | P | PART |
Tony Young
|
|
|
john - shear inspection Phone #: ###-####,, exterior shear ok
|
BLD-Framing/Rough-in | 8/15/2011 | 8/16/2011 | 8/16/2011 | A | PART |
Tony Young
|
|
|
john - shear inspection Phone #: ###-####,, 2nd floor ok
|
BLD-Framing/Rough-in | 8/12/2011 | 8/12/2011 | 8/15/2011 | P | PART |
Tony Young
|
|
|
john Phone #: ###-####,, SHEAR INSPECTION,, MOST OK ,, just needs a more in a few areas
|
BLD-Framing/Rough-in | 8/8/2011 | 8/9/2011 | 8/9/2011 | A | PART |
Tony Young
|
|
|
framing, hold down & roofing//John Sanchez Phone #: ###-####,, fireblocking,, work in progress,, ok
|
BLD-Framing/Rough-in | 8/5/2011 | 8/8/2011 | 8/8/2011 | P | PART |
Tony Young
|
|
|
framing, hold down & roofing//John Sanchez Phone #: ###-####,, roof nailing ok,, hold downs ok,, walk through with framer and super,, ok,, some verbal fixes,, mainly straps and fireblocks,, hidden straps ok to cover
|
BLD-Conference | 7/28/2011 | 7/28/2011 | 7/29/2011 | P | PASS |
Tony Young
|
|
|
take C. Westfall,, walk through
|
BLD-Conference | 7/27/2011 | 7/28/2011 | 7/28/2011 | A | PASS |
Tony Young
|
|
|
take C. Westfall,, walk through,,, GACR
|
BLD-Conference | 7/22/2011 | 7/26/2011 | 7/26/2011 | P | PART |
Tony Young
|
|
|
1pm please-- John Phone #: ###-#### ?s on a future temp occupancy for admin part..
|
FIRE-Conference | 7/22/2011 | 7/26/2011 | 7/26/2011 | P | DONE |
Forrest France
|
|
|
Regarding project schedule and related FIR trade permit work.
|
BLD-Concrete | 7/13/2011 | 7/13/2011 | 7/13/2011 | P | PART |
Tony Young
|
|
|
JOHN Phone #: ###-####,, S. I. report
|
BLD-Footing | 7/11/2011 | 7/12/2011 | 7/12/2011 | A | PART |
Tony Young
|
|
|
john Phone #: ###-####,, Strata on site,, ok pending report
|
BLD-Footing | 7/5/2011 | 7/6/2011 | 7/6/2011 | P | PART |
Tony Young
|
|
|
john - pouring at 3:00 Phone #: ###-####,, ramp walls and piers,, ok pending special inspection report
|
BLD-Footing | 7/1/2011 | 7/1/2011 | 7/1/2011 | P | PART |
Tony Young
|
|
|
john -rebar - pouring at 1:30 - floor inspection also Phone #: ###-####,, ftgs for ADA ramp,, and 3 columns,, ok pending special inspection reports
|
BLD-Framing/Rough-in | 6/29/2011 | 6/29/2011 | 6/29/2011 | P | PART |
Tony Young
|
|
|
JOHN Phone #: ###-####,, under floor shear walls.. ok,,// . anchor bolts,, adding at ends of plates,, // epoxy shear holddowns ok pending special inspections
|
BLD-Footing | 6/23/2011 | 6/24/2011 | 6/24/2011 | A | PART |
Tony Young
|
|
|
john - rebar - pouring at 9 Phone #: ###-####,, pending special inspection report
|
BLD-Footing | 6/21/2011 | 6/22/2011 | 6/22/2011 | A | PART |
Tony Young
|
|
|
john - rebar inspection Phone #: ###-####,, some walls,, some footings on west side,, special inspectors on site
|
BLD-Footing | 6/16/2011 | 6/17/2011 | 6/17/2011 | A | PART |
Tony Young
|
|
|
JOHN Phone #: ###-####,, pending special inspection report,, had to have contractor dig out an area of footing to make it 12" thick,, also had a short rebar lap,, (8") al this was after 1st S. I. looked at the job.. fix is in progress and concrete tester and job super was laid out on what was required,,, then ok to pour
|