BLD-Final | 11/21/2011 | 11/23/2011 | 11/23/2011 | A | PASS |
Tony Young
|
|
|
MIke-Please call while doing inspection Phone #: ###-####
|
DOC - Permit Finaled | 11/23/2011 | 11/23/2011 | 11/23/2011 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 11/21/2011 | 11/21/2011 | 11/21/2011 | P | PART |
Tony Young
|
|
|
MIke-Please call while doing inspection Phone #: ###-####,, hand rails ok per 325 and 408,,, turn exception.. still need a protection post
|
BLD-Final | 11/15/2011 | 11/16/2011 | 11/16/2011 | A | FAIL |
Tony Young
|
|
|
Eric Phone #: ###-#### please call for access,,, need continous handrail,, need protection post in front of gas appliance,, seal firewall/ ceiling
|
BLD-Grading Inspection | 11/14/2011 | 11/14/2011 | 11/14/2011 | A | DONE |
Terry Records
|
|
|
Final grading and drainage approved
|
BLD-Other | 8/19/2011 | 8/22/2011 | 8/22/2011 | A | NR |
Jim Storey
|
|
|
eric Phone #: ###-####,, soffit and light boxes
|
BLD-Framing/Rough-in | 8/18/2011 | 8/19/2011 | 8/19/2011 | A | PART |
Tony Young
|
|
|
eric Phone #: ###-####,,, soffits,, lighting boxes,, work in progress
|
BLD-Energy code compliance | 8/10/2011 | 8/11/2011 | 8/11/2011 | A | PART |
Dave Hannah
|
|
|
mike Phone #: ###-#### ok to cover int but still needs can lights in sofits protected also crew on site double rocking sofits as thry cover
|
BLD-Other | 8/9/2011 | 8/10/2011 | 8/10/2011 | P | FAIL |
Mike Jordan
|
|
|
mike Phone #: ###-####,, soffits. Correction notice posted.
|
BLD-Energy code compliance | 8/9/2011 | 8/10/2011 | 8/10/2011 | P | FAIL |
Jim Storey
|
|
|
mike Phone #: ###-#### canlights in soffit must be boxed or ratted lights/ walls in attic need encapsulated.
|
BLD-Conference | 8/9/2011 | 8/9/2011 | 8/9/2011 | P | PART |
Tony Young
|
|
|
mike Phone #: ###-####,, conf on soffits,, need 2 layers
|
BLD-Framing/Rough-in | 8/8/2011 | 8/8/2011 | 8/8/2011 | P | PART |
Tony Young
|
|
|
Mike Phone #: ###-####,, frame ok,,, need another mech inspection,,, put a SWO on soffits,, they need 2 layers of 5/8",, (they were only putting 1 layer)
|
BLD-Conference | 8/5/2011 | 8/5/2011 | 8/5/2011 | P | PART |
Tony Young
|
|
|
Jason Phone #: ###-####,, conf with the framer
|
BLD-Framing/Rough-in | 8/5/2011 | 8/5/2011 | 8/5/2011 | A | NR |
Tony Young
|
|
|
blake - ###-####,, conf only
|
BLD-Framing/Rough-in | 8/3/2011 | 8/4/2011 | 8/4/2011 | A | FAIL |
Tony Young
|
|
|
mike Phone #: ###-####,, walk through only,, need to call for a on site conf.
|
BLD-Foundation | 5/12/2011 | 5/13/2011 | 5/13/2011 | A | PART |
Tony Young
|
|
|
Steve Phone #: ###-####,, poured
|
BLD-Footing | 5/10/2011 | 5/10/2011 | 5/10/2011 | P | PART |
Tony Young
|
|
|
|