Permit Information
Permit NumberBLD11-00507
StatusFinaled
Name GAFFORD CONSTRUCTION INC
Site Address 1620 W RIVER ST
Project NameINTERFAITH SANCTUARY
Customer Number 
ePlanReviewNo
Description
(INTERFAITH SANCTUARY HOUSING-MENS RESTROOM UPGRADE) Remodel to continue phased construction program for work required under an existing Upgrade Agreement (see BLD08-02236) on file. This phase to include upgrading the Men's restroom to current accessibility standards; create rooms designated as future shower and unisex restroom with perimeter walls and installing rough-in plumbing lines for future fixtures; added new walls re-define previous proposed sleeping areas to become Administration & Hospitality Rooms. Sleeping Unit #1-Single Men will be slightly increased in size and existing Sleeping Room 109A indicated for use for 6 residents will be reduced in size, all as indicated on reviewed plans. The scope of this permit will begin providing compliance for a portion of Phase 4 as indicated in upgrade agreement on file. NOTE: This building is fully fire sprinklered in accordance with requirements for "R" occupancy fire areas per Ch. 9, 2006 IBC. 4/25/12 - REDUCED SCOPE OF WORK CHANGE SUBMITTED REMOVING THE REPLACEMENT OF EXISTING 5 TON HVAC UNIT WITH NEW 4 TON UNIT. SEE COPY OF WRITTEN LIST OF CHANGES ATTACHED TO THIS PERMIT. drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  5/1/2012 DONE
DetailsAlexandra L. DeYoung
BLD-Final4/30/20124/30/20124/30/2012PPASS
DetailsDave Hannah
SHAUN PLEASE CALL 30 MIN BEFORE Phone #: ###-####
BLD-Other4/13/20124/13/20124/13/2012PPEND
DetailsDave Hannah
Entire scope of work must be completed prior to issuance of CO
BLD-Final4/10/20124/11/20124/11/2012AFAIL
DetailsDave Hannah
Shawn Phone #: ###-#### vert grab bars wrong location and needs to change permit to show that the hvac work was not done under this permit.
BLD-Final4/10/20124/10/20124/10/2012PDEFR
DetailsDave Hannah
Shawn Phone #: ###-####
FIRE-Final Inspection4/6/20124/9/20124/9/2012APASS
DetailsForrest France
Fire life safety finaled.
FIRE-Final Inspection4/5/20124/6/20124/9/2012APART
DetailsForrest France
BLD-Final4/5/20124/6/20124/9/2012PNR
DetailsDave Hannah
call 1/2 hr prior//Shawn Phone #: ###-####
FIRE-Conference4/6/20124/6/20124/6/2012PDONE
Details
One emergency light battery not functioning; Door knob needs lever action hardware; additional exit sign needed.
FIRE-Sprinkler Rough-in3/5/20123/5/20123/5/2012APART
DetailsForrest France
Overhead work at the remodel area approved for ceiling cover. Lacking coverage below an existing overhead garage door, system is due annual inspection.
BLD-Framing/Rough-in3/2/20123/2/20123/2/2012APART
DetailsDave Hannah
shaun - please call 1/2 hr prior - late afternoon please Phone #: ###-####ok to cover phase one mens rest rooms
BLD-Framing/Rough-in2/29/20123/1/20123/2/2012PCANC
DetailsDave Hannah
shaun - please call 1/2 hr prior - late afternoon please Phone #: ###-####
BLD-Conference2/28/20122/28/20122/28/2012PPART
DetailsBob Archibald
Dave H, Ron with HCD and I walked site and reviewed current status. Framing request will be requested soon.