Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD11-00519
StatusFinaled
Name BOISE CITY PUBLIC WORKS
Site Address 11818 W JOPLIN RD
Project Name 
Customer Number 
ePlanReviewNo
Description
City Of Boise Public Works - Struvite Production Building -To construct a new 2,315 square foot, multilevel one story building with a 1,520 square foot basement and related site improvements. This building will be constructed of masonry exterior walls with steel roof structure and metal roof decking. The basement contains a storage area and structural support for the five struvite reactors. The main level contains a Product Storage Area, a Chemical Storage Area, an Electrical Room and an Entry/Walkway Area. There is a 190 sq. ft. Separator Platform mezzanine with a roof access walkway. There is also approximately 470 sq. ft. of steel bar-grate equipment inspection walkways at 20 feet above the main entry floor level. The chemical storage room contain corrosive and toxic hazardous materials that exceed the maximum allowable quantities and requires compliance with all applicable H-4 Occupancy requirements. The H-4 Occupancy portion of this building is separated into a separate fire area by a three-hour fire-resistive fire barrier wall. The H-4 Occupancy portion of this building will be fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/2/201310/3/201310/3/2013APASS
DetailsJim Sly
Jim Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection10/2/201310/3/201310/3/2013APASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection9/5/20139/6/20139/6/2013AFAIL
DetailsTroy Cobbley
Provide city approved plans, provide fire extinguishers, repaire the exit signs, provide NFPA signage on the H occupancy doors, provide signage on the FACP/Electrical room doors and it appears that notes 1 - 7 have not been addressed for the ventilation.
FIRE-Final Inspection6/10/20136/11/20136/11/2013AFAIL
DetailsTroy Cobbley
Todays inspection was a cover for the underground supply line. Everything can be covered except for the locations of the thrust blocks which are not complete. Treasure valley fire is supervising the underground installation.
FIRE-Final Inspection6/10/20136/10/20136/10/2013PCANC
DetailsTroy Cobbley
Per Jeremiah the project is not ready for inspection. Will be rescheduled for inspection on underground supply piping to the fire sprinkler system.
FIRE-Final Inspection5/30/20136/4/20136/4/2013AFAIL
DetailsTroy Cobbley
The project related fire sprinkler permit needs to be addressed which includes all aspects of the underground supply piping to the fire sprinkler system. Also no city approved plans/notes were on site for an inspection.
BLD-Other9/25/20129/26/20129/26/2012APART
DetailsJim Sly
Roof inspection-Dave Jenkins Phone #: ###-####
Not quite complete .....but what is done is OK.
BLD-Framing/Rough-in8/1/20128/2/20128/2/2012PPART
DetailsJim Sly
Dave Phone #: ###-####
Looked at ceiling joist connections to ledger and to top of wall at pop out rooms from main bldg.....West and North ends. Reviewed letter from Engineer of record as to how to make these connections........ which is different from appr. plan. Engineer has also physically inspected the connections.
BLD-Final1/25/20121/26/20121/26/2012PNR
DetailsJim Sly
dave Phone #: ###-####
Looked at roof panels prior to installation.
BLD-Foundation11/8/201111/8/201111/8/2011PPART
DetailsJim Sly
Dave Phone #: ###-####
CMU grouting North Bldg section.
BLD-Footing10/21/201110/21/201110/21/2011PPART
DetailsJim Sly
Dave Phone #: ###-####
Footing and pad North side OK pending MTI special inspection tests and approvals.
BLD-Foundation10/7/201110/10/201110/10/2011APART
DetailsJim Sly
dave Phone #: ###-####
MTI on site......
BLD-Foundation10/4/201110/4/201110/4/2011PPART
DetailsJim Sly
Dave Phone #: ###-####
BLD-Concrete9/8/20119/8/20119/8/2011PPART
DetailsJim Sly
CMU-grout rebar inspection please-Dave Jenkins Phone #: ###-####
MTI on site.
BLD-Concrete9/1/20119/1/20119/1/2011PPART
DetailsJim Sly
CMU-rebar --Dave Jenkins Phone #: ###-####
Select wall OK pending MTI special insp, tests and approvals.
BLD-Footing8/25/20118/25/20118/25/2011PPART
DetailsJim Sly
dave - rebar Phone #: ###-####
OK pending MTI insp, tests and approvals.
BLD-Other8/17/20118/18/20118/18/2011APART
DetailsJim Sly
dave - CMU walls Phone #: ###-####
OK pend MTI special insp, tests and approvals.
BLD-Framing/Rough-in8/16/20118/16/20118/16/2011PPEND
DetailsJim Sly
Dave Jenkins-CMU inspection please Phone #: ###-####
OK pending MTI special insp tests and approvals.
BLD-Other8/8/20118/9/20118/9/2011ACANC
DetailsJim Sly
cmu block insp//Dave Jenkins Phone #: ###-####
OK pending MTI inspections, tests and approvals.
BLD-Foundation8/3/20118/4/20118/4/2011APASS
DetailsTom Arcoraci
dave Phone #: ###-#### spec insp
BLD-Foundation7/25/20117/26/20117/26/2011APART
DetailsJim Sly
dave Phone #: ###-####
Portion of North wall OK pending MTI special insp, tests and approvals.
BLD-Foundation7/20/20117/21/20117/21/2011APASS
DetailsTom Arcoraci
dave Phone #: ###-#### spec insp
BLD-Foundation7/15/20117/18/20117/19/2011PPART
DetailsTony Young
Dave Phone #: ###-####,, engineer will also inspect,, walls on tank and west wall on east structure
BLD-Foundation7/13/20117/13/20117/13/2011PPART
DetailsTom Arcoraci
dave Phone #: ###-####
BLD-Foundation7/11/20117/12/20117/12/2011APART
DetailsJim Sly
DAVE Phone #: ###-####East wall......OK Pendig MTI insp, tests & approvals
BLD-Foundation7/5/20117/6/20117/6/2011APART
DetailsJim Sly
Dave Phone #: ###-####
East wall ..4' high H occupancy....and South wall Main Bldg 8' high....OK pending MTI special insp, tests and approvals. Structural Engineer and Rick Cummings (City employee) have done visual inspections with pictures.
BLD-Foundation6/27/20116/28/20116/28/2011APART
DetailsJim Sly
dave Phone #: ###-####
Wall...OK pending MTI special insp, tests and approvals. Engineer has done a visual inspection on this wall.
BLD-Footing6/13/20116/13/20116/13/2011PPART
DetailsJim Sly
dave Phone #: ###-####
OK pending MTI special inspections, tests and approvals. Footing pads for main bldg and H occupancy .