Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD11-00544
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 11311 W CHINDEN BLVD
Project NameHP BLDG # 7
Customer Number 
ePlanReviewNo
Description
(HEWLETT PACKARD BLDG 7 - IPG SERVER ROOM) - To remodel a 5,439 sq. ft. area (3 rooms) within an existing office / storage / shipping building, for current and future I.T. infrastructure growth. Work to include: demolition work per plans; install a new raised access floor system, a new ceiling system with relocated lighting, a new hydraulic lift for equipment and ADA access; construct interior UL listed walls, doors and associated hardware per plans; install a new suspended soffit and acoustical ceiling grid systems; frame new interior walls suspended from roof structure; install new exterior concrete pads w/ mechanical units and exhaust systems that will serve the I.T. room; construct new exterior concrete stairs with metal handrails and guards; provide new exterior fascia and wall panel finishes; interior finishes in compliance with chapter 8 of the 2009 IBC; modify the existing fire alarm/sprinkler system to meet tenants needs and be in compliance with current adopted codes. Work per the approved plans, Engineering, and all other reviewing agencies approvals. NOTE: This building is fully sprinklered with 60 foot yards all around for unlimited area based on current occupancy use. A "Letter of Completion / Compliance" is required as a condition of occupancy for this tenant improvement. DRH10-00308 **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection8/26/20118/29/20118/31/2011APASS
DetailsForrest France
Fire life safety passed final inspection.
BLD-Final8/29/20118/30/20118/30/2011APASS
DetailsJim Sly
Wes Smith Phone #: ###-####
DOC - Permit Finaled8/30/20118/30/20118/30/2011PPASS
DetailsJim Sly
BLD-Final8/25/20118/26/20118/29/2011PCANC
DetailsJim Sly
wes - ###-####
FIRE-Final Inspection8/25/20118/26/20118/26/2011ADEFR
DetailsForrest France
FIRE-Sprinkler Rough-in6/3/20116/6/20116/6/2011APART
DetailsForrest France
Preliminary overhead inspection for fire sprinkler work at the new server room double interlock preaction system. Discussed plan review schedule, hydrostatic testing, heat at the riser room, seismic issues, as-builts for field mods, system impairments, cover inspections, etc.
FIRE-Conference6/3/20116/3/20116/3/2011ADONE
DetailsForrest France
Regarding project related fire sprinkler work.
BLD-Framing/Rough-in5/6/20115/6/20115/6/2011PPASS
DetailsJim Sly
WES Phone #: ###-####