FIRE-Final Inspection | 8/26/2011 | 8/29/2011 | 8/31/2011 | A | PASS |
Forrest France
|
|
|
Fire life safety passed final inspection.
|
BLD-Final | 8/29/2011 | 8/30/2011 | 8/30/2011 | A | PASS |
Jim Sly
|
|
|
Wes Smith Phone #: ###-####
|
DOC - Permit Finaled | 8/30/2011 | 8/30/2011 | 8/30/2011 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 8/25/2011 | 8/26/2011 | 8/29/2011 | P | CANC |
Jim Sly
|
|
|
wes - ###-####
|
FIRE-Final Inspection | 8/25/2011 | 8/26/2011 | 8/26/2011 | A | DEFR |
Forrest France
|
|
|
|
FIRE-Sprinkler Rough-in | 6/3/2011 | 6/6/2011 | 6/6/2011 | A | PART |
Forrest France
|
|
|
Preliminary overhead inspection for fire sprinkler work at the new server room double interlock preaction system. Discussed plan review schedule, hydrostatic testing, heat at the riser room, seismic issues, as-builts for field mods, system impairments, cover inspections, etc.
|
FIRE-Conference | 6/3/2011 | 6/3/2011 | 6/3/2011 | A | DONE |
Forrest France
|
|
|
Regarding project related fire sprinkler work.
|
BLD-Framing/Rough-in | 5/6/2011 | 5/6/2011 | 5/6/2011 | P | PASS |
Jim Sly
|
|
|
WES Phone #: ###-####
|