BLD-Final | 10/21/2011 | 10/21/2011 | 10/28/2011 | P | PASS |
Dave Hannah
|
|
|
Per 410
|
FIRE-Conference | 10/21/2011 | 10/21/2011 | 10/21/2011 | P | DONE |
Forrest France
|
|
|
Regarding finals.
|
FIRE-Final Inspection | 10/20/2011 | 10/20/2011 | 10/20/2011 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled. Inspection passed, signature card not available on site.
|
FIRE-Final Inspection | 8/19/2011 | 8/22/2011 | 8/23/2011 | A | NR |
Forrest France
|
|
|
Chris Jackson Phone #: ###-####
|
BLD-Final | 8/18/2011 | 8/19/2011 | 8/23/2011 | P | FAIL |
Dave Hannah
|
|
|
chris Phone #: ###-#### needs fire finals first
|
BLD-Other | 8/8/2011 | 8/8/2011 | 8/8/2011 | P | PASS |
Dave Hannah
|
|
|
ceiling grid insp// Jerry Phone #: ###-####
|
BLD-Energy code compliance | 7/12/2011 | 7/13/2011 | 7/13/2011 | P | PASS |
Dave Hannah
|
|
|
jerry Phone #: ###-####
|
BLD-Framing/Rough-in | 7/11/2011 | 7/12/2011 | 7/12/2011 | A | PART |
Dave Hannah
|
|
|
Jerry Phone #: ###-#### ok to insulate add one more 7 1/2 lvl over windows finish bolting seal plate add kickers to walls fire block furred out wall
|
BLD-Framing/Rough-in | 7/5/2011 | 7/6/2011 | 7/6/2011 | P | PART |
Jim Storey
|
|
|
Jerry Phone #: ###-#### exterior ok to cover/ interior ok to oneside.
|
BLD-Foundation | 6/10/2011 | 6/13/2011 | 6/13/2011 | P | FAIL |
Dave Hannah
|
|
|
stem wall//Jerry Phone #: ###-#### elevation of ftg and wall not to plan
|
BLD-Footing | 6/9/2011 | 6/10/2011 | 6/10/2011 | A | PASS |
Dave Hannah
|
|
|
Jerry Phone #: ###-####
|