BLD-Final | 10/21/2011 | 10/21/2011 | 10/21/2011 | P | PASS |
Mike Jordan
|
|
|
ok for perm. occ.
|
BLD-Final | 10/19/2011 | 10/19/2011 | 10/19/2011 | P | PART |
Mike Jordan
|
|
|
Need final letter from special inspection agency. Everything else ok.
|
BLD-Final | 10/18/2011 | 10/19/2011 | 10/19/2011 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer. moved to pm.
|
FIRE-Final Inspection | 10/18/2011 | 10/19/2011 | 10/19/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
FIRE-Final Inspection | 9/19/2011 | 9/19/2011 | 9/19/2011 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to final when the project related fire alarm permit has been passed.
|
FIRE-Final Inspection | 9/12/2011 | 9/13/2011 | 9/13/2011 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer Inspection cancelled from web by: Chris Palmer
|
BLD-Final | 9/12/2011 | 9/13/2011 | 9/13/2011 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer Inspection cancelled from web by: Chris Palmer
|
BLD-Final | 9/9/2011 | 9/12/2011 | 9/12/2011 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 9/9/2011 | 9/12/2011 | 9/12/2011 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Chris Palmer
|
BLD-Final | 9/6/2011 | 9/8/2011 | 9/8/2011 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer. Needs fire/life/safety.
|
FIRE-Final Inspection | 9/6/2011 | 9/7/2011 | 9/7/2011 | P | FAIL |
Troy Cobbley
|
|
|
Project is not ready for a final inspection due to the project related fire alarm permit. Per Ron Amandus, it is ok for Winco to begin moving in the items that are to be stored in this warehouse. No finals will be given until the fire alarm and all related life safety items have passed inspection.
|
FIRE-Alarm Testing | 9/6/2011 | 9/6/2011 | 9/6/2011 | P | CANC |
Troy Cobbley
|
|
|
No fire alarm testing was performed due to no permit for the fire alarm work. Stop work order was posted.
|
FIRE-Conference | 9/6/2011 | 9/6/2011 | 9/6/2011 | P | DONE |
Troy Cobbley
|
|
|
I found fire alarm work being performed without permits. I spoke to Jeremy with Allied General and Chris with ESI about the "stop work order" that I posted. Pictures of the stop work order and the installed devices were taken and sent to the fire alarm plan reviewer.
|
FIRE-Conference | 8/25/2011 | 8/25/2011 | 8/25/2011 | P | DONE |
Troy Cobbley
|
|
|
Went over racking issues with Chris Palmer
|
BLD-Energy code compliance | 8/17/2011 | 8/17/2011 | 8/17/2011 | P | PASS |
Mike Jordan
|
|
|
Wall insulation at the perimeter framing. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 8/15/2011 | 8/16/2011 | 8/16/2011 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer. Interior steel stud walls for payroll storage room and perimeter fur out walls.
|
BLD-Concrete | 7/7/2011 | 7/8/2011 | 7/8/2011 | P | DEFR |
Mike Jordan
|
|
|
CMU grout pour at 2pm. MTI will be onsite. Phone #: ###-#### >> Inspection requested via web by Chris Palmer. Special inspector on site.
|
BLD-Concrete | 7/6/2011 | 7/6/2011 | 7/6/2011 | P | DEFR |
Mike Jordan
|
|
|
Special inspector on site.
|
BLD-Concrete | 7/5/2011 | 7/6/2011 | 7/6/2011 | A | PART |
Mike Jordan
|
|
|
Grout pour at CMU scheduled for 9:30am and 3:00pm. MTI scheduled to be onsite for both pours. Phone #: ###-#### >> Inspection requested via web by Chris Palmer. AMsonry grout at west wall 8 to 12 ft. elev.
|
BLD-Concrete | 7/5/2011 | 7/5/2011 | 7/5/2011 | P | DEFR |
Mike Jordan
|
|
|
Masonry grout pour at 3pm today. MTI will be onsite. Phone #: ###-#### >> Inspection requested via web by Chris Palmer. Special inspector on site.
|
BLD-Concrete | 6/28/2011 | 6/28/2011 | 6/28/2011 | P | PASS |
Mike Jordan
|
|
|
Rebar mat for SOG Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Foundation | 6/27/2011 | 6/27/2011 | 6/27/2011 | P | PASS |
Mike Jordan
|
|
|
Inspection of the insulation around the stem walls under slab. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Foundation | 6/21/2011 | 6/21/2011 | 6/21/2011 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Footing | 6/17/2011 | 6/20/2011 | 6/20/2011 | A | PART |
Mike Jordan
|
|
|
Pouring concrete at 2pm for the stem walls and spread footings. If at all possible, would like to schedule inspection for 11:00am - noon. Thank You. Phone #: ###-#### >> Inspection requested via web by Chris Palmer. Perimeter stemwall and interior column pad footings. PEnding special inspection.
|
BLD-Concrete | 6/14/2011 | 6/16/2011 | 6/16/2011 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Footing | 6/14/2011 | 6/16/2011 | 6/16/2011 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer. Perimeter footings. Will have special inspection.
|