Permit Information
Permit NumberBLD11-00788
StatusFinaled
Name ESI
Site Address 650 N ARMSTRONG PL
Project NameWinco Foods Office TI
Customer Number 
ePlanReviewNo
Description
Winco General Office Remodel - PLAN MOD 11-9-2011 Add to original scope of work by demolition of interior non-bearing wall areas for new doorways to (8) new private offices created by dividing existing office's into two office's with new wall construction and finish; modify mechanical & electrical for new room layout per plan; interior partial height walls to create (8) work stations in open office areas.New work is between grid lines C.5 to D.5 and 7 to 9. Scope of work does not increase floor area, occupant load or change occupancy use group. Remainder of originally approved plans and all plan review notes and comments on plans are still a part of this review for plan mod. Separate permits are required for any modification to the fire sprinkler system or the alarm system before any work begins, as regulated by the fire department. drs To convert an existing 7,710 square foot open area into 43 new offices and two new multi-user accessible restrooms. This work is being done between grid lines 9&11 and C.5&E.8. To construct four new workstations between grids 8&9 at grid line E.8. To demo 11 workstations and replace with three large offices north of grid line F, between grid lines 7&8. Demo and remove partitions between four offices to create two larger open areas 67 and 68. Add two new workstations north of grid line E and west of grid line 8. To add a partition at large storage area to create HIPPA Storage Room 04 and Plan Storage Room 05. This building is fully fire sprinkled and sprinklers are used for building area increase. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection1/3/20121/4/20121/4/2012APASS
DetailsTroy Cobbley
Life safety passed
BLD-Final1/3/20121/4/20121/4/2012APASS
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Chris Palmer. OK for perm occ.
FIRE-Alarm Testing12/29/201112/30/201112/30/2011PNR
DetailsForrest France
Final Fire Alarm test to be completed. Addition of (3) H/S. As discussed, late afternoon (4:30) is beneficial. Thanks Phone #: ###-#### >> Inspection requested via web by Chris Palmer
BLD-Final12/15/201112/15/201112/15/2011PNR
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
FIRE-Conference12/13/201112/13/201112/13/2011PDONE
DetailsTroy Cobbley
Chris with ESI and myself discussed the requirements for notification devices that will need to be installed in the new four person offices. There are two of these offices. I also verified spacing for the new notification device that was added in the conference room as referenced on the previous correction notice.
BLD-Framing/Rough-in11/29/201111/30/201111/30/2011PPASS
DetailsMike Jordan
Inspection of the grid patch back in the new office build out. I can meet onsite at 3:30 pm if necessary. Thanks! Phone #: ###-#### >> Inspection requested via web by Chris Palmer
BLD-Framing/Rough-in11/21/201111/22/201111/22/2011ACANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Chris Palmer. Interior steel stud demissing walls for new offices and cubicles, phase 2.
BLD-Final10/31/201110/31/201110/31/2011APART
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Chris Palmer. Ok to occupy phase 2 only. Needs to submit plan mod for additional work.
FIRE-Final Inspection10/31/201110/31/201110/31/2011AFAIL
DetailsTroy Cobbley
Life safety in phase II is passed.
BLD-Other10/12/201110/12/201110/12/2011PPASS
DetailsMike Jordan
Grid patch in inspection in the new TI space. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
BLD-Final10/8/201110/10/201110/10/2011PCANC
DetailsMike Jordan
Above Ceiling Final. Phone #: ###-#### >> Inspection requested via web by Craig Leavitt Inspection cancelled from web by: Craig Leavitt
BLD-Final10/4/201110/4/201110/4/2011PCANC
DetailsMike Jordan
New restrooms final. Please call for building access. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
BLD-Conference10/4/201110/4/201110/4/2011PPART
DetailsMike Jordan
Inspection on completed restrooms. All life sfaety is operational, ada ok. Ok to use pending plumbing ok.
BLD-Framing/Rough-in9/19/20119/20/20119/20/2011PPASS
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Chris Palmer. Interior steel stud framed walls for new offices were records storage was previously.
BLD-Framing/Rough-in8/15/20118/16/20118/16/2011PPASS
DetailsMike Jordan
Restroom framing inside the existing general office building. Phone #: ###-#### >> Inspection requested via web by Chris Palmer. Interior steel stud walls for new restroom.
BLD-Concrete8/8/20118/8/20118/8/2011PPASS
DetailsMike Jordan
Plumbing trenches for new restrooms in the existing general office Phone #: ###-#### >> Inspection requested via web by Chris Palmer
BLD-Framing/Rough-in8/3/20118/3/20118/3/2011PPASS
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by Chris Palmer office walls ok
FIRE-Final Inspection7/26/20117/26/20117/26/2011APART
DetailsTroy Cobbley
Partial final for the Phase I portion of the TI. See the city approved plans for three new offices, storage room and HIPA storage room where life safety is passed. Near the three new offices there are two overspaced sprinklers and fire alarm audio/visual modifications that are needed.
BLD-Other7/25/20117/25/20117/25/2011PPASS
DetailsTom Arcoraci
Phase I Partial Final Phone #: ###-#### >> Inspection requested via web by Chris Palmer ok pending fire ok
BLD-Framing/Rough-in7/1/20117/1/20117/1/2011APART
DetailsMike Jordan
Framing in the Phase I of the GO TI Phone #: ###-#### >> Inspection requested via web by Chris Palmer. Interior steel stud framed walls at phase 1, needs to remoce screws from topplates to grid and support wall to structure. Also pend. electrical inspection.
BLD-Framing/Rough-in6/30/20116/30/20116/30/2011PNR
DetailsMike Jordan
Phase I section of General Office TI Phone #: ###-#### >> Inspection requested via web by Chris Palmer