Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberBLD11-01031
StatusFinaled
Name CM COMPANY
Site Address 130 E MALLARD DR
Project NamePlaza Apartments
Customer Number 
ePlanReviewNo
Description
(PLAZA APARTMENTS – FLOOR JOIST HANGER REPAIRS) To repair a portion of the existing floor system due to floor joist hangers failing. PLAN MODIFICATION 1-17-12 – Modification submitted to include additional structural engineering onto this permit. Additional engineering includes: grid “M” beam replacement, grid “G” beam replacement, wood column repairs, wood joist replacement, and overhead walkway deck calculations. **TLW** Work to include: Removal of sheetrock and installation of new ledger support. Approved per engineered plans, plan review report, and structural calculations. PLAN MODIFICATION 1-17-12 – Modification submitted to include additional structural engineering onto this permit. Additional engineering includes: grid “M” beam replacement, grid “G” beam replacement, wood column repairs, wood joist replacement, and overhead walkway deck calculations. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Other3/8/20133/29/20133/29/2013ADONE
DetailsTom Arcoraci
Follow up..Check status and maintenance
DOC - Permit Finaled3/29/20133/29/20133/29/2013PPASS
DetailsTom Arcoraci
BLD-Final3/29/20133/29/20133/29/2013PPASS
DetailsTom Arcoraci
Follow up..Check status and maintenance ok
BLD-Conference10/31/201211/1/201211/1/2012APASS
DetailsJim Storey
ben ###-#### fire resiatave membrane complet and firestopping done / walkway skim coat in progress ok will be complet in aprox. 1 wk.
BLD-Conference10/31/201210/31/201210/31/2012PDEFR
DetailsTom Arcoraci
ben Phone #: ###-####
BLD-Other9/13/20129/14/20129/14/2012APASS
DetailsJim Storey
structural to cover basement ceiling, and planter repairs//Ben Mclenna Phone #: ###-#### framing and water mangment of planters tested and aproved for gyp aplacation of ceilling .
BLD-Other7/17/20127/18/20127/18/2012PPASS
DetailsJim Storey
Status update? meet ben to review job progress. all post and beam const. complet per engineer of records oversite. membrane and diphram installed except for one area pending observation of joist uncovered that may need replaced. scott will be by the afternoon to make this discition.. walkways framed out and ready for membrane as son as the last colm. is stablaized. letter will be forthcomimg from scott upon completion fof all strucrual observation.
BLD-Other3/2/20123/2/20123/9/2012PPEND
DetailsBob Archibald
Reviewed project status with Jim S.
BLD-Conference3/5/20123/5/20123/5/2012PPART
DetailsJim Storey
meet engineer of record on site. review of glb and floor joist repair. to be revised as to conditions.
BLD-Other2/29/20123/1/20123/2/2012APART
DetailsJim Storey
insp for beam and planter//Ben Mclenna Phone #: ###-#### discused issues w/scott eng. will meet next wk.
BLD-Other1/31/20122/3/20122/3/2012APASS
DetailsJim Storey
ben - columns for the walkways - please call 1/2 hr prior Phone #: ###-#### all colums but two are complet as well as ledger angle instaled g line beam and colums are part of the beam replacment as a plan mod that was discuvered at colum repair. contractor is having steel fab and matrial orded and will e-mail me with a time line as to when this will be ready to begin instaltion.
BLD-Conference8/19/20118/19/20118/22/2011PPASS
DetailsJim Storey
400 pm apointment
BLD-Final2/7/20132/7/2013 P 
DetailsJim Storey
ben Phone #: ###-####