BLD-Final | 8/4/2011 | 8/8/2011 | 8/8/2011 | A | PASS |
Dave Hannah
|
|
|
ben Phone #: ###-#### ok for perm occ per Jim storey after fire finalss
|
FIRE-Final Inspection | 7/7/2011 | 8/5/2011 | 8/5/2011 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 8/3/2011 | 8/4/2011 | 8/4/2011 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 7/5/2011 | 7/7/2011 | 7/7/2011 | P | NR |
Jim Storey
|
|
|
ken Phone #: ###-####
|
FIRE-Final Inspection | 7/5/2011 | 7/7/2011 | 7/7/2011 | A | PART |
Troy Cobbley
|
|
|
A 30 day temporary occupancy for life safety was given with Gordan's permission until the fire alarm is addressed.
|
FIRE-Conference | 7/6/2011 | 7/6/2011 | 7/6/2011 | A | DONE |
Troy Cobbley
|
|
|
Amy did not arrive but another lady did and I let her know that Gordan with the Boise Fire Dept was ok with a 30 day temporary occupancy as long as the door hardware and the fire sprinklers were addressed. This would leave the fire alarm modifications needing to be completed.
|
FIRE-Final Inspection | 7/5/2011 | 7/5/2011 | 7/6/2011 | P | FAIL |
Troy Cobbley
|
|
|
No items on the correction notice have been addressed.
|
BLD-Final | 7/5/2011 | 7/5/2011 | 7/5/2011 | P | NR |
Tom Arcoraci
|
|
|
Ben Phone #: ###-####
|
FIRE-Final Inspection | 7/1/2011 | 7/1/2011 | 7/1/2011 | P | FAIL |
Troy Cobbley
|
|
|
Provide single action hardware on the restroom and breakroom doors. Replace all painted sprinkler heads as discussed and per NFPA 13 6.2.6.2. Provide for fire alarm notification in the restroom, washroom and breakroom. This work will require permit. Situation was discussed with Ben.
|
BLD-Final | 6/30/2011 | 6/30/2011 | 6/30/2011 | P | NR |
Dave Hannah
|
|
|
Ben-Please call prior to inspection Phone #: ###-#### needs other trades finaled first
|