BLD-Final | 10/10/2011 | 10/11/2011 | 10/11/2011 | A | PASS |
Jim Sly
|
|
|
cody Phone #: ###-#### C/C issued
|
DOC - Permit Finaled | 10/11/2011 | 10/11/2011 | 10/11/2011 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 10/5/2011 | 10/6/2011 | 10/6/2011 | A | NR |
Jim Sly
|
|
|
RYAN Phone #: ###-#### Need Mech, Mech F/P, Electr finals and copy of Foam/seal inspection and approval or Blower door test approval.
|
BLD-Energy code compliance | 8/12/2011 | 8/15/2011 | 8/15/2011 | A | PASS |
Jim Sly
|
|
|
ryan Phone #: ###-####
|
BLD-Framing/Rough-in | 8/12/2011 | 8/12/2011 | 8/12/2011 | P | PART |
Jim Sly
|
|
|
Cody phone ###-#### ###-#### Misc. corr....OK to insulate
|
BLD-Framing/Rough-in | 8/11/2011 | 8/12/2011 | 8/12/2011 | A | CANC |
Jim Sly
|
|
|
Ryan or ###-#### for Cody Phone #: ###-#### Re-sched....
|
BLD-Conference | 8/11/2011 | 8/12/2011 | 8/12/2011 | A | CANC |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 8/9/2011 | 8/11/2011 | 8/11/2011 | A | NR |
Jim Sly
|
|
|
Ryan Phone #: ###-#### Need to meet Contr and Framer at jobsite.
|
BLD-Footing | 6/27/2011 | 6/28/2011 | 6/28/2011 | P | PART |
Jim Sly
|
|
|
bill Phone #: ###-#### Advised concrete contractor of Engineering required for tall wing walls at garage. Engineering shows special bolts for hold downs and rebar specific for hold down area. Contractor working on this area. Advised to talk to Engineer and owner of Concrete Co. prior to pour.
|
BLD-Conference | 6/27/2011 | 6/28/2011 | 6/28/2011 | A | CANC |
Jim Sly
|
|
|
|
BLD-Footing | 6/24/2011 | 6/27/2011 | 6/27/2011 | P | PASS |
Jim Sly
|
|
|
Bill Phone #: ###-####
|