FIRE-Final Inspection | 5/10/2012 | 5/11/2012 | 5/11/2012 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 5/11/2012 | 5/11/2012 | 5/11/2012 | P | PASS |
Tom Arcoraci
|
|
|
nate Phone #: ###-####
|
BLD-Final | 4/18/2012 | 4/19/2012 | 4/19/2012 | A | DONE |
Tom Arcoraci
|
|
|
Nate Phone #: ###-####
|
BLD-Final | 4/18/2012 | 4/18/2012 | 4/18/2012 | P | PASS |
Tom Arcoraci
|
|
|
Nate Phone #: ###-#### ok for temp occ
|
FIRE-Final Inspection | 4/16/2012 | 4/17/2012 | 4/17/2012 | A | PART |
Troy Cobbley
|
|
|
A temporary is being given for the fire life safety inspection until the bollards and parking lot is finished. This is per Romeo Gervais.
|
FIRE-Conference | 4/16/2012 | 4/16/2012 | 4/16/2012 | P | DONE |
Troy Cobbley
|
|
|
Met Darren and went over the signage requirement for fire dept access. I also noted that a 5,000 or 6,000 gallon carbon dioxide tank that had not been shown on the plans is now installed along the north property line. I contacted scott arellano and he was ok with the installation of the tank and no additional submittal were to be required. Darren also asked about the bollards at the north side tanks. I deferred him to the fire chief since their installation does not match IFC 318.
|
BLD-Final | 4/12/2012 | 4/12/2012 | 4/13/2012 | P | NR |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 4/10/2012 | 4/12/2012 | 4/12/2012 | P | FAIL |
Troy Cobbley
|
|
|
(1) The vehicle protection "bollards", required per the IFC do not meet section 312.2, 1, 2 and 5 for spacing between posts, filled with concrete or 3'-0" clearance from the propane tank. (2) The LOX tank has not been installed to verify the 5'-0" clearance from the property line. (3) Provide fire dept access signage per review note #8 (4) Finish mounting the fire extinguishers. (5) Provide the missing exits signs and repair the exit discharge and interior emergency lights. (6) Mount and test the fire sprinkler exterior alarm bell (7) The fire alarm system manual pull station is mounted too high and needs to be lowered. (8) United Water has not turned on the water supply for the fire sprinkler system therefore the forward flush could not be performed or any alarms for flow tested. (9) Repair the 6" sprinkler hanger at the top of the dry pipe system that has been disconnected. There may be other items added to the list once actual testing can be performed. Per the drawings and the electrical contractor the electrical service is less than the 1,200 ampers therefore panic hardware is not required on the electrical room.
|
BLD-Final | 4/10/2012 | 4/12/2012 | 4/12/2012 | A | NR |
Tom Arcoraci
|
|
|
nate Phone #: ###-####
|
BLD-Other | 3/14/2012 | 3/15/2012 | 3/15/2012 | A | PASS |
Tom Arcoraci
|
|
|
Grid ceiling -- Darrin Phone #: ###-####
|
BLD-Footing | 2/9/2012 | 2/10/2012 | 2/10/2012 | A | PASS |
Tom Arcoraci
|
|
|
darrin - concrete pour at 10:00 Phone #: ###-####
|
BLD-Conference | 2/1/2012 | 2/1/2012 | 2/1/2012 | P | PASS |
Tom Arcoraci
|
|
|
eng says 2500 psi min ok for tank slab
|