BLD-Final | 2/27/2012 | 2/28/2012 | 2/28/2012 | A | PASS |
Mike Jordan
|
|
|
Rob Phone #: ###-####. ok for perm occ.
|
BLD-Final | 2/24/2012 | 2/27/2012 | 2/27/2012 | A | NR |
Mike Jordan
|
|
|
Rob Phone #: ###-####. Everything ok, needs zoning to sign off first.
|
FIRE-Final Inspection | 2/23/2012 | 2/23/2012 | 2/23/2012 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 2/22/2012 | 2/23/2012 | 2/23/2012 | A | FAIL |
Troy Cobbley
|
|
|
Provide the missing door hardware and the missing exit sign. Rescheduled for this afternoon.
|
BLD-Energy code compliance | 1/12/2012 | 1/12/2012 | 1/12/2012 | P | PASS |
Mike Jordan
|
|
|
rob Phone #: ###-####
|
BLD-Other | 1/3/2012 | 1/4/2012 | 1/4/2012 | A | PASS |
Mike Jordan
|
|
|
Rob Phone #: ###-####. Interior shear walls and holdowns, added hold downs on exterior walls at phase 2.
|
FIRE-Final Inspection | 12/8/2011 | 12/9/2011 | 12/9/2011 | A | PART |
Troy Cobbley
|
|
|
The east side remodeled area life safety is passed.
|
FIRE-Final Inspection | 12/7/2011 | 12/8/2011 | 12/8/2011 | P | FAIL |
Troy Cobbley
|
|
|
This inspection was for the east side remodeled area only. The two exit discharge lights need to be repaired. Also a fire alarm sytem is shown to be installed but has not been. It appears to be only there to monitor the duct smoke detectors. I told the contractor that the remote annunciators as installed are ok if the fire alarm panel is installed. If it is not installed then the correct remote annunciators need to be installed. The duct smoke detectors will need to be tested when a decision has been made.
|
BLD-Other | 10/11/2011 | 10/12/2011 | 10/12/2011 | P | PASS |
Mike Jordan
|
|
|
Soffit shear---Request early---Rob Phone #: ###-####
|
BLD-Framing/Rough-in | 10/4/2011 | 10/5/2011 | 10/5/2011 | A | PASS |
Mike Jordan
|
|
|
rob Phone #: ###-####Sofitt and barrel cieling ok.
|
BLD-Framing/Rough-in | 9/26/2011 | 9/27/2011 | 9/27/2011 | A | PART |
Mike Jordan
|
|
|
steel stud framing//Rob Phone #: ###-####. Interior steel stud walls only ok to cover. Need framing details for barrell ceiling. Aslo need to verifiy additional holdowns at extrior shear wall locations.
|
BLD-Other | 9/20/2011 | 9/21/2011 | 9/21/2011 | P | PASS |
Mike Jordan
|
|
|
insulation and shear wall//Rob Phone #: ###-####. Wall and roof insulation on clere story ok. Nailing and hold downs on both interior shear walls ok.
|
BLD-Conference | 9/13/2011 | 9/14/2011 | 9/14/2011 | A | DONE |
Mike Jordan
|
|
|
Rob Phone #: ###-####
|
BLD-Wall cover | 9/9/2011 | 9/9/2011 | 9/9/2011 | P | PASS |
Mike Jordan
|
|
|
SHEAR ROOF---Rob Phone #: ###-####. Nails were used as per approved plan. roof ok, clere story ok.
|
BLD-Framing/Rough-in | 9/1/2011 | 9/2/2011 | 9/2/2011 | A | FAIL |
Mike Jordan
|
|
|
Rob Phone #: ###-####. Needs to provide staple equivelabcy chart from engineer for shear walls on clere story and for osb attachment on clere story.
|
BLD-Foundation | 8/8/2011 | 8/9/2011 | 8/9/2011 | A | PASS |
Mike Jordan
|
|
|
Rob Phone #: ###-####. Stemwall for new vault wall. Also discussed required special inspections for project.
|
BLD-Footing | 8/3/2011 | 8/5/2011 | 8/5/2011 | P | PASS |
Tom Arcoraci
|
|
|
Rob Phone #: ###-####
|