FIRE-Final Inspection | 8/24/2012 | 8/24/2012 | 8/24/2012 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 8/24/2012 | 8/24/2012 | 8/24/2012 | P | PASS |
Jim Sly
|
|
|
OK for Perm Occ.
|
FIRE-Alarm Testing | 8/24/2012 | 8/24/2012 | 8/24/2012 | P | DONE |
Troy Cobbley
|
|
|
Alarm testing was previously completed.
|
BLD-Final | 8/6/2012 | 8/10/2012 | 8/10/2012 | A | PART |
Jim Sly
|
|
|
ROB Phone #: ###-#### Temp Occ OK for 1st and 2nd floors bldg C (tower 3)
|
FIRE-Final Inspection | 8/9/2012 | 8/10/2012 | 8/10/2012 | A | PART |
Troy Cobbley
|
|
|
Life safety has passed in area "C" first and second floors. To final this building the signage needs to be provided at the fire control room doors and the fire alarm permit finaled.
|
FIRE-Final Inspection | 8/6/2012 | 8/9/2012 | 8/9/2012 | P | FAIL |
Troy Cobbley
|
|
|
Second floor of area "C" life safety passed but the first floor still has sprinkler pendants taped off and smoke alarms with covers on so it could not pass
|
BLD-Final | 8/2/2012 | 8/3/2012 | 8/3/2012 | P | PART |
Jim Sly
|
|
|
occ for 3rd flr//Rob Phone #: ###-#### Temp Occ. OK for 3rd floor ....Tower 3.
|
FIRE-Final Inspection | 8/2/2012 | 8/3/2012 | 8/3/2012 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed for the 3rd floor of area "C"
|
BLD-Final | 7/27/2012 | 7/27/2012 | 7/27/2012 | P | PART |
Jim Sly
|
|
|
4th Floor Temp Occupancy Inspection Phone #: ###-#### >> Inspection requested via web by Rob Fraser OK for Temp Occ. of 4th floor only.
|
BLD-Final | 7/25/2012 | 7/27/2012 | 7/27/2012 | A | NR |
Jim Sly
|
|
|
Inspection for 3rd and 4th floors of Tower 3. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
|
FIRE-Final Inspection | 7/27/2012 | 7/27/2012 | 7/27/2012 | P | PART |
Troy Cobbley
|
|
|
The life safety for the 4th floor Area "C" passed.
|
BLD-Final | 7/25/2012 | 7/26/2012 | 7/27/2012 | P | NR |
Jim Sly
|
|
|
Final inspection for 4th floor Tower 3. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
|
FIRE-Alarm Testing | 7/24/2012 | 7/24/2012 | 7/24/2012 | P | DONE |
Troy Cobbley
|
|
|
Todays test was for the smoke alarms for the third floors of Area "C". The smoke alarms passed testing. The fourth floor could not be tested due to capet work in the corridor.
|
FIRE-Conference | 6/27/2012 | 6/28/2012 | 6/28/2012 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection was for fire life safety for 3rd and 4th floors of Tower 1 and Tower 2. Items needing completed are smoke alarm testing for tower 2 for both the third and fourth floors due to covers still being in place on the smoke alarms. Also there are still protective tape on several sprinkler heads. A smoke alarm in one bedroom of room 302 did not activate the other smoke alarms.
|
FIRE-Conference | 5/21/2012 | 5/21/2012 | 5/21/2012 | P | DONE |
Troy Cobbley
|
|
|
Rod and I went over life safety requirements. I went over the three options for fire dept access designation. The fire hydrant in the northwest corner of the property needs the 5" outlet turned to where it is accessible to the fire dept. A knox box needs to be provided. It appears that exit sign/emergency lights, if placed per plans, will be adequate. The "area of refuge" is noted in the fire dept review as being placed in the stairwells with the requirements for communication. Per Rod the "area of refuge" is in the main corridor. I deferred that any changes will need to be requested through Scott Arellano in plan review. I suggested that the architect become involved.
|
BLD-Framing/Rough-in | 4/27/2012 | 4/30/2012 | 4/30/2012 | A | PASS |
Jim Sly
|
|
|
Cover inspection for 1st floor units of Tower 3. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
|
FIRE-Conference | 4/27/2012 | 4/27/2012 | 4/27/2012 | P | DONE |
Troy Cobbley
|
|
|
The standpipe hose valves located on all of the floors at the fire wall per the sprinkler plans were to be mounted recessed in the corridor walls. They have been installed surface mounted on the walls and are possibly encroaching into the egress path. After speaking to Dan Stuart, I spoke to the job site superintendant about having the architect submit to the plan reviewer for approval of this installation.
|
BLD-Conference | 4/23/2012 | 4/24/2012 | 4/25/2012 | P | PASS |
Jim Sly
|
|
|
Cover inspection for 1st, 2nd, 3rd, 4th floors for corridor rated ceilings. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
|
BLD-Conference | 4/23/2012 | 4/24/2012 | 4/24/2012 | A | FAIL |
Jim Sly
|
|
|
Cover inspection for 1st, 2nd, 3rd, and 4th floor corridor rated ceilings. Phone #: ###-#### >> Inspection requested via web by Rob Fraser Need to complete fire caulking.
|
BLD-Wall cover | 4/19/2012 | 4/19/2012 | 4/20/2012 | P | NR |
Jim Sly
|
|
|
Inspection for cover for 1st, 2nd, 3rd, 4th floor corridor ceilings for Tower 3 (Building C). Phone #: ###-#### >> Inspection requested via web by Rob Fraser
|
BLD-Framing/Rough-in | 4/12/2012 | 4/13/2012 | 4/15/2012 | P | PASS |
Jim Sly
|
|
|
Inspection for all units on 3rd and 2nd floor in Building C - "Tower 3" for cover. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
|
BLD-Framing/Rough-in | 4/11/2012 | 4/11/2012 | 4/11/2012 | P | CANC |
Jim Sly
|
|
|
Rob phone
|
BLD-Energy code compliance | 4/10/2012 | 4/10/2012 | 4/11/2012 | A | PASS |
Jim Sly
|
|
|
Fire caulking and energy compliance inspection for cover: Units 435, 436, 437, 438, 439, 440. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
|
BLD-Energy code compliance | 4/9/2012 | 4/10/2012 | 4/10/2012 | P | NR |
Mike Jordan
|
|
|
Fire caulking and energy compliance inspection for cover: Units 435, 436, 437, 438, 439, 440. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
|
BLD-Framing/Rough-in | 4/3/2012 | 4/4/2012 | 4/4/2012 | A | PASS |
Jim Sly
|
|
|
corridor 5 rm# 479//Rob Phone #: ###-####
|
BLD-Other | 3/20/2012 | 3/20/2012 | 3/20/2012 | P | PASS |
Jim Sly
|
|
|
rob - cover inspection for unit 428, 429, 430, 431, 432, 433, and 434 - also 184 and 186 Phone #: ###-####
|
BLD-Foundation | 10/3/2011 | 10/3/2011 | 10/3/2011 | P | PART |
Mike Jordan
|
|
|
frazier - wall - pouring at 2 Phone #: ###-####. Work in progress on stemwalls. Will have special inspection.
|