BLD-Final | 11/28/2011 | 11/29/2011 | 11/29/2011 | A | PASS |
Dave Hannah
|
|
|
request 10am//Ron Phone #: ###-#### ok for perm occ
|
BLD-Aging Inspection | 11/23/2011 | 11/23/2011 | 11/28/2011 | | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 9/23/2011 | 9/23/2011 | 9/26/2011 | P | PASS |
Dave Hannah
|
|
|
walked project with cont and owner
|
BLD-Final | 9/21/2011 | 9/22/2011 | 9/22/2011 | P | PART |
Dave Hannah
|
|
|
Bruce Phone #: ###-#### ok for temp occ needs a letter to Jason about not using second floor for now and getting permits later for second floor and stair remodel everything on first floor is ok
|
FIRE-Final Inspection | 9/22/2011 | 9/22/2011 | 9/22/2011 | P | PASS |
Forrest France
|
|
|
Noted C/N items verified for completion. Fire life safety finaled.
|
FIRE-Final Inspection | 9/21/2011 | 9/22/2011 | 9/22/2011 | A | PART |
Forrest France
|
|
|
Items to be finished prior to final include; max occupant sign per review notes, knox box installation, signage at the riser room door, current inspection tag on the fire riser, provide approved hardware at three exit doors from hall 105 as discussed and per approved plans and review notes.
|
FIRE-Conference | 9/21/2011 | 9/21/2011 | 9/21/2011 | A | DONE |
Forrest France
|
|
|
Regarding fire life safety conditions for occupancy approval.
|
BLD-Framing/Rough-in | 9/15/2011 | 9/16/2011 | 9/16/2011 | A | PASS |
Dave Hannah
|
|
|
bruce - after 10:00 please - call 1/2 hr prior Phone #: ###-####
|
BLD-Framing/Rough-in | 9/1/2011 | 9/1/2011 | 9/2/2011 | P | PART |
Dave Hannah
|
|
|
ceiling gride ok most of the rooms are old grid with new tiles and lights checked every thing on first floor only found two lights that they missed wires on they will fix them. I will ckeck them on inspection of fire wall around stirs
|
BLD-Framing/Rough-in | 8/11/2011 | 8/11/2011 | 8/11/2011 | P | PASS |
Mike Jordan
|
|
|
Bruce Phone #: ###-####. Steel stud interior framed infill walls on 1st. floor. ok.
|