BLD-Final | 11/21/2011 | 11/22/2011 | 11/22/2011 | A | PASS |
Dave Hannah
|
|
|
matthew Phone #: ###-####
|
BLD-Final | 11/7/2011 | 11/8/2011 | 11/8/2011 | A | PART |
Dave Hannah
|
|
|
Matthew Phone #: ###-#### ok for temp occ needs to finish plumbing
|
BLD-Final | 11/3/2011 | 11/4/2011 | 11/4/2011 | A | PART |
Dave Hannah
|
|
|
matthew Phone #: ###-#### needs to get fire final and finish plumbing
|
FIRE-Final Inspection | 11/3/2011 | 11/4/2011 | 11/4/2011 | A | PASS |
Forrest France
|
|
|
Fire life safety passed pending signage at the main entry/exit and removal of the manual thumbturn. To be completed prior to structural final as discussed.
|
FIRE-Final Inspection | 11/2/2011 | 11/3/2011 | 11/3/2011 | A | NR |
Forrest France
|
|
|
Missing signage at the main entry/exit, remove manual thumbturn at the storefront door, post permanent suite address, missing SD at the electrical room for the new fire alarm NAC panel.
|
BLD-Framing/Rough-in | 10/19/2011 | 10/20/2011 | 10/20/2011 | A | PASS |
Dave Hannah
|
|
|
perry - ceiling grid Phone #: ###-####
|
BLD-Framing/Rough-in | 10/4/2011 | 10/4/2011 | 10/5/2011 | P | PART |
Dave Hannah
|
|
|
perry Phone #: ###-#### ok to cover plumbing wall
|
BLD-Framing/Rough-in | 9/8/2011 | 9/8/2011 | 9/9/2011 | P | DONE |
Dave Hannah
|
|
|
Perry Phone #: ###-####
|
BLD-Framing/Rough-in | 9/8/2011 | 9/9/2011 | 9/9/2011 | A | PART |
Dave Hannah
|
|
|
Perry Phone #: ###-#### ok to cover all but plumbing walls
|