BLD-Final | 2/27/2012 | 2/27/2012 | 2/27/2012 | P | PASS |
Mike Jordan
|
|
|
Junior Phone #: ###-####. ok for perm occ.
|
BLD-Aging Inspection | 1/23/2012 | 1/23/2012 | 1/25/2012 | | DONE |
Mike Jordan
|
|
|
Spoke to Junior with HCD, he noted that rated glazing should be here by the end of Jan 2012.
|
BLD-Final | 11/21/2011 | 11/22/2011 | 11/22/2011 | A | PART |
Mike Jordan
|
|
|
Please call 30 min before thanks Phone #: ###-#### >> Inspection requested via web by Les Seal. Ok for temp occ. only. Will be ok for perm occ. once plumbing is perm. and firerated glazing is installed in place of temp. 1hr. wall.
|
BLD-Final | 11/21/2011 | 11/21/2011 | 11/21/2011 | P | NR |
Mike Jordan
|
|
|
junior Phone #: ###-####
|
FIRE-Final Inspection | 11/21/2011 | 11/21/2011 | 11/21/2011 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
BLD-Conference | 11/18/2011 | 11/18/2011 | 11/18/2011 | P | DONE |
Mike Jordan
|
|
|
junior Phone #: ###-####
|
FIRE-Conference | 11/17/2011 | 11/17/2011 | 11/17/2011 | P | DONE |
Troy Cobbley
|
|
|
For a final on this project we need to test the smoke alarms, exit signs/emergency lights, and verify hardware.
|
BLD-Final | 11/14/2011 | 11/14/2011 | 11/14/2011 | P | CANC |
Mike Jordan
|
|
|
Please call junior 30 min before Phone #: ###-#### >> Inspection requested via web by Les Seal. Cancelled by contractor via phone call.
|
FIRE-Conference | 11/14/2011 | 11/14/2011 | 11/14/2011 | A | DONE |
Troy Cobbley
|
|
|
I went over life safety notes with JR.
|
BLD-Framing/Rough-in | 11/1/2011 | 11/1/2011 | 11/1/2011 | P | PASS |
Mike Jordan
|
|
|
junior - late afternoon please Phone #: ###-####. double layer 5/8 type x at canopy lid ok.
|
BLD-Wall cover | 11/1/2011 | 11/1/2011 | 11/1/2011 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Les Seal. Structural beam in canopy wrap with 5/8 type x rock, 2 layers ok.
|
BLD-Wall cover | 10/24/2011 | 10/25/2011 | 10/25/2011 | A | PASS |
Mike Jordan
|
|
|
Please call junior 30 min before thanks Phone #: ###-#### >> Inspection requested via web by Les Seal
|
BLD-Conference | 10/24/2011 | 10/25/2011 | 10/25/2011 | A | DONE |
Mike Jordan
|
|
|
Please call junior 30 min before thanks Phone #: ###-#### >> Inspection requested via web by Les Seal. Conferance on canopy protection.
|
BLD-Framing/Rough-in | 10/19/2011 | 10/20/2011 | 10/20/2011 | A | PASS |
Jim Storey
|
|
|
Dennis-dry wall inspection Phone #: ###-#### gyp ok/ col rapped and ok to continue 2nd layer on north side. roof framing ok to cover glb still needs 48" gyp wrap and 2x4 removed from 2 hr wall penatrations will need fire stopped.
|