Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD11-02317
StatusFinaled
Name CM COMPANY
Site Address 150 N CAPITOL BLVD
Project NameBOISE CITY HALL
Customer Number 
ePlanReviewYes
Description
(BOISE CITY HALL)(PHASE 1) **PLAN MODIFICATION 10-8-12 – Modification submitted to remodel the 3rd Floor Council Chambers and surrounding area. Modification includes: roof structural upgrades, new interior walls recreating the council chambers, new lighting, new mechanical, new doors / hardware, etc. TLW** Seismic structural upgrades and tenant improvements to all 4 floors & basement of City Hall Building 1 in the City Hall Building complex per approved plans. Total area of four stories is approximately 179,881 sq. ft. with a 63,312 sq. ft. basement used as a parking garage and mechanical equipment & maintenance office area. Work to include select interior demolition; preparation for and installation of seismic ties, connectors, concrete footings, concrete walls, steel beams, steel columns, steel & concrete structural elements at floor infill of atrium at 2nd and 3rd floors, adding additional usable floor area; providing fire-resistive assemblies or applications of listed products to maintain the required fire-resistive construction for Type I-B Construction; opening up the first floor lobby and remodeling of the clerk's office area and service counter; new interior walls to create new conference rooms, future tenant areas and work areas with relocated or new millwork work stations; new interior finishes or repair in areas of remodel; new roof assembly to include foam plastic roof insulation and single ply TPO roof membrane as per specs; upgrade and or relocation of electrical, mechanical, plumbing, fire suppression and alarm systems.NOTE: This building complex is fully sprinklered. **PLAN MODIFICATION 10-8-12 – Modification submitted to remodel the 3rd Floor Council Chambers and surrounding area. Modification includes: roof structural upgrades, new interior walls recreating the council chambers, new lighting, new mechanical, new doors / hardware, etc. TLW** drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/16/20138/16/20138/16/2013PPASS
DetailsDave Hannah
Bruce-PLease call first Phone #: ###-####
FIRE-Final Inspection8/14/20138/15/20138/15/2013PPASS
DetailsForrest France
Fire life safety finaled.
BLD-Final6/21/20136/24/20136/25/2013PPEND
DetailsDave Hannah
Bruce 1 pm ? Phone #: ###-#### ok after fire finals
FIRE-Final Inspection6/21/20136/24/20136/24/2013PPART
DetailsForrest France
Items on the previous correction list are finished with the exception of one junction box cover above the basement level fire panel and plan modification for project related FIR trade work.
BLD-Final5/9/20135/14/20135/22/2013PPART
DetailsDave Hannah
at 1:00pm please-Bruce Phone #: ###-#### ok for temp occ needs to finish fire sprinklers fire door smoke seals exit sign on forth floor
FIRE-Final Inspection5/9/20135/14/20135/14/2013PPART
DetailsForrest France
Completed walkthrough of work completed to date including the basement and 1st thru 4th floors. Refer to corrections list for items noted in need of adjustment, repair or provision.
BLD-Final5/8/20135/9/20135/10/2013PPART
DetailsDave Hannah
Bruce at 2:00 if possible please Phone #: ###-#### OK FOR TEMP OCC ON 3RD FLOOR
FIRE-Final Inspection5/8/20135/9/20135/10/2013PPART
DetailsForrest France
Third floor remodel work passed fire life safety inspection. One EM light repaired while on site, EM light at the council offices to be replaced.
FIRE-Conference5/8/20135/8/20135/8/2013PDONE
DetailsTroy Cobbley
Met with bruce and discussed work originally shown on the first floor permit and is now shown on the third floor permit.
BLD-Framing/Rough-in4/23/20134/24/20134/24/2013PPART
DetailsDave Hannah
All of 3rd fl Atruim and building 2 3rd floor Lobby-Bruce Phone #: ###-#### atruim office area fail lobby area ok to cover ceiling grid.
BLD-Framing/Rough-in4/17/20134/17/20134/17/2013PPASS
DetailsDave Hannah
Bruce--Ceiling grid inspection on the 3rd floor lobby & halls Phone #: ###-####
BLD-Framing/Rough-in4/3/20134/4/20134/4/2013APASS
DetailsDave Hannah
Bruce-3rd floor council chambers-ceiling inspection please Phone #: ###-####
BLD-Framing/Rough-in3/25/20133/26/20133/27/2013PPART
DetailsDave Hannah
Bruce-3:30 Please Phone #: ###-#### walls third floor atrim ok to cover after other trades ok
BLD-Other3/13/20133/14/20133/15/2013PPASS
DetailsDave Hannah
Bruce-3rd floor Atrium 2 hr expansion joint fill in 3:30 Phone #: ###-####
BLD-Framing/Rough-in3/13/20133/14/20133/15/2013PPASS
DetailsDave Hannah
Bruce-3rd floor Sofits @Elevator & South to current sheerock wall ok 3:30 Phone #: ###-####
BLD-Conference3/7/20133/11/20133/12/2013PPART
DetailsDave Hannah
Bruce-3rd floor Coucil Chambers between 3:30 & 3:45 Phone #: ###-#### third floor doors into exit stairways north and south ends will come up with a fix also third floor north end ceiling grid ok to cover after other trades ok for cover.
BLD-Final2/27/20132/28/20133/1/2013PPART
DetailsDave Hannah
Bruce-1st & 2nd floor north end around 3:30 please Phone #: ###-#### ok to occ north side after fire oks
BLD-Framing/Rough-in2/21/20132/22/20132/25/2013PPART
DetailsDave Hannah
Ceiling grid inspection on 1st & 2nd floor-north end--3:30pm-Bruce Phone #: ###-#### needs to wire up several lighs an mains
BLD-Framing/Rough-in1/28/20131/30/20131/31/2013PPASS
DetailsDave Hannah
Bruce-2nd floor, 3rd floor & 4th floor at 3:30 please Phone #: ###-####
BLD-Framing/Rough-in1/22/20131/22/20131/23/2013PPASS
DetailsBob Archibald
Framing inspection for the 4th floor collectors (9) east & west south end--3rd floor council chambers--walls north of grid line 5 & skylight framing--Bruce @ ###-#### @ 3:30 please
FIRE-Final Inspection11/14/201211/15/201211/15/2012PPART
DetailsForrest France
!st floor lobby and SW office area life safety inspection completed satisfactory.
BLD-Final11/14/201211/15/201211/15/2012PPART
DetailsBob Archibald
Around 1:00 if possible please-- for lobby & remainder of offices on the 1st floor--Bruce Phone #: ###-####. Lobby and offices south of central elevators/stair enclosure ok for occupancy.
BLD-Ceiling Grid Inspection11/1/201211/2/201211/6/2012APASS
DetailsDave Hannah
Bruce @ ###-#### 1st floor lobby and offices ok to cover ceiling grid after all other trades ok
FIRE-Final Inspection10/8/201210/9/201210/17/2012ANR
DetailsForrest France
Bryan -2nd flr antrium and 3rd floor bld 2 confr rm Phone #: ###-#### * Flush bolts at inactive doors, ceilings at adjacent closet to the conference room, fire sprinklers at atrium*
BLD-Final10/8/201210/9/201210/10/2012PPEND
DetailsDave Hannah
Bryan -2nd flr antrium and 3rd floor bld 2 confr rm
BLD-Final10/4/201210/5/201210/10/2012APART
DetailsDave Hannah
Partial fire life safety for building 2 2nd floor atrium & 3 fl building 2 conference rm Bruce ###-#### ok to use these areas will final at end of project
FIRE-Final Inspection10/4/201210/5/201210/5/2012ACANC
DetailsTroy Cobbley
I left voice message for Bruce stating that before I can perform a life safety inspection I would need the revised building plans. Per the online activities plans were resubmitted on 10/1/2012 and are still in the "review status" with a note from the plan reviewer stating that only the council chambers are approved. No inspection was performed.
BLD-Framing/Rough-in10/3/201210/3/201210/4/2012PPASS
DetailsDave Hannah
Bruce ###-#### Building 2 Ceiling grid inspection 3rd floor conference room please
BLD-Framing/Rough-in9/19/20129/20/20129/20/2012APASS
DetailsDave Hannah
bruce first floor finance Phone #: ###-####
BLD-Framing/Rough-in9/19/20129/20/20129/20/2012APASS
DetailsDave Hannah
bruce 2nd floor celing grid Phone #: ###-####
BLD-Framing/Rough-in9/19/20129/20/20129/20/2012APASS
DetailsDave Hannah
bruce Phone #: ###-#### 2nd floor Atrium & office off of west elevators
BLD-Framing/Rough-in8/14/20128/15/20128/16/2012APASS
DetailsDave Hannah
South entry framing and the basment column framing Phone #: ###-####
FIRE-Conference8/9/20128/9/20128/9/2012ADONE
DetailsForrest France
Regarding NFPA 72 18.4.2.5 at the first floor level between buildings one, two and the annex.
BLD-Framing/Rough-in8/1/20128/6/20128/9/2012APART
DetailsDave Hannah
BC1 basement--Bruce Phone #: ###-#### fire protection on new beam ok
FIRE-Conference7/31/20127/31/20127/31/2012PPART
DetailsForrest France
Fire life safety walkthrough for the 1st floor lobby/front counter and employee work area remodel finishes to date. Noted missing EM lights at exit discharge landings- see fire code review note #8 related. Upright sprinkler protection to be provided where drop ceilings are missing within occupied areas at the lobby. Physical barriers to be maintained between areas under construction and those accessible to building staff and the public.
BLD-Final7/24/20127/25/20127/26/2012PNR
DetailsDave Hannah
Bruce-After3 please phase 1 --1st & 2nd floor Phone #: ###-####
FIRE-Final Inspection7/25/20127/25/20127/25/2012PNR
DetailsForrest France
Bruce @ 3:00 please w/Dave Hannah Phone #: ###-####
BLD-Other7/11/20127/12/20127/16/2012APASS
DetailsBob Archibald
Firecaulking
BLD-Final7/10/20127/11/20127/11/2012PPART
DetailsBob Archibald
3pm Bruce Phone #: ###-####. Ok for ceiling grid installation on first floor /atrium except at bldg 2 elevator and south exterior exit (firecaulk required on penatrations).
BLD-Framing/Rough-in7/11/20127/11/20127/11/2012PPASS
DetailsDave Hannah
Fire rated shaft construction and floor joint @ 2nd floor atrium.
FIRE-Conference6/7/20126/7/20126/8/2012ADONE
DetailsForrest France
Regarding second floor cover inspections.
BLD-Framing/Rough-in5/8/20125/8/20126/7/2012PPART
DetailsDave Hannah
first floor walls and soffits phase one ok to cover
BLD-Conference6/5/20126/6/20126/7/2012PPART
DetailsDave Hannah
Meet at 3:00 ok to cover second floor ceiling first phase after fire and mec oks rough ins
BLD-Framing/Rough-in4/24/20124/25/20124/25/2012APASS
DetailsDave Hannah
soffits and entryway framing on frist floor ok to cover
BLD-Conference4/3/20124/3/20124/16/2012ADONE
DetailsDave Hannah
BLD-Conference3/30/20123/30/20124/3/2012PPEND
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Bruce Steinwinter talked with dan on 1hr corridor on first floor south stiar tower
BLD-Framing/Rough-in3/28/20123/28/20123/30/2012PPART
DetailsDave Hannah
second floor phase one replace org walls back to thier org location ok to cover
BLD-Framing/Rough-in3/27/20123/27/20123/29/2012PPART
DetailsDave Hannah
Electrical inspection has been called for tomorrow p.m. also. Plumbing has already inspected. Would like to start sheetrocking tomorrow night. Phone #: ###-#### >> Inspection requested via web by Bruce Steinwinter ok to cover first floor lobby and office area
BLD-Framing/Rough-in3/28/20123/28/20123/28/2012ADEFR
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Bruce Steinwinter
FIRE-Conference3/19/20123/20/20123/21/2012ADONE
DetailsForrest France
On site conference with contractor regarding building modifications at the basement level storage/lab room 2-005, engineering office 2-006, and the trash/locker room. Relocated doors, new walls and infill will require modifications to the existing fire alarm system to maintain coverage where provided.
FIRE-Conference1/10/20121/10/20121/11/2012PDONE
DetailsForrest France
On site visit with fire sprinkler contractor regarding demo work, project schedule, existing deficiencies, etc.