BLD-Final | 8/16/2013 | 8/16/2013 | 8/16/2013 | P | PASS |
Dave Hannah
|
|
|
Bruce-PLease call first Phone #: ###-####
|
FIRE-Final Inspection | 8/14/2013 | 8/15/2013 | 8/15/2013 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
BLD-Final | 6/21/2013 | 6/24/2013 | 6/25/2013 | P | PEND |
Dave Hannah
|
|
|
Bruce 1 pm ? Phone #: ###-#### ok after fire finals
|
FIRE-Final Inspection | 6/21/2013 | 6/24/2013 | 6/24/2013 | P | PART |
Forrest France
|
|
|
Items on the previous correction list are finished with the exception of one junction box cover above the basement level fire panel and plan modification for project related FIR trade work.
|
BLD-Final | 5/9/2013 | 5/14/2013 | 5/22/2013 | P | PART |
Dave Hannah
|
|
|
at 1:00pm please-Bruce Phone #: ###-#### ok for temp occ needs to finish fire sprinklers fire door smoke seals exit sign on forth floor
|
FIRE-Final Inspection | 5/9/2013 | 5/14/2013 | 5/14/2013 | P | PART |
Forrest France
|
|
|
Completed walkthrough of work completed to date including the basement and 1st thru 4th floors. Refer to corrections list for items noted in need of adjustment, repair or provision.
|
BLD-Final | 5/8/2013 | 5/9/2013 | 5/10/2013 | P | PART |
Dave Hannah
|
|
|
Bruce at 2:00 if possible please Phone #: ###-#### OK FOR TEMP OCC ON 3RD FLOOR
|
FIRE-Final Inspection | 5/8/2013 | 5/9/2013 | 5/10/2013 | P | PART |
Forrest France
|
|
|
Third floor remodel work passed fire life safety inspection. One EM light repaired while on site, EM light at the council offices to be replaced.
|
FIRE-Conference | 5/8/2013 | 5/8/2013 | 5/8/2013 | P | DONE |
Troy Cobbley
|
|
|
Met with bruce and discussed work originally shown on the first floor permit and is now shown on the third floor permit.
|
BLD-Framing/Rough-in | 4/23/2013 | 4/24/2013 | 4/24/2013 | P | PART |
Dave Hannah
|
|
|
All of 3rd fl Atruim and building 2 3rd floor Lobby-Bruce Phone #: ###-#### atruim office area fail lobby area ok to cover ceiling grid.
|
BLD-Framing/Rough-in | 4/17/2013 | 4/17/2013 | 4/17/2013 | P | PASS |
Dave Hannah
|
|
|
Bruce--Ceiling grid inspection on the 3rd floor lobby & halls Phone #: ###-####
|
BLD-Framing/Rough-in | 4/3/2013 | 4/4/2013 | 4/4/2013 | A | PASS |
Dave Hannah
|
|
|
Bruce-3rd floor council chambers-ceiling inspection please Phone #: ###-####
|
BLD-Framing/Rough-in | 3/25/2013 | 3/26/2013 | 3/27/2013 | P | PART |
Dave Hannah
|
|
|
Bruce-3:30 Please Phone #: ###-#### walls third floor atrim ok to cover after other trades ok
|
BLD-Other | 3/13/2013 | 3/14/2013 | 3/15/2013 | P | PASS |
Dave Hannah
|
|
|
Bruce-3rd floor Atrium 2 hr expansion joint fill in 3:30 Phone #: ###-####
|
BLD-Framing/Rough-in | 3/13/2013 | 3/14/2013 | 3/15/2013 | P | PASS |
Dave Hannah
|
|
|
Bruce-3rd floor Sofits @Elevator & South to current sheerock wall ok 3:30 Phone #: ###-####
|
BLD-Conference | 3/7/2013 | 3/11/2013 | 3/12/2013 | P | PART |
Dave Hannah
|
|
|
Bruce-3rd floor Coucil Chambers between 3:30 & 3:45 Phone #: ###-#### third floor doors into exit stairways north and south ends will come up with a fix also third floor north end ceiling grid ok to cover after other trades ok for cover.
|
BLD-Final | 2/27/2013 | 2/28/2013 | 3/1/2013 | P | PART |
Dave Hannah
|
|
|
Bruce-1st & 2nd floor north end around 3:30 please Phone #: ###-#### ok to occ north side after fire oks
|
BLD-Framing/Rough-in | 2/21/2013 | 2/22/2013 | 2/25/2013 | P | PART |
Dave Hannah
|
|
|
Ceiling grid inspection on 1st & 2nd floor-north end--3:30pm-Bruce Phone #: ###-#### needs to wire up several lighs an mains
|
BLD-Framing/Rough-in | 1/28/2013 | 1/30/2013 | 1/31/2013 | P | PASS |
Dave Hannah
|
|
|
Bruce-2nd floor, 3rd floor & 4th floor at 3:30 please Phone #: ###-####
|
BLD-Framing/Rough-in | 1/22/2013 | 1/22/2013 | 1/23/2013 | P | PASS |
Bob Archibald
|
|
|
Framing inspection for the 4th floor collectors (9) east & west south end--3rd floor council chambers--walls north of grid line 5 & skylight framing--Bruce @ ###-#### @ 3:30 please
|
FIRE-Final Inspection | 11/14/2012 | 11/15/2012 | 11/15/2012 | P | PART |
Forrest France
|
|
|
!st floor lobby and SW office area life safety inspection completed satisfactory.
|
BLD-Final | 11/14/2012 | 11/15/2012 | 11/15/2012 | P | PART |
Bob Archibald
|
|
|
Around 1:00 if possible please-- for lobby & remainder of offices on the 1st floor--Bruce Phone #: ###-####. Lobby and offices south of central elevators/stair enclosure ok for occupancy.
|
BLD-Ceiling Grid Inspection | 11/1/2012 | 11/2/2012 | 11/6/2012 | A | PASS |
Dave Hannah
|
|
|
Bruce @ ###-#### 1st floor lobby and offices ok to cover ceiling grid after all other trades ok
|
FIRE-Final Inspection | 10/8/2012 | 10/9/2012 | 10/17/2012 | A | NR |
Forrest France
|
|
|
Bryan -2nd flr antrium and 3rd floor bld 2 confr rm Phone #: ###-#### * Flush bolts at inactive doors, ceilings at adjacent closet to the conference room, fire sprinklers at atrium*
|
BLD-Final | 10/8/2012 | 10/9/2012 | 10/10/2012 | P | PEND |
Dave Hannah
|
|
|
Bryan -2nd flr antrium and 3rd floor bld 2 confr rm
|
BLD-Final | 10/4/2012 | 10/5/2012 | 10/10/2012 | A | PART |
Dave Hannah
|
|
|
Partial fire life safety for building 2 2nd floor atrium & 3 fl building 2 conference rm Bruce ###-#### ok to use these areas will final at end of project
|
FIRE-Final Inspection | 10/4/2012 | 10/5/2012 | 10/5/2012 | A | CANC |
Troy Cobbley
|
|
|
I left voice message for Bruce stating that before I can perform a life safety inspection I would need the revised building plans. Per the online activities plans were resubmitted on 10/1/2012 and are still in the "review status" with a note from the plan reviewer stating that only the council chambers are approved. No inspection was performed.
|
BLD-Framing/Rough-in | 10/3/2012 | 10/3/2012 | 10/4/2012 | P | PASS |
Dave Hannah
|
|
|
Bruce ###-#### Building 2 Ceiling grid inspection 3rd floor conference room please
|
BLD-Framing/Rough-in | 9/19/2012 | 9/20/2012 | 9/20/2012 | A | PASS |
Dave Hannah
|
|
|
bruce first floor finance Phone #: ###-####
|
BLD-Framing/Rough-in | 9/19/2012 | 9/20/2012 | 9/20/2012 | A | PASS |
Dave Hannah
|
|
|
bruce 2nd floor celing grid Phone #: ###-####
|
BLD-Framing/Rough-in | 9/19/2012 | 9/20/2012 | 9/20/2012 | A | PASS |
Dave Hannah
|
|
|
bruce Phone #: ###-#### 2nd floor Atrium & office off of west elevators
|
BLD-Framing/Rough-in | 8/14/2012 | 8/15/2012 | 8/16/2012 | A | PASS |
Dave Hannah
|
|
|
South entry framing and the basment column framing Phone #: ###-####
|
FIRE-Conference | 8/9/2012 | 8/9/2012 | 8/9/2012 | A | DONE |
Forrest France
|
|
|
Regarding NFPA 72 18.4.2.5 at the first floor level between buildings one, two and the annex.
|
BLD-Framing/Rough-in | 8/1/2012 | 8/6/2012 | 8/9/2012 | A | PART |
Dave Hannah
|
|
|
BC1 basement--Bruce Phone #: ###-#### fire protection on new beam ok
|
FIRE-Conference | 7/31/2012 | 7/31/2012 | 7/31/2012 | P | PART |
Forrest France
|
|
|
Fire life safety walkthrough for the 1st floor lobby/front counter and employee work area remodel finishes to date. Noted missing EM lights at exit discharge landings- see fire code review note #8 related. Upright sprinkler protection to be provided where drop ceilings are missing within occupied areas at the lobby. Physical barriers to be maintained between areas under construction and those accessible to building staff and the public.
|
BLD-Final | 7/24/2012 | 7/25/2012 | 7/26/2012 | P | NR |
Dave Hannah
|
|
|
Bruce-After3 please phase 1 --1st & 2nd floor Phone #: ###-####
|
FIRE-Final Inspection | 7/25/2012 | 7/25/2012 | 7/25/2012 | P | NR |
Forrest France
|
|
|
Bruce @ 3:00 please w/Dave Hannah Phone #: ###-####
|
BLD-Other | 7/11/2012 | 7/12/2012 | 7/16/2012 | A | PASS |
Bob Archibald
|
|
|
Firecaulking
|
BLD-Final | 7/10/2012 | 7/11/2012 | 7/11/2012 | P | PART |
Bob Archibald
|
|
|
3pm Bruce Phone #: ###-####. Ok for ceiling grid installation on first floor /atrium except at bldg 2 elevator and south exterior exit (firecaulk required on penatrations).
|
BLD-Framing/Rough-in | 7/11/2012 | 7/11/2012 | 7/11/2012 | P | PASS |
Dave Hannah
|
|
|
Fire rated shaft construction and floor joint @ 2nd floor atrium.
|
FIRE-Conference | 6/7/2012 | 6/7/2012 | 6/8/2012 | A | DONE |
Forrest France
|
|
|
Regarding second floor cover inspections.
|
BLD-Framing/Rough-in | 5/8/2012 | 5/8/2012 | 6/7/2012 | P | PART |
Dave Hannah
|
|
|
first floor walls and soffits phase one ok to cover
|
BLD-Conference | 6/5/2012 | 6/6/2012 | 6/7/2012 | P | PART |
Dave Hannah
|
|
|
Meet at 3:00 ok to cover second floor ceiling first phase after fire and mec oks rough ins
|
BLD-Framing/Rough-in | 4/24/2012 | 4/25/2012 | 4/25/2012 | A | PASS |
Dave Hannah
|
|
|
soffits and entryway framing on frist floor ok to cover
|
BLD-Conference | 4/3/2012 | 4/3/2012 | 4/16/2012 | A | DONE |
Dave Hannah
|
|
|
|
BLD-Conference | 3/30/2012 | 3/30/2012 | 4/3/2012 | P | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Bruce Steinwinter talked with dan on 1hr corridor on first floor south stiar tower
|
BLD-Framing/Rough-in | 3/28/2012 | 3/28/2012 | 3/30/2012 | P | PART |
Dave Hannah
|
|
|
second floor phase one replace org walls back to thier org location ok to cover
|
BLD-Framing/Rough-in | 3/27/2012 | 3/27/2012 | 3/29/2012 | P | PART |
Dave Hannah
|
|
|
Electrical inspection has been called for tomorrow p.m. also. Plumbing has already inspected. Would like to start sheetrocking tomorrow night. Phone #: ###-#### >> Inspection requested via web by Bruce Steinwinter ok to cover first floor lobby and office area
|
BLD-Framing/Rough-in | 3/28/2012 | 3/28/2012 | 3/28/2012 | A | DEFR |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Bruce Steinwinter
|
FIRE-Conference | 3/19/2012 | 3/20/2012 | 3/21/2012 | A | DONE |
Forrest France
|
|
|
On site conference with contractor regarding building modifications at the basement level storage/lab room 2-005, engineering office 2-006, and the trash/locker room. Relocated doors, new walls and infill will require modifications to the existing fire alarm system to maintain coverage where provided.
|
FIRE-Conference | 1/10/2012 | 1/10/2012 | 1/11/2012 | P | DONE |
Forrest France
|
|
|
On site visit with fire sprinkler contractor regarding demo work, project schedule, existing deficiencies, etc.
|