BLD-Final | 3/18/2014 | 3/20/2014 | 3/20/2014 | A | PASS |
Dave Hannah
|
|
|
Bob Cooper Phone #: ###-####
|
FIRE-Final Inspection | 3/18/2014 | 3/19/2014 | 3/19/2014 | A | PASS |
Forrest France
|
|
|
Verified previous correction items. Life safety finaled.
|
BLD-Conference | 3/17/2014 | 3/18/2014 | 3/19/2014 | A | PEND |
Dave Hannah
|
|
|
Status for final? needs fire final
|
BLD-Final | 2/3/2014 | 2/4/2014 | 2/4/2014 | A | PEND |
Dave Hannah
|
|
|
Bob Phone #: ###-####
|
FIRE-Conference | 9/17/2013 | 9/18/2013 | 9/19/2013 | A | DONE |
Forrest France
|
|
|
Missing approved plans on site. Noted missing EM lighting at the second exit access.
|
FIRE-Final Inspection | 5/29/2013 | 5/30/2013 | 5/29/2013 | P | DEFR |
Forrest France
|
|
|
Scheduled 5/30/13 AM
|
BLD-Conference | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | PASS |
Dave Hannah
|
|
|
5 day notice issued.
|
BLD-Aging Inspection | 8/27/2012 | 8/27/2012 | 8/27/2012 | | PEND |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 6/4/2012 | 6/6/2012 | 6/6/2012 | P | PART |
Dave Hannah
|
|
|
Bob-###-#### fire wall inspection please ok to cover the rest of the walls and start on lid
|
BLD-Framing/Rough-in | 4/3/2012 | 4/4/2012 | 4/4/2012 | A | PART |
Dave Hannah
|
|
|
bob Phone #: ###-#### back walls in storage area ok to start second layer
|
BLD-Final | 1/12/2012 | 1/12/2012 | 1/12/2012 | P | PART |
Dave Hannah
|
|
|
Bob Phone #: ###-#### ok for temp occ as for jason
|
FIRE-Final Inspection | 1/11/2012 | 1/12/2012 | 1/12/2012 | A | PART |
Forrest France
|
|
|
Temp. occupancy approved with conditions per J. Blais and R. Gervais.
|
BLD-Other | 1/12/2012 | 1/12/2012 | 1/12/2012 | P | PEND |
Dave Hannah
|
|
|
Ok for temporary occcupancy when trade permits are obtained for remainder of work to be performed.
|
BLD-Final | 1/4/2012 | 1/5/2012 | 1/6/2012 | A | NR |
Dave Hannah
|
|
|
wants temp (need elec & plmb?) //Bob Phone #: ###-####
|
FIRE-Final Inspection | 1/4/2012 | 1/5/2012 | 1/5/2012 | A | NR |
Forrest France
|
|
|
wants temp //Bob Phone #: ###-####
|
BLD-Other | 12/6/2011 | 12/7/2011 | 12/8/2011 | P | PART |
Dave Hannah
|
|
|
bob - drywall rough in Phone #: ###-#### first layer ok
|
BLD-Conference | 11/21/2011 | 11/21/2011 | 11/22/2011 | P | PASS |
Dave Hannah
|
|
|
Bob Cooper or ###-#### Phone #: ###-#### talked about 2hr fire wall
|
FIRE-Final Inspection | 5/29/2013 | 5/30/2013 | | A | |
Forrest France
|
|
|
Contact on site, or Dave at ###-####
|