FIRE-Final Inspection | 2/7/2012 | 2/7/2012 | 2/7/2012 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed.
|
BLD-Final | 2/6/2012 | 2/7/2012 | 2/7/2012 | P | PASS |
Jim Storey
|
|
|
JOHN Phone #: ###-####
|
DOC - Permit Finaled | 2/7/2012 | 2/7/2012 | 2/7/2012 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 2/6/2012 | 2/6/2012 | 2/6/2012 | P | NR |
Jim Storey
|
|
|
JOHN Phone #: ###-####
|
FIRE-Conference | 1/27/2012 | 1/30/2012 | 1/30/2012 | A | DONE |
Troy Cobbley
|
|
|
On site visit with contractor regarding fire code review note items and project finish schedule.
|
FIRE-Conference | 1/3/2012 | 1/3/2012 | 1/24/2012 | P | DONE |
Forrest France
|
|
|
|
BLD-Other | 1/19/2012 | 1/20/2012 | 1/20/2012 | P | DONE |
Tom Arcoraci
|
|
|
John-above cieling inspection please Phone #: ###-####
|
BLD-Other | 1/19/2012 | 1/20/2012 | 1/20/2012 | A | PASS |
Tom Arcoraci
|
|
|
john - ceiling grid - as early as possible please Phone #: ###-#### ok pending elec inspection
|
FIRE-Conference | 1/12/2012 | 1/12/2012 | 1/12/2012 | P | DONE |
Forrest France
|
|
|
Regarding fire code review note items.
|
FIRE-Conference | 1/10/2012 | 1/10/2012 | 1/11/2012 | P | DONE |
Forrest France
|
|
|
On site visit regarding manual pull box locations for activation of the hood suppression systems per IFC requirements.
|
BLD-Framing/Rough-in | 12/15/2011 | 12/16/2011 | 12/16/2011 | A | PASS |
Jim Storey
|
|
|
john - first thing in the morning if possible, please Phone #: ###-####
|
BLD-Framing/Rough-in | 12/6/2011 | 12/7/2011 | 12/7/2011 | A | PASS |
Jim Storey
|
|
|
soffits
|
BLD-Framing/Rough-in | 12/6/2011 | 12/6/2011 | 12/6/2011 | P | FAIL |
Jim Storey
|
|
|
tighten up conections.
|