BLD-Final | 4/11/2012 | 4/12/2012 | 4/12/2012 | A | PASS |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
DOC - Permit Finaled | 4/12/2012 | 4/12/2012 | 4/12/2012 | P | PASS |
Mike Jordan
|
|
|
Certificate of completion issued.
|
BLD-Final | 4/9/2012 | 4/10/2012 | 4/10/2012 | A | FAIL |
Mike Jordan
|
|
|
Chris Phone #: ###-####. Needs zoning and mechanical finals. Needs to complete firestopping for electrical conduits for 1hr. fire wall.
|
FIRE-Final Inspection | 4/5/2012 | 4/6/2012 | 4/9/2012 | A | DONE |
Forrest France
|
|
|
|
FIRE-Final Inspection | 4/9/2012 | 4/9/2012 | 4/9/2012 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 4/6/2012 | 4/9/2012 | 4/9/2012 | A | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to final when the project related fire alarm permit is addressed. Rescheduled for 3:00pm
|
BLD-Final | 4/6/2012 | 4/6/2012 | 4/6/2012 | P | NR |
Mike Jordan
|
|
|
CHRIS Phone #: ###-####
|
BLD-Framing/Rough-in | 3/26/2012 | 3/27/2012 | 3/27/2012 | P | PART |
Dave Hannah
|
|
|
Chris Phone #: ###-#### ext soffit ok to cover
|
BLD-Framing/Rough-in | 3/12/2012 | 3/12/2012 | 3/12/2012 | P | PASS |
Mike Jordan
|
|
|
chris Phone #: ###-####. Ok to cover storefront.
|
FIRE-Conference | 3/12/2012 | 3/12/2012 | 3/12/2012 | P | DONE |
Troy Cobbley
|
|
|
Mike Jordan and I verified that the existing plywood sheating, at the store front, is indeed fire rated.
|
FIRE-Conference | 3/9/2012 | 3/9/2012 | 3/9/2012 | P | DONE |
Troy Cobbley
|
|
|
I met Mike Jordan and the building superintendant and discussed the apparent combustible concealed space at the main entry. New sheating being installed is fire rated but the existing sheating appears not to be fire rated. Therefore sprinkler protection will be required or meeting one of the exceptions in chapter 8 of NFPA 13.
|
BLD-Framing/Rough-in | 3/8/2012 | 3/9/2012 | 3/9/2012 | A | NR |
Mike Jordan
|
|
|
chris Phone #: ###-####. Framing inspection for storefront. HAd Fire inspector Troy C. also at jobsite for conferance regarding the combustible material that will be enclosed within storefront. Contractor to recall dframing inspection when fire issues have been resolved.
|
BLD-Framing/Rough-in | 3/5/2012 | 3/5/2012 | 3/5/2012 | P | PART |
Mike Jordan
|
|
|
CHRIS Phone #: ###-####. 5/8 type x rock attachment for 1hr. fire walls.
|
BLD-Framing/Rough-in | 2/27/2012 | 2/28/2012 | 2/28/2012 | A | PASS |
Mike Jordan
|
|
|
chris Phone #: ###-####. Remainder of rated demissing wall ok.
|
BLD-Framing/Rough-in | 2/22/2012 | 2/23/2012 | 2/23/2012 | A | PART |
Jim Sly
|
|
|
chris Phone #: ###-#### OK'd framing (only) at West wall, and North wall. North wall extends from West wall to East wall. Walls do not include the firestopping any penitrations or tops of 1hr walls. Advised contractor to contact architect for UL listed tested assembly for tops of walls and penitrations. (no details on plan) The other issue to be resolved by architect is that the North wall bisects the smoke evacuation system located at roof.
|