BLD-Final | 6/6/2013 | 6/7/2013 | 6/7/2013 | P | PASS |
Tom Arcoraci
|
|
|
Tom, the electrical inspector has signed off temp. and hopefully he will get here before you do. Otherwise all set. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
FIRE-Final Inspection | 6/6/2013 | 6/7/2013 | 6/7/2013 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 6/4/2013 | 6/6/2013 | 6/6/2013 | P | FAIL |
Troy Cobbley
|
|
|
Fire Life and safety can ve passed when the project related fire alarm and fire sprinkler permits have been addressed.
|
BLD-Ceiling Grid Inspection | 4/10/2013 | 4/11/2013 | 4/11/2013 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Conference | 3/13/2013 | 3/13/2013 | 3/13/2013 | P | CANC |
Tom Arcoraci
|
|
|
Tom, I had one more thing for you to look at. If you are close it will only take a few minutes. Just come to the gate and drive in. Thanks Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Framing/Rough-in | 3/12/2013 | 3/12/2013 | 3/12/2013 | P | PASS |
Tom Arcoraci
|
|
|
Tom, I need a ceiling rough in inspection.
Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Other | 2/11/2013 | 2/12/2013 | 2/12/2013 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 2/11/2013 | 2/11/2013 | 2/12/2013 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Ceiling Grid Inspection | 1/28/2013 | 1/29/2013 | 1/29/2013 | P | PASS |
Tom Arcoraci
|
|
|
Tom, I need a ceiling inspection for fat grid. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Concrete | 1/10/2013 | 1/10/2013 | 1/11/2013 | P | PASS |
Tom Arcoraci
|
|
|
rebar is in place for remaining mezz. slab. Strata will inspect and test concrete. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Concrete | 1/3/2013 | 1/4/2013 | 1/4/2013 | P | PASS |
Tom Arcoraci
|
|
|
Tom, we are placing concrete for the mezz. floor. Strata will be onsite for rebar inspection as well as concrete testing. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Conference | 12/12/2012 | 12/12/2012 | 12/12/2012 | P | PASS |
Jim Storey
|
|
|
Tom, I have got a couple of things I want you to take a look at. This should not take up much of your time. Thanks Phone #: ###-#### >> Inspection requested via web by Gary Simon stair head height ok at guard station access.
|
BLD-Other | 9/26/2012 | 9/27/2012 | 9/27/2012 | P | PASS |
Tom Arcoraci
|
|
|
Cmu inspection. 1:00pm Strata will be onsite for special inspection. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Other | 9/19/2012 | 9/20/2012 | 9/20/2012 | P | PASS |
Tom Arcoraci
|
|
|
grout cmu at various hgts. at noon. Strata to inspect rebar and observe grouting. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Concrete | 9/19/2012 | 9/20/2012 | 9/20/2012 | A | PASS |
Tom Arcoraci
|
|
|
Place concrete slab for Alt. # 2 area. Strata to inspect rebar and test concrete. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Other | 9/13/2012 | 9/14/2012 | 9/14/2012 | P | PASS |
Tom Arcoraci
|
|
|
Grouting cmu walls at 4, 8, and 12 feet. Strata will be onsite for special inspection. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Footing | 9/6/2012 | 9/7/2012 | 9/7/2012 | P | PASS |
Dave Hannah
|
|
|
Concrete for footings and stemwall for alternate# 2. Strata to inspect rebar and test concrete. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Other | 9/6/2012 | 9/7/2012 | 9/7/2012 | A | PASS |
Dave Hannah
|
|
|
Grout interior cmu walls @ 4''. Strata to inspect rebar. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Concrete | 8/27/2012 | 8/28/2012 | 8/28/2012 | A | PASS |
Tom Arcoraci
|
|
|
Tom, we are placing the concrete for the remaining slab tomorrow at 5:00am. Strata will look at the rebar mat, vapor barrier today and test the concrete tomorrow. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Footing | 8/21/2012 | 8/21/2012 | 8/21/2012 | P | PASS |
Tom Arcoraci
|
|
|
Strata will be onsite for rebar inspection and concrete testing. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Concrete | 8/16/2012 | 8/17/2012 | 8/17/2012 | A | PASS |
Tom Arcoraci
|
|
|
Inspect vapor barrier and rebar mat for slab. Strata will inspect vapor and rebar today and test concrete monday am. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Foundation | 8/8/2012 | 8/8/2012 | 8/8/2012 | P | PASS |
Tom Arcoraci
|
|
|
Tom, we are pouring the 12" stemwalls on the ftgs. Strata will be onsite for rebar and concrete testing. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Footing | 8/6/2012 | 8/7/2012 | 8/7/2012 | P | PASS |
Tom Arcoraci
|
|
|
Tom,we are placing concrete in interior footings late afternoon. Strada will be onsite to inspect the rebar and test concrete. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Foundation | 7/12/2012 | 7/16/2012 | 7/16/2012 | A | PASS |
Tom Arcoraci
|
|
|
We are pouring foundation walls starting at 6:00am Monday morning. Strata is doing all rebar inspections. if you would like you could come by tomorrow and look at everything its all set up now.
MB >> Inspection requested via web by Mike Burden
|
BLD-Footing | 7/9/2012 | 7/9/2012 | 7/9/2012 | P | PASS |
Tom Arcoraci
|
|
|
We are planning on pouring at 2:00 PM you can call me on my cell when you get here and i will get you in it the far east entry there is a little guard shack outside the gate. Phone #: ###-#### >> Inspection requested via web by Mike Burden
|