Permit Information
Permit NumberBLD11-03019
StatusFinaled
Name SCOTT HEDRICK CONSTRUCTION
Site Address 7210 W BARRISTER DR
Project NameADA COUNTY JAIL POD D
Customer Number 
ePlanReviewYes
Description
(ADA COUNTY JAIL - POD D EXPANSION) The fire sprinkler system is required because this building is an I-3 Occupancy. To construct a 12,639 square foot prison (7,403 square foot 1st tier and 5,236 square foot 2nd tier). Work is to include concrete footings, concrete foundations, concrete slab on grade floor, masonry walls, elevated concrete floors, concrete columns, elevated concrete slab with steel pan deck, steel skin cell walls filled with concrete grout, stairways, steel bar joist roof, steel roof deck, roof insulation installed on top of the roof deck, skylights, and a membrane roof covering. The work is required to comply with the approved drawings, with the specifications, with the structural calculations, with the plan review report, and with all applicable codes and ordinances. Required Special Inspections include concrete, expansion bolts, epoxy anchors, masonry, high strength bolting, welding, structural steel, spray fire proofing, and soils. Some site work will also be done under this permit. The upper tier floor and support structure at the cells is a deferred submittal item. That work shall not be done until the structural design is reviewed and approved. See the letter signed by David Logan, Director of Ada County Operations. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. The fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/6/20136/7/20136/7/2013PPASS
DetailsTom Arcoraci
Tom, the electrical inspector has signed off temp. and hopefully he will get here before you do. Otherwise all set. Phone #: ###-#### >> Inspection requested via web by Gary Simon
FIRE-Final Inspection6/6/20136/7/20136/7/2013APASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection6/4/20136/6/20136/6/2013PFAIL
DetailsTroy Cobbley
Fire Life and safety can ve passed when the project related fire alarm and fire sprinkler permits have been addressed.
BLD-Ceiling Grid Inspection4/10/20134/11/20134/11/2013APASS
DetailsTom Arcoraci
Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Conference3/13/20133/13/20133/13/2013PCANC
DetailsTom Arcoraci
Tom, I had one more thing for you to look at. If you are close it will only take a few minutes. Just come to the gate and drive in. Thanks Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Framing/Rough-in3/12/20133/12/20133/12/2013PPASS
DetailsTom Arcoraci
Tom, I need a ceiling rough in inspection.

Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Other2/11/20132/12/20132/12/2013APASS
DetailsTom Arcoraci
BLD-Other2/11/20132/11/20132/12/2013PPASS
DetailsTom Arcoraci
BLD-Ceiling Grid Inspection1/28/20131/29/20131/29/2013PPASS
DetailsTom Arcoraci
Tom, I need a ceiling inspection for fat grid.
Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Concrete1/10/20131/10/20131/11/2013PPASS
DetailsTom Arcoraci
rebar is in place for remaining mezz. slab. Strata will inspect and test concrete. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Concrete1/3/20131/4/20131/4/2013PPASS
DetailsTom Arcoraci
Tom, we are placing concrete for the mezz. floor. Strata will be onsite for rebar inspection as well as concrete testing. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Conference12/12/201212/12/201212/12/2012PPASS
DetailsJim Storey
Tom, I have got a couple of things I want you to take a look at. This should not take up much of your time. Thanks Phone #: ###-#### >> Inspection requested via web by Gary Simon stair head height ok at guard station access.
BLD-Other9/26/20129/27/20129/27/2012PPASS
DetailsTom Arcoraci
Cmu inspection. 1:00pm Strata will be onsite for special inspection. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Other9/19/20129/20/20129/20/2012PPASS
DetailsTom Arcoraci
grout cmu at various hgts. at noon. Strata to inspect rebar and observe grouting. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Concrete9/19/20129/20/20129/20/2012APASS
DetailsTom Arcoraci
Place concrete slab for Alt. # 2 area. Strata to inspect rebar and test concrete. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Other9/13/20129/14/20129/14/2012PPASS
DetailsTom Arcoraci
Grouting cmu walls at 4, 8, and 12 feet. Strata will be onsite for special inspection. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Footing9/6/20129/7/20129/7/2012PPASS
DetailsDave Hannah
Concrete for footings and stemwall for alternate# 2. Strata to inspect rebar and test concrete. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Other9/6/20129/7/20129/7/2012APASS
DetailsDave Hannah
Grout interior cmu walls @ 4''. Strata to inspect rebar. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Concrete8/27/20128/28/20128/28/2012APASS
DetailsTom Arcoraci
Tom, we are placing the concrete for the remaining slab tomorrow at 5:00am. Strata will look at the rebar mat, vapor barrier today and test the concrete tomorrow. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Footing8/21/20128/21/20128/21/2012PPASS
DetailsTom Arcoraci
Strata will be onsite for rebar inspection and concrete testing. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Concrete8/16/20128/17/20128/17/2012APASS
DetailsTom Arcoraci
Inspect vapor barrier and rebar mat for slab.
Strata will inspect vapor and rebar today and test concrete monday am. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Foundation8/8/20128/8/20128/8/2012PPASS
DetailsTom Arcoraci
Tom, we are pouring the 12" stemwalls on the ftgs. Strata will be onsite for rebar and concrete testing. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Footing8/6/20128/7/20128/7/2012PPASS
DetailsTom Arcoraci
Tom,we are placing concrete in interior footings late afternoon. Strada will be onsite to inspect the rebar and test concrete. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Foundation7/12/20127/16/20127/16/2012APASS
DetailsTom Arcoraci
We are pouring foundation walls starting at 6:00am Monday morning. Strata is doing all rebar inspections. if you would like you could come by tomorrow and look at everything its all set up now.


MB >> Inspection requested via web by Mike Burden
BLD-Footing7/9/20127/9/20127/9/2012PPASS
DetailsTom Arcoraci
We are planning on pouring at 2:00 PM you can call me on my cell when you get here and i will get you in it the far east entry there is a little guard shack outside the gate. Phone #: ###-#### >> Inspection requested via web by Mike Burden