(TEEN CHALLENGE IDAHO) Tenant is the GC-- Remodel of an existing teenage girl dormitory and school within an existing building per approved plans. Work to include select interior demolition; construct new interior walls to define office reception area, new kitchen with commercial grease hood / exhaust system; combine two restrooms to provide for accessibility of water closet & shower to serve new Teen Challenge dorm room; two private sleeping units and common living area for two staff; a laundry room and study area to create a combined educationa / residential facility for up to 20 teenage girls plus staff. This building will be fully sprinklered as part of this permit scope. Separate permit for sprinkler system and alarm system work requires separate permits as regulated by the fire department. A grease interceptor is being installed. Planning approval done under CUP11-00032.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/2/20134/2/20134/2/2013PPASS
DetailsJim Sly
chris Phone #: ###-####
OK for Perm Occ.
BLD-Final3/7/20133/7/20133/7/2013PPART
DetailsJim Sly
chris Phone #: ###-####
OK For Temp occ. OK for Perm Occ when all Fire Finals are complete. Need to complete stalls in center restroom
FIRE-Final Inspection3/4/20133/4/20133/4/2013PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection3/1/20133/1/20133/1/2013PPART
DetailsTroy Cobbley
A temporary occupancy was given with scott arellanos permision until the additional smoke alarm is installed in the vestibule between the staff sleeping rooms as per the city approved fire alarm plans. Once installed this device will need to be tested. I also need the final paper work. All other life safety items are ok.
BLD-Final3/1/20133/1/20133/1/2013PNR
DetailsJim Sly
chris Phone #: ###-####
Need all three Fire finals, CDHD, One Mechanical permit, and Zoning Finals.
FIRE-Conference2/19/20132/19/20132/19/2013PDONE
DetailsTroy Cobbley
I went over life safety items with Savannah, who was on site and with Chris on the phone. The items covered included getting the fire sprinkler permit finished. Getting the fire alarm system completely installed and inspected, Life safety items included the need for a knox box, exit signs and emergency lights tested, fire extinguishers installed, all door hardware installed.
BLD-Conference11/26/201211/26/201211/26/2012PDONE
DetailsJim Sly
Chris Phone #: ###-####
Met with new superintendant. OK to cover select walls ....Sleeping room areas....N. E. corner of bldg.
BLD-Framing/Rough-in10/3/201210/4/201210/5/2012APART
DetailsJim Sly
Charles Phone #: ###-####
Select walls OK to cover..... Need letter from Architect .... will install NFPA 13 fire sprinklers throughout.....therefor interior walls do not have to go up to roof deck.
BLD-Framing/Rough-in7/2/20127/3/20127/3/2012ANR
DetailsJim Sly
Charles ###-####
Need all trade R/Is installed. Need Conf. with Architect ... rated walls, type of sprinkler system etc..
BLD-Framing/Rough-in7/2/20127/2/20127/2/2012PNR
DetailsJim Sly
Charles Phone #: ###-####