Permit Information
Permit NumberBLD12-00530
StatusFinaled
Name BENITON CONSTRUCTION
Site Address 1609 S OWYHEE ST
Project NameWhitney Elemetary Classroom Ad
Customer Number 
ePlanReviewYes
Description
(WHITNEY ELEMENTARY SCHOOL) - Classroom Addition - To construct a 2,150 square foot one story, two classroom addition at the north end of the east classroom wing. To construct a 2,510 square foot, one story, two classroom addition on the north end of the east classroom wing. The additions are constructed of metal stud walls and wood trussed roof. This permit also includes related site improvements. The building is separated into three buildings, for allowable area purposes, by two-hour fire walls. Building "A" with new addition is 14,800 square feet, contains classroom areas and is located on the northwest corner of the school. Building "B" is 4,805 square feet and contains the gymnasium, dental clinic, small office and storage areas. Building "B" is located on the south end of the school. Building "C" with the new addition is 43,335 square feet and comprises the remainder of the building. Building "C" contains the cafeteria, kitchen, administration offices, library, multi-purpose community area and classrooms. Building "C" is at maximum allowable area and no future expansion is allowed to this portion of the school. This building also contains attic mechanical spaces. This school is fully fire sprinkled. The sprinklers are used for building area increase. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/7/201211/8/201211/8/2012APART
DetailsTom Arcoraci
Ryan Phone #: ###-#### needs landscape
FIRE-Final Inspection11/2/201211/5/201211/5/2012APASS
DetailsForrest France
Fire life safety inspection completed satisfactory.
BLD-Other10/11/201210/11/201210/11/2012PPASS
DetailsTom Arcoraci
Ceiling grid - Ryan Phone #: ###-####
BLD-Framing/Rough-in9/17/20129/18/20129/18/2012APASS
DetailsTom Arcoraci
ryan Phone #: ###-####
BLD-Energy code compliance8/29/20128/29/20128/29/2012PPASS
DetailsTom Arcoraci
RYAN Phone #: ###-####
BLD-Framing/Rough-in8/23/20128/24/20128/24/2012PPASS
DetailsTom Arcoraci
Ryan Phone #: ###-####
BLD-Framing/Rough-in8/20/20128/20/20128/20/2012PPASS
DetailsTom Arcoraci
ryan Phone #: ###-####
BLD-Framing/Rough-in8/13/20128/14/20128/14/2012PPASS
DetailsTom Arcoraci
Ryan Phone #: ###-#### wip ok
BLD-Wall Bracing8/6/20128/6/20128/6/2012PPASS
DetailsTom Arcoraci
Shear wall -- Brian Phone #: ###-####
BLD-Wall cover7/31/20127/31/20127/31/2012PPASS
DetailsTom Arcoraci
BLD-Framing/Rough-in7/27/20127/30/20127/30/2012PPASS
DetailsTom Arcoraci
Fire Wall- Ryan Phone #: ###-####
BLD-Energy code compliance7/2/20127/2/20127/2/2012PPASS
DetailsJim Sly
ryan Phone #: ###-####
Foundation insulation OK.
BLD-Concrete6/27/20126/28/20126/28/2012APASS
DetailsJim Sly
ryan Phone #: ###-####
Foundation walls OK pending MTI special insp, tests and approvals.......MTI employed by Boise School Dist.
BLD-Concrete6/21/20126/22/20126/21/2012APART
DetailsJim Sly
Ryan Phone #: ###-####
No approved plans on site. Contractor to verify that MTI was not hired by Contractor. Need credentials from all special inspectors employed by MTI. Un-approved set of plans calls for special insp...Concrete, reinforcement, epoxy. Cannot find design strength of concrete. Unable to contact Engineer of record to verify this. MTI to be on site for inspections. Plans were examined electronically. Architect to provide. I observed 2-#5s in footing Horiz. and 2-#4's Vert at 18"oc. Can pour only if approved plans on site and MTI approval. Advised Ryan.