Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD12-00551
StatusFinaled
Name J & L DEVELOPMENT LTD CORP
Site Address 4262 N EAGLE RD
Project NameGRACE BIBLE CHURCH
Customer Number 
ePlanReviewNo
Description
(GRACE BIBLE CHURCH) - Addition - To Construct a new 19,600 sq. ft., one story, wood framed church building addition and related site improvements. This church building is being added to an existing 2,350 sq. ft., one story church office building. The new addition and existing building will be fully fire sprinkled. The sprinklers are used for area increase. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/16/20144/17/20144/17/2014APASS
DetailsJim Sly
Jesse Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection4/16/20144/16/20144/17/2014PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Final4/9/20144/9/20144/9/2014PCANC
DetailsJim Sly
Jesse p[hone ###-####
BLD-Final4/8/20144/8/20144/8/2014PPEND
DetailsJim Sly
Jesse ......WIP.
BLD-Ceiling Grid Inspection1/24/20141/24/20141/24/2014PPASS
DetailsJim Sly
Jesse Phone #: ###-####
BLD-Framing/Rough-in12/12/201312/12/201312/12/2013PPASS
DetailsJim Sly
JESSE Phone #: ###-####
Talked to Jesse .....Make sure Troy has looked at sprinklers.
BLD-Conference11/4/201311/5/201311/5/2013PDONE
DetailsJim Sly
Starting to finish classrooms
BLD-Final11/4/201311/4/201311/4/2013PPEND
DetailsJim Sly
Re-sched..... for Tues PM.
BLD-Final6/13/20136/13/20136/14/2013PPEND
DetailsJim Sly
BLD-Final2/4/20132/5/20132/5/2013PPART
DetailsJim Sly
Hello Jim,

we have everything signed off, can we get a final? Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
Some un-finished classroom areas to be finished in the near future. Corr. Notice...... Need Fire, Zoning, public Works, and Plumbing to sign off for Perm Occ. They have signed Temp as per now. OK for Temp Occ. from Structural.
BLD-Final2/1/20132/1/20132/1/2013PFAIL
DetailsJim Sly
Need Zoning final.
BLD-Final1/31/20132/1/20132/1/2013ACANC
DetailsJim Sly
Hello Jim,

Can you call me when you are on your way? Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
BLD-Conference1/29/20131/30/20131/31/2013ACANC
DetailsJim Sly
Hello Jim, this is a reminder to discuss Grace Bible with Bob Archibald. Possible walk through. Call me when you would like to do that. ###-####. Need Fire Final.
Thanks. >> Inspection requested via web by Jesse Ferrer
FIRE-Final Inspection1/30/20131/31/20131/31/2013PPART
DetailsTroy Cobbley
A temporary occupancy is being given with Jim sly's and Jason Blais permission until the rest of theconstruction has been completed.. New sprinkler and fire alarm permits will be required.
BLD-Final1/25/20131/28/20131/28/2013ANR
DetailsJim Sly
Hey Jim, can you call me when you are on your way.
Thanks. Jesse Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
Walked through Bldg with Jesse.....made list of requirements needed to obtain Cert of Occ.
FIRE-Final Inspection1/25/20131/28/20131/28/2013AFAIL
DetailsTroy Cobbley
Todays inspection was for a conference. It needs to be verified through building plan review that it is ok to not finish part of the building but still have people exiting through these areas, several emergency lights did not function, fire alarm and fire sprinkler permits need addressed.
BLD-Ceiling Grid Inspection12/14/201212/17/201212/17/2012APASS
DetailsJim Sly
Hey Jim,
Can you give me a call before you head out?
Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
FIRE-Conference12/12/201212/12/201212/12/2012PDONE
DetailsTroy Cobbley
I posted a stop work order on the front of the building due to hardlids continuing to be installed prior to a sprinkler rough-in inspection. I had a previous conversation with contractor about this. Stop work order states "Stop all sheet rock that is covering sprinkler piping. Cover inspection is required".
FIRE-Conference11/7/201211/7/201211/7/2012PDONE
DetailsTroy Cobbley
The sprinkler piping in the main lobby area has been covered by sheet rock without approval. I spoke to the job site superintendant about a possible stop work order if covering pipe prior to an inspection continued. He agreed that it would not happen again. Access needs to be provided for the following inspection.
BLD-Wall cover10/30/201210/31/201210/31/2012APASS
DetailsJim Sly
Wall covering.

Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
BLD-Energy code compliance10/30/201210/31/201210/31/2012APASS
DetailsJim Sly
Hello Jim,

This is for insulation walls and wall covering. Can you give me a call when you are on your way?

Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
BLD-Framing/Rough-in10/25/201210/26/201210/26/2012APART
DetailsJim Sly
Hello Jim,

Can we get an am on this and can you call me so I can meet you ot there?

Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
Select truss corrections. OK to insulate walls.
BLD-Wall Bracing10/22/201210/23/201210/23/2012APASS
DetailsJim Sly
Hello Jim,

This inspection is for wall shaething and bracing. We would like to start drying in.
If you could call me when you are on your way that would be great.
Thanks. Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
All Exterior shear nailing.....OK.
BLD-Wall cover10/4/201210/5/201210/5/2012APART
DetailsJim Sly
Hello Jim,
can we get a final roof sheathing inspection in the morning. The only thing left to inspect on the roof is the portico.
Thanks, Jesse Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
Portico roof nailing....OK.
BLD-Conference9/6/20129/6/20129/6/2012ADEFR
DetailsJim Sly
Good morning Jim,We wanted to know if you could meet us on site to discuss an issue that came up with our site work. It should only take a few minutes. If you can give me a call when you think you might be available that would be great. If you can''t do it today tomorrow will work too.
Thanks Jim. Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
Zoning issues ....Deferred.
BLD-Wall Bracing9/4/20129/5/20129/5/2012APART
DetailsJim Sly
Hello Jim, this is for a partial sheet and shear inspection. Can you call me or Mike at Leighton before you swing by so one of us can plan to be there.
Thanks Phone #: ###-#### >>
Inspection requested via web by Jesse Ferrer
Roof nailing OK except approx. 40' wide area at front entry.
BLD-Other7/17/20127/18/20127/18/2012ADONE
DetailsJim Sly
Hello Jim, This is for a CMU lift.
Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
1st lift .....OK pending MTI inspections, tests and approvals.
BLD-Concrete7/3/20127/6/20127/6/2012APASS
DetailsJim Sly
Please call Jared Advanced concrete ###-#### so he can meet you on site.
Thanks Jim. Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
Flatwork....footings.
BLD-Foundation6/11/20126/12/20126/12/2012APASS
DetailsJim Sly
Good morning Jim, can you call before you show up so we can have someone there?
Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
Verified MTI contracted by Grace church and special inspectors on site certified in thier discipline.
BLD-Footing6/7/20126/7/20126/7/2012APASS
DetailsJim Sly
I just noticed that I used the grading permit # on previous inspection request. (same inspection) Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer

No Special insp req. on foundations. Verified with Sarah (Eng. of record). MTI will be doing other required inspections per appr plans. Jesse to provide verification that MTI not hired by contr. Need MTI inspectors credentials next insp.