BLD-Final | 4/16/2014 | 4/17/2014 | 4/17/2014 | A | PASS |
Jim Sly
|
|
|
Jesse Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 4/16/2014 | 4/16/2014 | 4/17/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 4/9/2014 | 4/9/2014 | 4/9/2014 | P | CANC |
Jim Sly
|
|
|
Jesse p[hone ###-####
|
BLD-Final | 4/8/2014 | 4/8/2014 | 4/8/2014 | P | PEND |
Jim Sly
|
|
|
Jesse ......WIP.
|
BLD-Ceiling Grid Inspection | 1/24/2014 | 1/24/2014 | 1/24/2014 | P | PASS |
Jim Sly
|
|
|
Jesse Phone #: ###-####
|
BLD-Framing/Rough-in | 12/12/2013 | 12/12/2013 | 12/12/2013 | P | PASS |
Jim Sly
|
|
|
JESSE Phone #: ###-#### Talked to Jesse .....Make sure Troy has looked at sprinklers.
|
BLD-Conference | 11/4/2013 | 11/5/2013 | 11/5/2013 | P | DONE |
Jim Sly
|
|
|
Starting to finish classrooms
|
BLD-Final | 11/4/2013 | 11/4/2013 | 11/4/2013 | P | PEND |
Jim Sly
|
|
|
Re-sched..... for Tues PM.
|
BLD-Final | 6/13/2013 | 6/13/2013 | 6/14/2013 | P | PEND |
Jim Sly
|
|
|
|
BLD-Final | 2/4/2013 | 2/5/2013 | 2/5/2013 | P | PART |
Jim Sly
|
|
|
Hello Jim,
we have everything signed off, can we get a final? Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer Some un-finished classroom areas to be finished in the near future. Corr. Notice...... Need Fire, Zoning, public Works, and Plumbing to sign off for Perm Occ. They have signed Temp as per now. OK for Temp Occ. from Structural.
|
BLD-Final | 2/1/2013 | 2/1/2013 | 2/1/2013 | P | FAIL |
Jim Sly
|
|
|
Need Zoning final.
|
BLD-Final | 1/31/2013 | 2/1/2013 | 2/1/2013 | A | CANC |
Jim Sly
|
|
|
Hello Jim,
Can you call me when you are on your way? Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
|
BLD-Conference | 1/29/2013 | 1/30/2013 | 1/31/2013 | A | CANC |
Jim Sly
|
|
|
Hello Jim, this is a reminder to discuss Grace Bible with Bob Archibald. Possible walk through. Call me when you would like to do that. ###-####. Need Fire Final. Thanks. >> Inspection requested via web by Jesse Ferrer
|
FIRE-Final Inspection | 1/30/2013 | 1/31/2013 | 1/31/2013 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given with Jim sly's and Jason Blais permission until the rest of theconstruction has been completed.. New sprinkler and fire alarm permits will be required.
|
BLD-Final | 1/25/2013 | 1/28/2013 | 1/28/2013 | A | NR |
Jim Sly
|
|
|
Hey Jim, can you call me when you are on your way. Thanks. Jesse Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer Walked through Bldg with Jesse.....made list of requirements needed to obtain Cert of Occ.
|
FIRE-Final Inspection | 1/25/2013 | 1/28/2013 | 1/28/2013 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for a conference. It needs to be verified through building plan review that it is ok to not finish part of the building but still have people exiting through these areas, several emergency lights did not function, fire alarm and fire sprinkler permits need addressed.
|
BLD-Ceiling Grid Inspection | 12/14/2012 | 12/17/2012 | 12/17/2012 | A | PASS |
Jim Sly
|
|
|
Hey Jim, Can you give me a call before you head out? Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
|
FIRE-Conference | 12/12/2012 | 12/12/2012 | 12/12/2012 | P | DONE |
Troy Cobbley
|
|
|
I posted a stop work order on the front of the building due to hardlids continuing to be installed prior to a sprinkler rough-in inspection. I had a previous conversation with contractor about this. Stop work order states "Stop all sheet rock that is covering sprinkler piping. Cover inspection is required".
|
FIRE-Conference | 11/7/2012 | 11/7/2012 | 11/7/2012 | P | DONE |
Troy Cobbley
|
|
|
The sprinkler piping in the main lobby area has been covered by sheet rock without approval. I spoke to the job site superintendant about a possible stop work order if covering pipe prior to an inspection continued. He agreed that it would not happen again. Access needs to be provided for the following inspection.
|
BLD-Wall cover | 10/30/2012 | 10/31/2012 | 10/31/2012 | A | PASS |
Jim Sly
|
|
|
Wall covering.
Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
|
BLD-Energy code compliance | 10/30/2012 | 10/31/2012 | 10/31/2012 | A | PASS |
Jim Sly
|
|
|
Hello Jim,
This is for insulation walls and wall covering. Can you give me a call when you are on your way?
Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
|
BLD-Framing/Rough-in | 10/25/2012 | 10/26/2012 | 10/26/2012 | A | PART |
Jim Sly
|
|
|
Hello Jim,
Can we get an am on this and can you call me so I can meet you ot there?
Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer Select truss corrections. OK to insulate walls.
|
BLD-Wall Bracing | 10/22/2012 | 10/23/2012 | 10/23/2012 | A | PASS |
Jim Sly
|
|
|
Hello Jim,
This inspection is for wall shaething and bracing. We would like to start drying in. If you could call me when you are on your way that would be great. Thanks. Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer All Exterior shear nailing.....OK.
|
BLD-Wall cover | 10/4/2012 | 10/5/2012 | 10/5/2012 | A | PART |
Jim Sly
|
|
|
Hello Jim, can we get a final roof sheathing inspection in the morning. The only thing left to inspect on the roof is the portico. Thanks, Jesse Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer Portico roof nailing....OK.
|
BLD-Conference | 9/6/2012 | 9/6/2012 | 9/6/2012 | A | DEFR |
Jim Sly
|
|
|
Good morning Jim,We wanted to know if you could meet us on site to discuss an issue that came up with our site work. It should only take a few minutes. If you can give me a call when you think you might be available that would be great. If you can''t do it today tomorrow will work too. Thanks Jim. Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer Zoning issues ....Deferred.
|
BLD-Wall Bracing | 9/4/2012 | 9/5/2012 | 9/5/2012 | A | PART |
Jim Sly
|
|
|
Hello Jim, this is for a partial sheet and shear inspection. Can you call me or Mike at Leighton before you swing by so one of us can plan to be there. Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer Roof nailing OK except approx. 40' wide area at front entry.
|
BLD-Other | 7/17/2012 | 7/18/2012 | 7/18/2012 | A | DONE |
Jim Sly
|
|
|
Hello Jim, This is for a CMU lift. Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer 1st lift .....OK pending MTI inspections, tests and approvals.
|
BLD-Concrete | 7/3/2012 | 7/6/2012 | 7/6/2012 | A | PASS |
Jim Sly
|
|
|
Please call Jared Advanced concrete ###-#### so he can meet you on site. Thanks Jim. Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer Flatwork....footings.
|
BLD-Foundation | 6/11/2012 | 6/12/2012 | 6/12/2012 | A | PASS |
Jim Sly
|
|
|
Good morning Jim, can you call before you show up so we can have someone there? Thanks Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer Verified MTI contracted by Grace church and special inspectors on site certified in thier discipline.
|
BLD-Footing | 6/7/2012 | 6/7/2012 | 6/7/2012 | A | PASS |
Jim Sly
|
|
|
I just noticed that I used the grading permit # on previous inspection request. (same inspection) Phone #: ###-#### >> Inspection requested via web by Jesse Ferrer
No Special insp req. on foundations. Verified with Sarah (Eng. of record). MTI will be doing other required inspections per appr plans. Jesse to provide verification that MTI not hired by contr. Need MTI inspectors credentials next insp.
|