Permit Information
Permit NumberBLD12-00676
StatusFinaled
Name TRILOGY DEVELOPMENT INC
Site Address 1461 S GOLDKING WAY
Project NameUnion Square Apartments
Customer Number 
ePlanReviewYes
Description
(UNION SQUARE) Community building/pool equipment room building #1. To construct a new 2,477 sq. ft. single story wood frame structure per approved plans. Community Room O.L. 49; Lobby O.L. 29; other 15 O.L. (NOTE: A-5 Occupancy: Pool/Deck Area will use building restrooms - Pool 16 O.L. / Deck 180 O.L). Work includes footing, foundation, framed walls, truss roof & sheathing, interior walls to create office's, community room, lobby room, kitchen area, exercise room, accessible restrooms & drinking fountains, pool equipment room and access to future pool (pool under separate permit), interior & exterior finishes, electrical, mechanical, plumbing and millwork, doors and hardware, all per reviewed plans. drs DRH12-00022 CUP08-ooo45
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/28/20132/28/20132/28/2013PPASS
DetailsMike Jordan
Michael Phone #: ###-####Ok for temp occ. at this time. Will be ok for perm occ. once zoning signs eprm.
FIRE-Final Inspection2/27/20132/28/20132/28/2013APASS
DetailsTroy Cobbley
life safety passed. Per letter from engineer the duct smoke detector is not required by them. Dead bolt is going to be blanked off.
FIRE-Final Inspection2/27/20132/27/20132/27/2013PFAIL
DetailsTroy Cobbley
Provide verification from the mechanical engineer for the deletion of the duct smoke detector and provide verification from the building plan reviewer for permission to install double keyed lock on the weight room door. If installed an "indicator" and sticker will also be required.
BLD-Energy code compliance11/9/201211/13/201211/13/2012PPASS
DetailsJim Sly
Kelly phone
OK to cover all but........Mechanical room and restrooms associated with pool area.
BLD-Energy code compliance11/9/201211/9/201211/9/2012PNR
DetailsJim Sly
Phone #: ###-#### >> Inspection requested via web by Kelly Perryman
Had a few corrections to complete before approval.
BLD-Framing/Rough-in11/7/201211/8/201211/8/2012APART
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by Kelly Perryman dg3 need lgt2 simpson at bearing point #1/ fire blk ceilling at unusable space/ provide ada backing in restarooms.
BLD-Framing/Rough-in11/6/201211/6/201211/6/2012PNR
DetailsJim Sly
Phone #: ###-#### >> Inspection requested via web by Kelly Perryman
Need all Rough-ins approved.
BLD-Wall Bracing9/18/20129/18/20129/18/2012PPART
DetailsMike Jordan
kelly Phone #: ###-####. Exterior shear nailing and holdowns. Missing HD3B holddown at NW corner, Add additional blocking and nailing at vertical edges on shear panel 5. Correction notice was posted. Also needs to tighten bolts on holddowns.
BLD-Foundation7/12/20127/13/20127/13/2012APASS
DetailsMike Jordan
dane Phone #: ###-####. Perimeter footings ok.
BLD-Footing7/11/20127/11/20127/11/2012PPART
DetailsMike Jordan
dane Phone #: ###-####. Perimeter footings and column pad footings. Work inprogress on placing vertical steel.