BLD-Final | 6/11/2013 | 6/11/2013 | 6/11/2013 | P | PASS |
Mike Jordan
|
|
|
Lets try this again >> Inspection requested via web by Fred Depold. Ok for perm occ.
|
BLD-Final | 6/6/2013 | 6/7/2013 | 6/7/2013 | P | NR |
Mike Jordan
|
|
|
This building is ready for final, Monday 7/10 works however if for any reason your schedule lightens up before Monday we are ready and Mikey will earn brownie points with the owners :-) >> Inspection requested via web by Fred Depold. Complete firecaulking on all rated penetrations, provide tempered glazing were required. Need blower door test results posted.
|
FIRE-Final Inspection | 6/4/2013 | 6/5/2013 | 6/5/2013 | A | PASS |
Troy Cobbley
|
|
|
Fire Life Safety passed. All smoke alarms tested ok.
|
BLD-Footing | 3/11/2013 | 3/12/2013 | 3/12/2013 | A | CANC |
Mike Jordan
|
|
|
mike Phone #: ###-####. Inspection done yesterday in the pm.
|
BLD-Conference | 3/11/2013 | 3/11/2013 | 3/11/2013 | P | PART |
Mike Jordan
|
|
|
Footing for stair foundation, east stairs per RFI from engineer.
|
BLD-Wall cover | 2/6/2013 | 2/7/2013 | 2/7/2013 | A | PASS |
Mike Jordan
|
|
|
This should be the final trip to approve taping in the last units Phone #: ###-#### >> Inspection requested via web by Fred Depold. Remainder of rooms ok to toape.
|
BLD-Wall cover | 2/6/2013 | 2/6/2013 | 2/6/2013 | A | NR |
Mike Jordan
|
|
|
|
BLD-Wall cover | 2/5/2013 | 2/5/2013 | 2/5/2013 | P | PASS |
Mike Jordan
|
|
|
sheet rock inspection balance of building approve to tape
As late in day as possible say 4 would be great if possible >> Inspection requested via web by Fred Depold. south end and middle units, floors 1-3 ok to tape. North units floor 1 and 3 ok. Still working on 2nd. floor.
|
BLD-Wall cover | 2/4/2013 | 2/4/2013 | 2/4/2013 | P | PASS |
Mike Jordan
|
|
|
sheet rock screw off inspection >> Inspection requested via web by Fred Depold
|
BLD-Wall cover | 1/31/2013 | 2/1/2013 | 2/1/2013 | A | PART |
Mike Jordan
|
|
|
Inspect sheet rock screw application to approve taping in building 7 top floor.
Early morning if possible
Thankyou- Fred Phone #: ###-#### >> Inspection requested via web by Fred Depold. Third floor, center units only ok to tape.
|
BLD-Energy code compliance | 1/23/2013 | 1/24/2013 | 1/24/2013 | A | PASS |
Jim Sly
|
|
|
Inspect insulation please and approve for wall cover. Phone #: ###-#### >> Inspection requested via web by Kelly Perryman
|
BLD-Energy code compliance | 1/16/2013 | 1/17/2013 | 1/17/2013 | A | PASS |
Tom Arcoraci
|
|
|
Ready to inspect fire caulking and all penetrations sealed
Thanks- Fred Phone #: ###-#### >> Inspection requested via web by Kelly Perryman
|
BLD-Wall Bracing | 12/11/2012 | 12/11/2012 | 12/11/2012 | P | PASS |
Mike Jordan
|
|
|
Shear Phone #: ###-#### >> Inspection requested via web by Kelly Perryman. Exterior shear and holdowns ok.
|
FIRE-Conference | 12/6/2012 | 12/7/2012 | 12/7/2012 | A | DONE |
Troy Cobbley
|
|
|
Kelly and I discussed the placement of smoke alarms in the resident rooms.
|
BLD-Wall Bracing | 12/5/2012 | 12/6/2012 | 12/6/2012 | A | FAIL |
Mike Jordan
|
|
|
Provide blocking at corridor walls, tighten all holdowns, re-nail all areas that were missed.
|
BLD-Framing/Rough-in | 12/5/2012 | 12/5/2012 | 12/5/2012 | P | NR |
Mike Jordan
|
|
|
Need Shear Inspection >> Inspection requested via web by Kelly Perryman
|
BLD-Foundation | 8/24/2012 | 8/27/2012 | 8/27/2012 | A | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####. South half stemwall ok.
|
BLD-Foundation | 8/22/2012 | 8/23/2012 | 8/23/2012 | A | PART |
Mike Jordan
|
|
|
dane Phone #: ###-####. Stemwalls north half only ok.
|
BLD-Footing | 8/17/2012 | 8/20/2012 | 8/20/2012 | A | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|