BLD-Final | 11/14/2012 | 11/14/2012 | 11/14/2012 | P | PASS |
Jim Sly
|
|
|
David Phone #: ###-####
|
DOC - Permit Finaled | 11/14/2012 | 11/14/2012 | 11/14/2012 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 9/25/2012 | 9/26/2012 | 9/26/2012 | P | PART |
Jim Sly
|
|
|
dave Phone #: ###-#### OK for Temp Occ C/N Waiting for some fixes for Select connections on rough sawn framing of Ext. patios and entrys. Eng. to provide stamped paperwork and calcs. Can final when framing insp and passed.
|
FIRE-Final Inspection | 9/19/2012 | 9/19/2012 | 9/19/2012 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 9/11/2012 | 9/11/2012 | 9/11/2012 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler permits addressed. Need the signage on the riser room door and the knox box mounted.
|
BLD-Conference | 8/16/2012 | 8/16/2012 | 8/16/2012 | P | DONE |
Jim Sly
|
|
|
dave Phone #: ###-#### Gave dave a list of required finals for Shell Core permit.
|
FIRE-Final Inspection | 8/16/2012 | 8/17/2012 | 8/16/2012 | A | CANC |
Troy Cobbley
|
|
|
Cancel per conversation with dave. To be rescheduled for next tueday.
|
BLD-Other | 7/27/2012 | 7/27/2012 | 7/27/2012 | P | DONE |
Jim Sly
|
|
|
Correction Notice Posted. Exterior heavy timber construction, not per approved plan. Re-submit revised plan, Engineering calcs etc. for approval. Do not proceed with any work beyond scope of work on cold shell building permit. Do not cover any interior walls prior to obtaining permits for tenant improvements and approvals from structural inspector.
|
BLD-Other | 7/26/2012 | 7/27/2012 | 7/27/2012 | A | CANC |
Jim Sly
|
|
|
Dave Phone #: ###-####
|
BLD-Energy code compliance | 6/4/2012 | 6/4/2012 | 6/4/2012 | P | PART |
Jim Sly
|
|
|
dave Phone #: ###-#### Brewery only.......OK
|
BLD-Framing/Rough-in | 6/1/2012 | 6/1/2012 | 6/4/2012 | P | PASS |
Jim Sly
|
|
|
Dave phone
|
BLD-Framing/Rough-in | 5/31/2012 | 5/31/2012 | 6/1/2012 | P | CANC |
Jim Sly
|
|
|
Dave Phone #: ###-#### Re-sched.....
|
BLD-Framing/Rough-in | 5/29/2012 | 5/29/2012 | 5/29/2012 | P | PART |
Jim Sly
|
|
|
dave Phone #: ###-#### Shear OK South wall only.
|
BLD-Framing/Rough-in | 5/24/2012 | 5/24/2012 | 5/24/2012 | P | PART |
Jim Sly
|
|
|
Shear inspection please--Dave Phone #: ###-#### West wall......OK.
|
BLD-Foundation | 5/22/2012 | 5/23/2012 | 5/23/2012 | A | PASS |
Jim Sly
|
|
|
###-#### Dave phone
|
BLD-Footing | 5/22/2012 | 5/22/2012 | 5/22/2012 | P | CANC |
Jim Sly
|
|
|
dave Phone #: ###-#### Re-sched......
|
BLD-Framing/Rough-in | 5/21/2012 | 5/21/2012 | 5/21/2012 | P | CANC |
Jim Sly
|
|
|
Dave Phone #: ###-####
|
BLD-Wall Bracing | 5/21/2012 | 5/21/2012 | 5/21/2012 | P | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### Nailing of Exterior. North Wall only......OK.
|