Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD12-00801
StatusFinaled
Name K2 CONSTRUCTION
Site Address 2777 S ORCHARD ST
Project NameDENNIS DILLON GMC
Customer Number 
ePlanReviewNo
Description
(DENNIS DILLON - GMC SHOWROOM REMODEL) This building does not have a fire sprinkler system. To remodel an existing 8,934 square foot vehicle showroom building. Work is to include 2 restrooms upgraded to be accessible to the disabled, a “high” and “low” drinking fountain, new exterior windows and doors, interior finishes, and exterior finishes. The new exterior wall finish veneer will be aluminum composite panels with a thermoplastic polyethylene core. The wind design for the exterior aluminum composite panels is a deferred submittal item. Structural work includes a new entry element arch with concrete footings and concrete pedestals. The design for the above grade portion of the entry element arch is a deferred submittal item. In addition, most of the parapet around the perimeter of the lower roof will be raised about 6 feet and braced back to the existing roof with a steep sloped roof structure. A new roof covering and roof drains will be installed. Special Inspection is required for welding, bolting, concrete, epoxy anchors, and soil. The work is required to comply with the approved drawings, with the structural calculations, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/17/20143/19/20143/19/2014APASS
DetailsTom Arcoraci
julio Phone #: ###-#### ok for perm occ
BLD-Aging Inspection1/31/20141/31/20141/31/2014 PEND
DetailsTom Arcoraci
BLD-Aging Inspection11/11/201311/11/201311/12/2013 PEND
DetailsTom Arcoraci
temp
BLD-Aging Inspection9/11/20139/11/20139/13/2013 PEND
DetailsTom Arcoraci
BLD-Final7/11/20137/12/20137/12/2013PPART
DetailsTom Arcoraci
Julio Phone #: ###-#### Pending ELE sign off
FIRE-Final Inspection7/11/20137/12/20137/12/2013APASS
DetailsTroy Cobbley
Life safety passed. Contractor to remove the thumbturn on the main exit prior to the building inspection.
Extend Permit 90/180 days7/12/20137/12/20137/12/2013APASS
DetailsTom Arcoraci
Julio Phone #: ###-####
BLD-Framing/Rough-in3/18/20133/19/20133/19/2013PPASS
DetailsTom Arcoraci
julio Phone #: ###-####
BLD-Framing/Rough-in3/4/20133/5/20133/5/2013PPASS
DetailsTom Arcoraci
Julio Phone #: ###-####