BLD-Final | 10/9/2013 | 10/9/2013 | 10/9/2013 | A | PASS |
Tom Arcoraci
|
|
|
Per Bob's request please doc final
|
DOC - Permit Finaled | 10/9/2013 | 10/9/2013 | 10/9/2013 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 10/2/2013 | 10/2/2013 | 10/2/2013 | P | PART |
Bob Archibald
|
|
|
Walk through with electrical on outstanding issues remaining prior to issuance of a Final inspection/CO. Electrical corrections required and future space identified on plans will have electrical work added to current electrical permit foradjacent tenant expansion.
|
FIRE-Final Inspection | 9/26/2013 | 9/27/2013 | 9/27/2013 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 9/25/2013 | 9/25/2013 | 9/25/2013 | P | FAIL |
Troy Cobbley
|
|
|
Provide single action hardware on the pump room doors and provide annual inspections for all of the fire extinguishers. Front door meets requirements for locking hardware though panic is shown. The rear combustible ramp is under 4' in width so it meets the non-sprinkler exception. Exit signs and emergency lights functioned correctly.
|
BLD-Conference | 9/23/2013 | 9/23/2013 | 9/23/2013 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 8/5/2013 | 8/5/2013 | 8/5/2013 | P | PART |
Tom Arcoraci
|
|
|
meet with bob at site needs to return handrails then ok for final when all others have signed
|
BLD-Conference | 6/6/2013 | 6/6/2013 | 6/7/2013 | P | PASS |
Tom Arcoraci
|
|
|
ramp near completion
|
BLD-Conference | 6/5/2013 | 6/6/2013 | 6/6/2013 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Conference | 6/5/2013 | 6/5/2013 | 6/6/2013 | P | CANC |
Tom Arcoraci
|
|
|
Check status of project, no call for inspections.
|
BLD-Other | 4/15/2013 | 4/15/2013 | 4/15/2013 | P | PART |
Tom Arcoraci
|
|
|
Verified ADA ramp slope is less then 1:12
|
BLD-Footing | 3/25/2013 | 3/26/2013 | 3/26/2013 | A | PASS |
Tom Arcoraci
|
|
|
Amanda Phone #: ###-####
|
BLD-Conference | 3/5/2013 | 3/5/2013 | 3/5/2013 | A | PEND |
Tom Arcoraci
|
|
|
No work in progress. New contractor "John" is oredering materials and preparing for wall cut of new door opening. Work scheduled to begin ~2 weeks.
|
BLD-Conference | 12/14/2012 | 12/14/2012 | 12/14/2012 | P | PEND |
Tom Arcoraci
|
|
|
No work in progress. Requested schedule on work from Chris as work was to be completed prior to this date per letter from Jenifer.
|