BLD-Final | 8/16/2013 | 8/16/2013 | 8/16/2013 | P | PASS |
Tony Young
|
|
|
|
DOC - Permit Finaled | 8/16/2013 | 8/16/2013 | 8/16/2013 | P | PASS |
Tony Young
|
|
|
c of c/o issued
|
BLD-Final | 6/27/2013 | 6/28/2013 | 6/28/2013 | P | DONE |
Tony Young
|
|
|
trent Phone #: ###-####
|
BLD-Energy code compliance | 12/4/2012 | 12/5/2012 | 12/5/2012 | A | PASS |
Tony Young
|
|
|
Trent Phone #: ###-####,, house ok
|
BLD-Framing/Rough-in | 12/3/2012 | 12/3/2012 | 12/3/2012 | P | PASS |
Jim Sly
|
|
|
Trent Phone #: ###-####
|
BLD-Foundation | 7/27/2012 | 7/30/2012 | 7/30/2012 | A | PART |
Tony Young
|
|
|
Trent- after 9 Phone #: ###-####,, garage foundation monolithic ok,,, work in progress,, ok to pour when ready
|
BLD-Conference | 7/11/2012 | 7/11/2012 | 7/11/2012 | A | PASS |
Tony Young
|
|
|
Work has been authorized and may continue on garage after conference with legal and director. Original North and West walls toppled by wind may be reinstalled on sill plates. No other work authorized under current Stop Work Order.
|
Stop Work Order | 6/26/2012 | 6/26/2012 | 6/26/2012 | | DONE |
Tony Young
|
|
|
Stop Work Order issued for exceeding scope of work.
|
BLD-Foundation | 5/30/2012 | 5/30/2012 | 5/30/2012 | P | PART |
Tony Young
|
|
|
request late PM//Trent Phone #: ###-#### basement foam block walls work in progress
|
BLD-Footing | 5/15/2012 | 5/15/2012 | 5/15/2012 | P | PART |
Tony Young
|
|
|
Trent Phone #: ###-#### //concrete at 1pm, house footings,, basement
|