FIRE-Final Inspection | 7/23/2012 | 7/23/2012 | 7/23/2012 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 7/23/2012 | 7/23/2012 | 7/23/2012 | P | PASS |
Mike Jordan
|
|
|
Mic Phone #: ###-####. POK for per occ. once fire/life/safety signs perm.
|
FIRE-Final Inspection | 7/20/2012 | 7/20/2012 | 7/20/2012 | P | FAIL |
Troy Cobbley
|
|
|
The exit signs and emergency lights in the warehouse area need to be finished and tested. Plans need to be resubmitted showing the actual wall layout.
|
BLD-Final | 7/20/2012 | 7/20/2012 | 7/20/2012 | P | FAIL |
Mike Jordan
|
|
|
NICK Phone #: ###-####. Needs to submit plan mod showing the deletion of office and double doors. Also needs to have flusher on toilet installed on turning side. Provide special inspection report for racking and calll racking permit in for final. Ceiling grid ok to cover.
|
BLD-Framing/Rough-in | 7/2/2012 | 7/2/2012 | 7/2/2012 | P | PART |
Jim Storey
|
|
|
Please call before....... Phone #: ###-#### >> Inspection requested via web by Mick Davis pending ele ri// ok to cover walls upon aproval// c/n isued to have ceilling covered to meet class c smoke/flame spread requirments.
|
FIRE-Conference | 6/25/2012 | 6/26/2012 | 6/26/2012 | A | DONE |
Troy Cobbley
|
|
|
Vic phone #: ###-#### Questions on insulation facing at the deck were deferred to Tim in plan review.
|
FIRE-Conference | 6/25/2012 | 6/25/2012 | 6/25/2012 | P | DONE |
Forrest France
|
|
|
Please call prior -- Vic Phone #: ###-#### Conversation with contractor regarding IBC 719.1 and 719.3.
|