BLD-Final | 8/28/2013 | 8/28/2013 | 8/28/2013 | P | PASS |
Jim Sly
|
|
|
chris Phone #: ###-#### OK for Perm Occ.
|
BLD-Final | 8/14/2013 | 8/15/2013 | 8/15/2013 | P | PART |
Jim Sly
|
|
|
steve Phone #: ###-#### OK for Temp Occ. OK for Perm Occ. when Plumbing Perms.
|
BLD-Final | 8/14/2013 | 8/15/2013 | 8/15/2013 | A | PEND |
Jim Sly
|
|
|
Coordinate with fire if possible. Walk thru with superintendant.......Waiting for fire to sign off.
|
FIRE-Final Inspection | 8/14/2013 | 8/15/2013 | 8/15/2013 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Conference | 8/12/2013 | 8/12/2013 | 8/12/2013 | P | DONE |
Jim Sly
|
|
|
steve Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/7/2013 | 8/8/2013 | 8/8/2013 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. 2nd. Floor ceiling grid ok.
|
FIRE-Conference | 7/25/2013 | 7/26/2013 | 7/26/2013 | A | DONE |
Forrest France
|
|
|
needs clarification on something//Steve Phone #: ###-#### *Regarding existing door holds and a curtain wall not shown on the approved plans and set to be removed*
|
BLD-Other | 7/25/2013 | 7/25/2013 | 7/25/2013 | P | PASS |
Jim Sly
|
|
|
STEVE Phone #: ###-#### Southwest Shaft....2nd floor......OK
|
BLD-Other | 7/24/2013 | 7/25/2013 | 7/25/2013 | A | NR |
Jim Sly
|
|
|
smoke stop at floor-veritcal shaft-Steve Phone #: ###-####
|
BLD-Other | 7/11/2013 | 7/11/2013 | 7/11/2013 | P | PART |
Jim Sly
|
|
|
shaft insp//steve Phone #: ###-#### Select shafts....OK
|
BLD-Other | 7/10/2013 | 7/10/2013 | 7/11/2013 | P | NR |
Jim Sly
|
|
|
Floor assembly & shaft opening x2 - Steve Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/8/2013 | 7/8/2013 | 7/8/2013 | P | PART |
Jim Sly
|
|
|
steve Phone #: ###-#### Bsmnt. OK
|
FIRE-Conference | 6/24/2013 | 6/25/2013 | 6/24/2013 | A | DONE |
Troy Cobbley
|
|
|
Steve and I discussed covering sprinkler piping prior to a rough-in inspection. I was ok with some covering as long as there was easy access. Phone #: ###-####
|
BLD-Framing/Rough-in | 6/20/2013 | 6/21/2013 | 6/21/2013 | A | CANC |
Jim Sly
|
|
|
Steve phone ###-####
|
BLD-Ceiling Grid Inspection | 6/19/2013 | 6/20/2013 | 6/21/2013 | A | PART |
Jim Sly
|
|
|
Above ceiling - Steve Phone #: ###-#### 2nd floor soffits OK
|
BLD-Framing/Rough-in | 5/22/2013 | 5/22/2013 | 5/22/2013 | P | PART |
Jim Sly
|
|
|
STEVE Phone #: ###-#### Select walls, soffits and ceilings.
|
BLD-Other | 5/6/2013 | 5/6/2013 | 5/6/2013 | P | PASS |
Jim Sly
|
|
|
Parapet plywood wall - Dan Phone #: ###-#### Parapet walls and Framing in South East restrooms on main floor OK .
|
BLD-Other | 5/1/2013 | 5/1/2013 | 5/1/2013 | P | PART |
Jim Sly
|
|
|
steve Phone #: ###-#### Select soffit framing ....West end Basement.
|
BLD-Framing/Rough-in | 4/24/2013 | 4/25/2013 | 4/25/2013 | A | PART |
Jim Sly
|
|
|
Steve Phone #: ###-#### Exterior walls...Front entry area.....OK
|
BLD-Concrete | 4/18/2013 | 4/19/2013 | 4/19/2013 | A | CANC |
Jim Sly
|
|
|
Steve phone
|
BLD-Other | 4/18/2013 | 4/18/2013 | 4/18/2013 | P | PASS |
Jim Sly
|
|
|
rebar for piers and trash enclosure//Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 4/10/2013 | 4/11/2013 | 4/11/2013 | A | PART |
Jim Sly
|
|
|
steve - 2nd floor Phone #: ###-#### All framing 2nd floor OK except... West of Grid line 3.
|
BLD-Conference | 3/25/2013 | 3/26/2013 | 3/26/2013 | A | DONE |
Jim Sly
|
|
|
Steve ###-####
|
BLD-Framing/Rough-in | 3/25/2013 | 3/25/2013 | 3/25/2013 | P | PART |
Jim Sly
|
|
|
steve Phone #: ###-####
|
BLD-Framing/Rough-in | 3/18/2013 | 3/18/2013 | 3/18/2013 | P | PART |
Jim Sly
|
|
|
steve - this is not for the entry Phone #: ###-#### Select 1st floor and Basement walls.......OK.
|
BLD-Footing | 3/14/2013 | 3/14/2013 | 3/14/2013 | P | PASS |
Jim Sly
|
|
|
steve Phone #: ###-#### Pending MTI insp. tests and approvals. OK'd only to pour foundation for front entry.
|
BLD-Other | 2/26/2013 | 2/27/2013 | 2/27/2013 | A | PASS |
Tom Arcoraci
|
|
|
insp on fire rated plywood at parapet wall //Steve Phone #: ###-####
|
BLD-Footing | 2/22/2013 | 2/22/2013 | 2/22/2013 | P | CANC |
Jim Sly
|
|
|
Steve Phone #: ###-#### After I notified Steve that a plan modification for front entry and basketball/volleyball courts were submitted for approval by the City on 2/22/13, He cancelled inspection.
|