Permit Information
Permit NumberBLD12-01698
StatusFinaled
Name HC COMPANY INC
Site Address 11005 W FAIRVIEW AVE
Project NameNAPA AUTO PARTS
Customer Number 
ePlanReviewNo
Description
NAPA Automotive Parts Store - To construct a new 9,605 square foot, one story, automotive parts store and related site improvements. This building is constructed of masonry exterior walls with interior steel columns and steel roof joists and girders. The building will be fully fire sprinkled. The storage area in this building will contain a two level rack storage system. The racks were not reviewed under this permit. A separate racking permit will be required before the installation of the proposed racking system. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/30/20134/30/20134/30/2013PPASS
DetailsMike Jordan
contact 1/2 hr prior//Darren Phone #: ###-####. Ok for perm occ.
FIRE-Final Inspection4/26/20134/30/20134/30/2013APASS
DetailsTroy Cobbley
life safety passed
BLD-Conference4/25/20134/25/20134/25/2013PDONE
DetailsMike Jordan
please call 1/2 hr prior//Darren Phone #: ###-####
FIRE-Conference4/23/20134/23/20134/23/2013PDONE
DetailsTroy Cobbley
Darrin, myself and a gentleman from Enterprise Electric dicussed and agreed that emergency lighting, below the mezzanine would be modified from what has been installed. We agreed that three lights would be installed in each of the three long corridors and one light would be installed in the short corridors. This was decided after readings from a light meter.
FIRE-Conference4/19/20134/19/20134/19/2013PDONE
DetailsTroy Cobbley
darren and I discussed fire extinguisher placement, addressing, facp room signage and emergency lighting
BLD-Framing/Rough-in4/10/20134/10/20134/10/2013PPASS
DetailsMike Jordan
please call 30min prior - darrin Phone #: ###-####. Blocking added to framing for exterior sign at nw end of bldg as per approved plans.
BLD-Framing/Rough-in4/4/20134/9/20134/9/2013APART
DetailsMike Jordan
call 1/2 hr prior//Jason Phone #: ###-####. Exterior steel stud framing for signatnwcorner of building. Need RFI from engineer of record showing the strapping at 4ft. oc. in leiu of steel studs. Ok pending electrical ri inspection.
BLD-Energy code compliance1/17/20131/18/20131/22/2013APASS
DetailsJim Sly
Darren Phone #: ###-####
All framing OK
BLD-Framing/Rough-in1/16/20131/17/20131/17/2013APART
DetailsJim Sly
Darren-PLease call at least 30 mins prior to inspection Phone #: ###-####
Exterior walls OK to insulate.... Need to see Engineering for Rest room and mezzanine framing.
BLD-Conference11/27/201211/27/201211/27/2012PPASS
DetailsMike Jordan
Reviewed special inspection reports and all work that is in progress.
BLD-Other11/9/201211/9/201211/9/2012PPASS
DetailsTom Arcoraci
steve Phone #: ###-#### - rebar brad from mti on site 408