FIRE-Final Inspection | 1/13/2014 | 1/13/2014 | 1/16/2014 | P | PASS |
Forrest France
|
|
|
|
BLD-Final | 1/7/2014 | 1/10/2014 | 1/16/2014 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 1/7/2014 | 1/10/2014 | 1/10/2014 | A | PASS |
Forrest France
|
|
|
|
DOC - Permit Finaled | | | 12/19/2013 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/17/2013 | 12/18/2013 | 12/18/2013 | P | PASS |
Forrest France
|
|
|
Shell permit life safety inspection completed acceptable.
|
BLD-Final | 12/17/2013 | 12/18/2013 | 12/18/2013 | P | PASS |
Dave Hannah
|
|
|
Shell and Core Building Final Final with Dave Hannah, requested by Jamal, PM. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Final | 12/12/2013 | 12/16/2013 | 12/17/2013 | A | PART |
Dave Hannah
|
|
|
Stairwells & egress - Adam Phone #: ###-#### stairs towers ok
|
BLD-Final | 12/6/2013 | 12/13/2013 | 12/13/2013 | A | CANC |
Dave Hannah
|
|
|
AM inspection of Stairwells, per Jamal. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Other | 12/9/2013 | 12/12/2013 | 12/12/2013 | A | PART |
Dave Hannah
|
|
|
Penthouse final interior inspection per Jamal. Thursday AM. Thanks akj. Phone #: ###-#### >> Inspection requested via web by Adam Johnson penthouse ok
|
BLD-Final | 12/6/2013 | 12/11/2013 | 12/12/2013 | A | PART |
Dave Hannah
|
|
|
Final Inspection of Garage Levels 3, 4, and 5. Request per Jamal. Wed Dec 11th AM. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Final | 12/6/2013 | 12/12/2013 | 12/12/2013 | A | NR |
Dave Hannah
|
|
|
Inspection of core and shell interior signage, per Jamal. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Final | 12/6/2013 | 12/10/2013 | 12/11/2013 | A | PEND |
Dave Hannah
|
|
|
Final Shell and Core inspection of Electrical Rooms, per Jamal. AM Tuesday Dec 10th. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson walked elec rooms with jamal still needs to seal up pentations on three levels
|
BLD-Framing/Rough-in | 12/5/2013 | 12/5/2013 | 12/9/2013 | P | PART |
Dave Hannah
|
|
|
per dave hannah ceiling in alley ok to cover
|
BLD-Other | 11/22/2013 | 11/26/2013 | 11/27/2013 | P | PART |
Dave Hannah
|
|
|
Inspection request for Reflective tape in stairways. Requested by Jamal for PM, Thanks. akj Phone #: ###-#### >> Inspection requested via web by Adam Johnson thats instilled is ok I still need to check on several items.
|
BLD-Final | 11/22/2013 | 11/26/2013 | 11/27/2013 | P | PART |
Dave Hannah
|
|
|
Request to walk stairway 1 and 2, top to bottom, final inspection. PM inspection with Jamal. Thanks. Adam ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson walked stairs crews still working on them but doors and door hardware ok
|
BLD-Framing/Rough-in | 11/22/2013 | 11/22/2013 | 11/25/2013 | P | PASS |
Dave Hannah
|
|
|
Exterior Perimeter at 17th Floor, Shell and Core scope. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Other | 11/22/2013 | 11/25/2013 | 11/25/2013 | A | PASS |
Dave Hannah
|
|
|
Request by G&G Firestop assembly, alleyway, at Grid Line 6. Thanks. akj Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 11/19/2013 | 11/19/2013 | 11/20/2013 | P | PASS |
Dave Hannah
|
|
|
Adam Phone #: ###-####
|
BLD-Final | 11/14/2013 | 11/15/2013 | 11/15/2013 | A | PART |
Dave Hannah
|
|
|
Request for Final inspection of Shell and Core Basement scope of work. Requested by Jamal, AM, 10:30 if possible. Thanks, Adam. Phone #: ###-#### >> Inspection requested via web by Adam Johnson walked basement with Jamal four items to check on
|
BLD-Final | 11/12/2013 | 11/13/2013 | 11/13/2013 | A | PART |
Dave Hannah
|
|
|
Request for 10:30 Inspection of restrooms (shell and core)levels 11 to 17th with Jamal. Thanks, Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson restroom ada pass
|
BLD-Final | 11/6/2013 | 11/12/2013 | 11/12/2013 | A | CANC |
Tom Arcoraci
|
|
|
Request for 10:30 inspection of restrooms, (shell and core) levels 11 to 17th, with Jamal. Thanks. Adam ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Final | 11/1/2013 | 11/5/2013 | 11/6/2013 | A | PART |
Dave Hannah
|
|
|
Shell and Core Restroom Inspection Levels 1-10, Shell and Core Permit work. Jamal is requesting this for 10:30 AM. Phone #: ###-#### >> Inspection requested via web by Adam Johnson floors 1and 2 ok 6 thru 9 ada stalls only 59 inchs wide
|
BLD-Framing/Rough-in | 11/1/2013 | 11/5/2013 | 11/5/2013 | A | FAIL |
Dave Hannah
|
|
|
Wall perimeter inspection at 9th and 10th floor, exterior walls, core and shell scope of work, conformation of cover. Requesting in conjunction with 10:30 inspection of Shell and Core restrooms. Thanks. Adam ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 10/8/2013 | 10/10/2013 | 10/14/2013 | A | PEND |
Dave Hannah
|
|
|
Weekly Shell and Core inspection. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 9/30/2013 | 10/3/2013 | 10/4/2013 | A | PART |
Dave Hannah
|
|
|
Weekly Shell and core inspection. Phone #: ###-#### >> Inspection requested via web by Adam Johnson walked project with adam
|
BLD-Conference | 9/17/2013 | 9/24/2013 | 9/24/2013 | A | DONE |
Daryl Spivey
|
|
|
Meeting at 9:30 in construction office Phone #: ###-####
|
BLD-Conference | 8/26/2013 | 8/29/2013 | 8/29/2013 | A | DONE |
Dave Hannah
|
|
|
Weekly Core and Shell Inspection Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 8/19/2013 | 8/22/2013 | 8/23/2013 | A | PASS |
Dave Hannah
|
|
|
Weekly Inspection Walk, Core and Shell. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 8/12/2013 | 8/15/2013 | 8/19/2013 | A | PASS |
Dave Hannah
|
|
|
Weekly Inspection Walk, Core and Shell. Adam ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 8/5/2013 | 8/8/2013 | 8/9/2013 | A | DONE |
Dave Hannah
|
|
|
Weekly Inspection walk for Core and Shell. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 7/29/2013 | 8/1/2013 | 8/9/2013 | A | DONE |
Dave Hannah
|
|
|
Weekly Job Inspection Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 7/22/2013 | 7/25/2013 | 7/30/2013 | A | PASS |
Dave Hannah
|
|
|
Weekly Shell and Core inspection. Adam will be out, please check in with John, FCS, and Roger, ESI, ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 7/16/2013 | 7/18/2013 | 7/18/2013 | A | PASS |
Tom Arcoraci
|
|
|
Weekly inspectoin walk. Phone #: ###-#### >> Inspection requested via web by Adam Johnson will meet with dave later
|
BLD-Conference | 7/8/2013 | 7/11/2013 | 7/11/2013 | A | PART |
Dave Hannah
|
|
|
Weekly Inspection Request. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 6/24/2013 | 6/27/2013 | 6/27/2013 | A | CANC |
Dave Hannah
|
|
|
Weekly Inspection Walk. Adam ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 6/7/2013 | 6/13/2013 | 6/13/2013 | A | DONE |
Dave Hannah
|
|
|
Weekly Job Walk. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 6/11/2013 | 6/12/2013 | 6/12/2013 | A | CANC |
Dave Hannah
|
|
|
Inspection Requested for 16th Floor Restrooms. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 6/4/2013 | 6/5/2013 | 6/11/2013 | A | PART |
Dave Hannah
|
|
|
Rescheduled Thursday to Wednesday, Follow up on items from Tuesdays AM walk. Thanks. Phone #: ###-#### >> Inspection requested via web by Adam Johnson see sign off sheets
|
BLD-Conference | 6/3/2013 | 6/6/2013 | 6/4/2013 | A | CANC |
Dave Hannah
|
|
|
Weekly inspection walk. Phone #: ###-#### >> Inspection requested via web by Adam Johnson Inspection cancelled from web by: Adam Johnson
|
BLD-Conference | 5/24/2013 | 5/24/2013 | 5/24/2013 | A | PART |
Dave Hannah
|
|
|
Dave, Looking for the following Inspection Items: Meet with John Woods, FCS. Look at 11th Floor Perimeter, and confirm inspection at 10th Floor. Thanks. Adam Phone #: ###-#### see>> Inspection requested via web by Adam Johnson see sign off book for locations
|
BLD-Conference | 5/20/2013 | 5/23/2013 | 5/24/2013 | A | PART |
Dave Hannah
|
|
|
Weekly Job Inspection. Please contact Adam ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson see sign off book for locations.
|
BLD-Conference | 5/15/2013 | 5/16/2013 | 5/22/2013 | A | PART |
Dave Hannah
|
|
|
Weekley Inspection Walk. Phone #: ###-#### >> Inspection requested via web by Adam Johnson see sign off book
|
BLD-Conference | 5/6/2013 | 5/9/2013 | 5/9/2013 | A | PART |
Dave Hannah
|
|
|
Weekly Job Walk ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover restrooms south stairtower and outer wall of mec shafts floors 10 11 & 12
|
BLD-Conference | 4/29/2013 | 5/2/2013 | 5/6/2013 | A | PART |
Dave Hannah
|
|
|
Weekly Inspection ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to spray curtain wall fire safeing 7,8 and 9th floors
|
BLD-Conference | 4/17/2013 | 4/17/2013 | 4/22/2013 | A | PART |
Dave Hannah
|
|
|
Phone #: 2084841503 >> Inspection requested via mobile web by Adam ( ok to cover restrooms 1,2 and 6th floors)
|
BLD-Conference | 4/12/2013 | 4/18/2013 | 4/22/2013 | A | DONE |
Dave Hannah
|
|
|
AT ESI OFFICE 9AM meeting with ele,plm,mec,& fir inspectors
|
BLD-Conference | 4/12/2013 | 4/18/2013 | 4/18/2013 | A | DONE |
Troy Cobbley
|
|
|
Meeting AT ESI OFFICE with other inspectors to discuss the documentation of inspections
|
BLD-Conference | 4/12/2013 | 4/18/2013 | 4/18/2013 | A | DONE |
Troy James
|
|
|
meeting AT ESI OFFICE 9AM with David Hannah
|
BLD-Conference | 4/12/2013 | 4/18/2013 | 4/18/2013 | A | DONE |
Bob Reichert
|
|
|
meeting AT ESI OFFICE 9AM with David Hannah 327 did
|
BLD-Conference | 4/12/2013 | 4/18/2013 | 4/18/2013 | A | DONE |
Daryl Spivey
|
|
|
meeting AT ESI OFFICE 9AM with David Hannah meeting to coordinate consistency for recording inspections........ds
|
BLD-Conference | 4/8/2013 | 4/11/2013 | 4/17/2013 | A | DONE |
Dave Hannah
|
|
|
Weekly Inspection Walk. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 3/25/2013 | 3/28/2013 | 4/2/2013 | A | DONE |
Dave Hannah
|
|
|
Weekly Inspection. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 3/19/2013 | 3/21/2013 | 3/22/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2084841503 >> Inspection requested via mobile web by Adam
|
BLD-Framing/Rough-in | 3/12/2013 | 3/12/2013 | 3/21/2013 | A | PASS |
Dave Hannah
|
|
|
Contractors meeting and walk project.
|
BLD-Conference | 3/12/2013 | 3/14/2013 | 3/15/2013 | A | PART |
Dave Hannah
|
|
|
Weekly Inspection walk. Phone #: ###-#### >> Inspection requested via web by Adam Johnson walked floors basement to 13flr is plans in ESIs office for areas ok to cover.
|
BLD-Conference | 3/4/2013 | 3/7/2013 | 3/12/2013 | A | DONE |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Adam Johnson wolked project
|
BLD-Framing/Rough-in | 2/28/2013 | 2/28/2013 | 3/1/2013 | A | PART |
Dave Hannah
|
|
|
John check framing floors 12 to basement John and I walked floors he needs to seal up between framing and beams and floors inter layer of shaft wall before placing outer layers of sheetrock
|
BLD-Conference | 2/11/2013 | 2/14/2013 | 2/20/2013 | P | PART |
Dave Hannah
|
|
|
8th and Main Inspection Walk.BP2 Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 2/14/2013 | 2/14/2013 | 2/14/2013 | A | PART |
Dave Hannah
|
|
|
8th and Main Inspection Walk.BP2 Phone #: ###-#### >> Inspection requested via web by Adam Johnson walked floors 10 down to basement framing crews working on shafts stair towers elevators halls elec rooms ect shafts are ok crews have shaft board on inside and are two siding elec rooms still waiting on trades roughins
|