BLD-Final | 7/19/2013 | 7/22/2013 | 7/22/2013 | A | PASS |
Jim Sly
|
|
|
Brandon Phone #: ###-#### OK for Perm Occ.
|
BLD-Final | 7/2/2013 | 7/3/2013 | 7/3/2013 | A | PART |
Jim Sly
|
|
|
Brandon Phone #: ###-#### OK for Temp Occ. OK for Perm Occ when Zoning perms and when Final affidavit letter of approval is provided........including Stamp and signature from Engineer of record. This document to be archived.
|
FIRE-Final Inspection | 7/1/2013 | 7/2/2013 | 7/2/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 7/1/2013 | 7/1/2013 | 7/1/2013 | P | FAIL |
Troy Cobbley
|
|
|
Project was not quite ready for fire life safety but we verified all of the emergency light was funtional and found three light that did not work but two of which were repaired while I waited. We also went over fire dept access curb painting.
|
BLD-Framing/Rough-in | 5/6/2013 | 5/6/2013 | 5/7/2013 | P | PASS |
Jim Sly
|
|
|
Jeff Ceiling grid inspection please Phone #: ###-#### Ceiling grid pass.
|
BLD-Ceiling Grid Inspection | 4/24/2013 | 4/24/2013 | 4/24/2013 | A | PART |
Mike Jordan
|
|
|
North half, missing some clips. Will check on final. pending electrical rough in inspection.
|
BLD-Framing/Rough-in | 1/16/2013 | 1/16/2013 | 1/16/2013 | P | PART |
Jim Sly
|
|
|
Jeff Phone #: ###-#### Exterior shear wall....OK
|
BLD-Footing | 11/26/2012 | 11/27/2012 | 11/27/2012 | A | PART |
Jim Sly
|
|
|
Jeff Phone #: ###-#### North wall OK pending MTI insp, tests and approval.
|
BLD-Footing | 11/20/2012 | 11/21/2012 | 11/21/2012 | A | DEFR |
Mike Jordan
|
|
|
jeff Phone #: ###-####. Special inspector on site.
|
BLD-Foundation | 11/19/2012 | 11/20/2012 | 11/20/2012 | A | CANC |
Jim Sly
|
|
|
Jeff Phone #: ###-#### CANCELLED BY CONTR.
|
BLD-Foundation | 11/14/2012 | 11/15/2012 | 11/15/2012 | A | PART |
Jim Sly
|
|
|
Fauldation wall - Jeff Phone #: ###-#### South and West walls OK pending MTI insp, tests and approvals. MTI inspectors so far....Roy Green and Kevin Schroeder. Both verified as certified in thieir dicipline.
|
BLD-Foundation | 11/9/2012 | 11/13/2012 | 11/13/2012 | A | PART |
Jim Sly
|
|
|
Jeff Phone #: ###-#### Mti on site.
|
BLD-Foundation | 11/7/2012 | 11/8/2012 | 11/8/2012 | A | PART |
Jim Sly
|
|
|
pouring at 2 - Jeff Phone #: ###-#### East wall ....OK pend MTI insp,tests and approvals.
|