BLD-Final | 1/15/2013 | 1/15/2013 | 1/15/2013 | P | PASS |
Tom Arcoraci
|
|
|
BRIAN LATE AFTERNOON IF POSSIBLE Phone #: ###-####
|
FIRE-Final Inspection | 1/7/2013 | 1/8/2013 | 1/8/2013 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Conference | 12/31/2012 | 12/31/2012 | 12/31/2012 | P | DONE |
Troy Cobbley
|
|
|
Per Romeo Gervais, with the fire alarm functional, it is ok for the owner to begin stocking the store. Public is not allowed until the fire alarm permit has been finaled and the life safety signed off.
|
FIRE-Hydro test above ground | 12/31/2012 | 12/31/2012 | 12/31/2012 | P | CANC |
Troy Cobbley
|
|
|
Wrong inspection type requested.
|
BLD-Final | 12/27/2012 | 12/28/2012 | 12/28/2012 | P | PEND |
Tom Arcoraci
|
|
|
Brian Phone #: ###-#### ok to stock
|
FIRE-Final Inspection | 12/27/2012 | 12/28/2012 | 12/28/2012 | A | FAIL |
Troy Cobbley
|
|
|
Life safety is ok to final when the project related fire alarm permit is passed. Per Romeo it will be ok for the owner to stock if the fire alarm is inspected to verify that sprinkler and hvac monitoring is in place.
|
BLD-Ceiling Grid Inspection | 12/18/2012 | 12/18/2012 | 12/18/2012 | P | PASS |
Jim Storey
|
|
|
Brian Phone #: ###-####
|
BLD-Energy code compliance | 11/15/2012 | 11/16/2012 | 11/16/2012 | A | PASS |
Tom Arcoraci
|
|
|
brian Phone #: ###-####
|
FIRE-Conference | 11/15/2012 | 11/15/2012 | 11/15/2012 | P | DONE |
Troy Cobbley
|
|
|
Per Boise Fire Dept. request I left correction notice requiring the existing FDC at the east wall to meet NFPA 13 requirements for height above access level (18" to 4'). Contractor stated that it will be no problem since a new docking is going to be constructed under it.
|
BLD-Framing/Rough-in | 11/8/2012 | 11/8/2012 | 11/8/2012 | P | PASS |
Tom Arcoraci
|
|
|
nailing insp for roof//Derek Phone #: ###-####
|