Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD12-02399
StatusFinaled
Name KREIZENBECK CONSTRUCTORS
Site Address 4120 N EAGLE RD
Project NameBioLife Plasma Services
Customer Number 
ePlanReviewNo
Description
(BioLife Plasma Collection Center - Grading/Drainage & Utilities) Grading permit to grub, clean, excavate, grade, import and compact site earth materials in preparation for the future construction of a new building. To install curb, gutter and paving in accordance with the grading and drainage plans approved by the Public Works department. Related site utilities are included in this scope. NO CONSTRUCTION IS ALLOWED UNDRE THIS PERMIT. Reference DRH11-00131 for planning approval.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/25/20137/26/20137/25/2013APASS
DetailsJim Sly
brandon Phone #: ###-####
I got a verbal From Brian Murphy for the Public Works Final.
DOC - Permit Finaled7/25/20137/25/20137/25/2013PPASS
DetailsJim Sly
BLD-Final7/22/20137/23/20137/23/2013ANR
DetailsJim Sly
need to close out grading permit...you finaled the new building under Bld12-02045
Called Dave .........Told him to get Public Works final......... Then call for Erosion control and Structural final.
BLD-Ceiling Grid Inspection4/23/20134/24/20134/24/2013ACANC
DetailsMike Jordan
jeff Phone #: ###-####
BLD-Ceiling Grid Inspection4/17/20134/17/20134/17/2013PPART
DetailsJim Sly
jeff Phone #: ###-####
Select rooms...... OK
BLD-Framing/Rough-in2/28/20133/1/20133/1/2013APASS
DetailsJim Sly
jeff Phone #: ###-####
BLD-Framing/Rough-in1/10/20131/10/20131/11/2013PPART
DetailsJim Sly
Jeff phone
Engineer provided fix for cross bracing installed in 2pcs on shear panels. South 3rd of bldg OK to cover on exterior after fix.
BLD-Framing/Rough-in1/8/20131/9/20131/10/2013APEND
DetailsJim Sly
Jeff ###-####
Waiting for fix from Engineer of record for shear bracing.
BLD-Framing/Rough-in1/7/20131/8/20131/8/2013AFAIL
DetailsJim Sly
Jeff Phone #: ###-####
Structural engineer to OK cross bracing at shear panels.....in 2 pieces in lieu of 1 pc. If no approval....provide fix.
BLD-Footing11/6/201211/6/201211/7/2012PPART
DetailsJim Sly
Jeff Phone #: ###-####
East (wall) footing only OK pending MTI special inspection, tests and approvals.