BLD-Final | 7/25/2013 | 7/26/2013 | 7/25/2013 | A | PASS |
Jim Sly
|
|
|
brandon Phone #: ###-#### I got a verbal From Brian Murphy for the Public Works Final.
|
DOC - Permit Finaled | 7/25/2013 | 7/25/2013 | 7/25/2013 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 7/22/2013 | 7/23/2013 | 7/23/2013 | A | NR |
Jim Sly
|
|
|
need to close out grading permit...you finaled the new building under Bld12-02045 Called Dave .........Told him to get Public Works final......... Then call for Erosion control and Structural final.
|
BLD-Ceiling Grid Inspection | 4/23/2013 | 4/24/2013 | 4/24/2013 | A | CANC |
Mike Jordan
|
|
|
jeff Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/17/2013 | 4/17/2013 | 4/17/2013 | P | PART |
Jim Sly
|
|
|
jeff Phone #: ###-#### Select rooms...... OK
|
BLD-Framing/Rough-in | 2/28/2013 | 3/1/2013 | 3/1/2013 | A | PASS |
Jim Sly
|
|
|
jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 1/10/2013 | 1/10/2013 | 1/11/2013 | P | PART |
Jim Sly
|
|
|
Jeff phone Engineer provided fix for cross bracing installed in 2pcs on shear panels. South 3rd of bldg OK to cover on exterior after fix.
|
BLD-Framing/Rough-in | 1/8/2013 | 1/9/2013 | 1/10/2013 | A | PEND |
Jim Sly
|
|
|
Jeff ###-#### Waiting for fix from Engineer of record for shear bracing.
|
BLD-Framing/Rough-in | 1/7/2013 | 1/8/2013 | 1/8/2013 | A | FAIL |
Jim Sly
|
|
|
Jeff Phone #: ###-#### Structural engineer to OK cross bracing at shear panels.....in 2 pieces in lieu of 1 pc. If no approval....provide fix.
|
BLD-Footing | 11/6/2012 | 11/6/2012 | 11/7/2012 | P | PART |
Jim Sly
|
|
|
Jeff Phone #: ###-#### East (wall) footing only OK pending MTI special inspection, tests and approvals.
|