FIRE-Final Inspection | 9/27/2013 | 9/30/2013 | 9/30/2013 | A | PASS |
Forrest France
|
|
|
Remainder of fire life safety inspection items completed and passed.
|
FIRE-Final Inspection | 9/23/2013 | 9/24/2013 | 9/24/2013 | A | FAIL |
Troy Cobbley
|
|
|
This was just a conference for today. I noted that both smoke detectors at the door are not centered and one exceeds 5' from the door. Unable to test the exit signs and emergency lights due to patients. All other items appear ok. Bob Phone #: ###-####
|
BLD-Final | 9/23/2013 | 9/24/2013 | 9/24/2013 | A | PASS |
Tom Arcoraci
|
|
|
Bob Phone #: ###-####
|
FIRE-Final Inspection | 8/2/2013 | 8/5/2013 | 8/5/2013 | A | PART |
Troy Cobbley
|
|
|
The Prep/Rec rooms and the west entry life safety has passed.
|
BLD-Ceiling Grid Inspection | 7/25/2013 | 7/26/2013 | 7/26/2013 | A | PASS |
Tom Arcoraci
|
|
|
Bob Phone #: ###-####
|
FIRE-Conference | 6/25/2013 | 6/26/2013 | 6/26/2013 | A | DONE |
Troy Cobbley
|
|
|
Bob Wheeler and I discussed what I would need a cover inspection on.
|
BLD-Framing/Rough-in | 6/21/2013 | 6/24/2013 | 6/24/2013 | A | PASS |
Tom Arcoraci
|
|
|
Bob Phone #: ###-#### wip ok
|
FIRE-Final Inspection | 5/23/2013 | 5/24/2013 | 5/24/2013 | A | PART |
Troy Cobbley
|
|
|
Life safety is complete in the Clean Room and the Procedure Room
|