(SPRINGHILL SUITES) To remodel and renovate the lobby of an existing 66,322 square foot four story motel building. Work to include: remove an relocate some existing non-structural interior wall partitions; install new floor and wall finishes in compliance with chapter 8 of the 2009 IBC; replace existing lighting fixtures with new; plumbing and electrical work; and all other work per the approved drawings, the plan review report, and all applicable codes. A certificate of completion shall be issued when work is completed and a final inspection has occurred. NOTE: This building is fully fire sprinklered for area increase with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/9/20134/10/20134/10/2013APASS
DetailsJim Sly
Ed Anderson Phone #: ###-####
C/C issued.
DOC - Permit Finaled4/10/20134/10/20134/10/2013PPASS
DetailsJim Sly
FIRE-Final Inspection4/8/20134/9/20134/9/2013APASS
DetailsTroy Cobbley
Life safety passed. Sam in plan review was going to verify that the lever/thumbturn type locks on the ADA pocket doors is code compliant prior to the building inspection.
BLD-Final4/5/20134/8/20134/8/2013ANR
DetailsJim Sly
ed Phone #: ###-####
Need all fire finals.
FIRE-Sprinkler Rough-in1/8/20131/10/20131/10/2013ADONE
DetailsTroy Cobbley
Inspection was actually for a conference for Frank Matson. We discussed sprinkler issues due to a new wall. From information provided over the phone the pendant head is not too close to the wall at 8".
FIRE-Sprinkler Rough-in1/8/20131/10/20131/10/2013ACANC
DetailsTroy Cobbley
Duplicate inspection
BLD-Framing/Rough-in1/7/20131/8/20131/8/2013APASS
DetailsJim Sly
Phone #: 2082496859 >> Inspection requested via mobile web by Frank Matson
Advised Contractor to have fire inspector look at sprinkler head placement prior to cover.